UNITED STATES NUCLEAR REGULATORY COMMISSION Mr. Oliver 0. Kingsley, President Nuclear Generation Group Commonwealth Edison Company Executive Towers West Ill 1400 Opus Place, Suite 500 Downers Grove, IL 60515 WAS.HINGTON, D.C. 20555 0001 August 27, 1998
SUBJECT:
EVALUATION OF PURGE AND VENT STRATEGY FOR PRIMARY CONTAINMENT HYDROGEN CONTROL AT DRESDEN AND QUAD CITIES NUCLEAR POWER.
STATIONS (TAC NOS. M94843, M94844, M94845 AND M94846)
By letter dated February 16, 1996, Commonwealth Edison Company (ComEd, the licensee) notified the NRC staff that they had chosen the purge and vent strategy described in the Boiling Water Reactor Owners' Group Emergency Procedure Guidelines, Revision 4 (EPG-Rev 4) for the Dresden and Quad Cities Nuclear Power Stations rather than the purge/repressurization strategy that was previously reviewed by the staff. The NRC staff has reviewed this change and concludes that the Dresden and Quad Cities facilities satisfy the criteria of Generic Letter 84-09 and that the nitrogen dilution capability provided allows ComEd to implement the purge and vent strategy recommended by EPG-Rev 4. This capability, along with ComEd's removal of the Air Containment Atmosphere Dilution (ACAD) system as a potential post-accident oxygen source, allows the staff to close TAC Nos. M94843, M94844, M94845 and M94846. Our safety evaluation (SE) is enclosed.
Docket Nos. 50-237, 50-249, 50-254, 50-265
Enclosure:
. cc w/encl: See next page 9809240330*980827
- PDR * --ADOCK- 05000237 P
PDR fi~d2~
Robert M. Pulsifer, Project Manager Project Directorate 111-2 Division of Reactor Projects - Ill/IV Office of Nuclear Reactor Regulation fl 1 :
u--". :
~\\'1
- ,... )..
i Mr. Oliver D. Kingsley, President Nuclear Generation Group Commonwealth Edison Company Executive Towers West Ill 1400 Opus Place, Suite 500 Downers Grove, IL 60515 August 27, 1998
SUBJECT:
EVALUATION OF PURGE AND VENT STRATEGY FOR PRIMARY CONTAINMENT HYDROGEN. CONTROL AT.DRESDEN AND QUAD CITIES NUCLEAR POWER STATIONS {TAC NOS. M94843, M94844, M94845 AND M94846)
By letter dated February 16, 1996, Commonwealth Edison Company (ComEd, the licensee) notified the NRC staff that they had chosen the purge and vent strategy described in the Boiling Water Reactor Owners' Group Emergency Procedure Guidelines, Revision 4 (EPG-Rev 4) for the Dresden and Quad Cities Nuclear Power Stations rather than the purge/repressurization strategy that was previously reviewed by the staff. The NRC staff has reviewed this change and concludes that the Dresden and Quad Cities facilities satisfy the criteria of Generic Letter 84-09 and that the nitrogen dilution capability provided allows ComEd to implement the p*urge and vent
. strategy recommended by EPG-Rev 4. This capability, along with Com Ed's removal *of the Air Containment Atmosphere Dilution (ACAD) system as a potential post-accident oxygen source, allows the staff to close TAC Nos. M94843, M94844, M94845 and M94846. Our safety evaluation (SE) is enclosed.
Docket Nos. 50-237, 50-249, 50-254, 50-265
Enclosure:
SE cc w/encl: See next page DISTRIBUTION:
Docket File SRichards RP a Ila JKudrick PUBLIC RPulsifer CBerlinger M.Snodder1y Sincerely, ORIG. SIGNED BY Robert M. Pulsifer, Project Manager Project Directorate 111*2 Division of Reactor Projects - Ill/IV Office of Nuclear Reactor Regulation PD3-2 R/F CMoore ACRS THarris (SE)
EAdensam LRossbach OGC MRing, Riii DOCUMENT NAME: G:\\CM\\DRESDEN\\DQC94845.SE To receive a co of thl* document, Indicate In the box: *c*.,; Co without attactfm;;*nt/enc" sure OFFICE f!. PM:PD32
~ D:PD32 NAME LRossbac DATE OFFICIAL RECORD COPY
- 0. Kingsley Commonwealth Edison Company.
cc:
Michael I. Miller, Esquire Sidley and Austin
- One First National Plaza Chicago, Illinois 60603 Commonwealth Edison Company Site Vice President - Dresden 6500 N. Dresden Road Morris, Illinois 60450-9765 Commonwealth Edison Company.
Dresden Station Manager 6500 N. Dresden Road Morris, Illinois 60450-9765.. *
- U.S. Nuclear Regulatory Commission Dresden Resident Inspectors Office 6500 N. Dresden Road Morris, Illinois 60450-9766 William D. Leach Manager - Nuclear.
MidAmerican Energy Company 907 Walnut Street P.O. Box 657 Des Moines, Iowa 50303 Vice President - Law and Regulatory Affairs MidAmerican Energy Company One River Center Place 106 E. Second Street P.O. Box 4350 Davenport, Iowa 52808 Chairman Rock Island County Board of Supervisors 1504 3rd Avenue Rock Island County Office Bldg.
Rock Island, Illinois 61201 Dresden Nuclear Power Station Units 2 and 3 Quad Cities Nuclear Power Station Units 1and2 Regional Administrator
. U.S. NRC, Region Ill 801 Warrenville Road Lisle, Illinois 60532-4351 Illinois Department of Nuclear Safety Office of Nuclear Facility Safety 1035 Outer Park Drive Springfield, Illinois 62704 Chairman Grundy County Board Administration Building 1320 Union Street Morris, Illinois
- 60450
.Commonwealth Edison Company Site Vice President - Quad Cities 22710 206th Avenue N.
Cordova, Illinois 61242-9740 Commonwealth Edison Company Quad Cities Station Manager 22710 206th Avenue N.
Cordova, Illinois 61242-9740 U.S. Nuclear Regulatory Commission Quad Cities Resident Inspectors Office 22712 206th Avenue N.
Cordova, Illinois 61242 Document Control Desk-Licensing Commonwealth Edison Company 1400 Opus Place, Suite 400 Downers Grove, Illinois 60515 Mr. David Helwig Senior Vice President Commonwealth Edison Company Executive Towers West Ill 1400 Opus Place, Suite 900 Downers Grove, IL 60515
- 0. Kingsley Commonwealth Edison Company Mr. Gene H. Stanley PWR's Vice President Commonwealth Edison Company Executive Towers West Ill 1400 Opus Place, Suite 900 Downers Grove, IL 60515 Mr. Steve Perry BWR's Vice President Commonwealth Edison Company Executive Towers West Ill 1400 Opus Place, Suite 900 Downers Grove, IL 60515 Mr. Dennis Farrar Regulatory Services Manager Commonwealth Edison Company Executive Towers West Ill
.* 1400 Opus Place, Suite 500 Downers Grove, IL 60515 Ms. Irene Johnson, Licensing Director Nuclear Regulatory Services Commonwealth Edison Company Executive Towers West Ill 1400 Opus Place, Suite 500 Downers Grove, IL 60515 Commonwealth Edison Company Reg. Assurance Supervisor - Dresden 6500 N~ Dresden Road
- Morris, Illinois 60450-9765 Commonwealth Edison Company Reg. Assurance Supervisor - Quad Cities 22710 206th Avenue N.
Cordova, Illinois 61242-9740 Dresden Nuclear Power Station Units 2 and 3 Quad Cities Nuclear Power Station Units 1and2 Mr. Michael J. Wallace Senior Vice President Commonwealth Edison Company Executive Towers West Ill 1400 Opus Place, Suite 900 Downers Grove, IL 60515