ML17187B041

From kanterella
Jump to navigation Jump to search
Insp Repts 50-237/97-10 & 50-249/97-10 on 970519-23. Violations Noted.Major Areas Inspected:Review of Licensee Performance,Including Evaluation of Effectiveness of Radiation Protection Program
ML17187B041
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 07/02/1997
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML17187B040 List:
References
50-237-97-10, 50-249-97-10, NUDOCS 9707080060
Download: ML17187B041 (16)


See also: IR 05000237/1997010

Text

U.S. NUCLEAR REGULATORY COMMISSION

Docket Nos:

Licenses No:

Reports No:

Licensee:

Facility:

Location:

Dates:

Inspectors:

Approved by:

9707080060 970702

PDR

ADOCK 05000237

G

PDR

REGION Ill

50-237; 50-249

DPR-19; DPR-25

50-237/9701 O(DRS); 50-249/9701 O(DRS)

Commonwealth Edison Company

Dresden Nuclear Station, Units 2 and 3

6500 N. Dresden Road

Morris, IL 60450

May 19-23, 1997

R. Paul, Senior Radiation Specialist

R. Glinski, Radiation Specialist

Gary L. Shear, Chief, Plant Support Branch 2

Division of Reactor Safety

EXECUTIVE SUMMARY

Dresden Generating Station, Units 2 & 3

NRC Inspection Reports 50-237/97010; 50-249/97010

This announced inspection included a review of the licensee's performance,

specifically an evaluation of the effectiveness of the radiation protection program.

Three violations of NRC requirements were identified, one concerning inadequate

high radiation area (HRA) controls,. another concerning the lack of an evaluation to

determine radiological conditions in an area in which a person received an intake of

radioactive material, and one which involved the failure to meet a station training

requirement.

A self revealing event occurred where two workers could not exit from a

posted and controlled HRA because a contract radiation protection

technician (APT) failed to erisure all workers were out of the HRA before

locking the door allowing egress. The dose rates in the room in which there

was no egress were less than one mrem per hour (Violation Nos. 50-

237 ;249-97010-01 (DRS) (Section R1 .5).

A self revealing event in which a worker received a slight intake of

radioactive material occurred because the licensee failed to perform an

evaluation of the radiological conditions in the area he was working. The .

investigation/assessment of the event identified several weaknesses and

poor worker performance. The immediate corrective actions were

appropriate (Violation Nos. 50-237;249-97010-02(DRS)) (Section R1 .6).

The overall RP training program was well implemented. A violation was

issued for the failure to follow a training procedure related to initial training

on a new instrument (Violation Nos. 50-237;249-97010-03(DRS).

Refueling outage dose (D3R14) was well controlled. Rework, which had

been a cause of significant dose during previous outages, was reduced. The

station's improved work process program radiologi~al controls, and ALARA

initiatives were instrumental in reducing rework and outage dose.

Conservative actions were taken for all work where the potential for alpha

airborne contamination was possible (Section R1 .2).

With the exception of some discrepancies noted with the calibration and test

results of alpha monitoring equipment, the overall calibration and test

program for alpha monitoring, the whole body frisker, the whole body

counter and tool monitoring equipment was well implemented (Section

R1 .4) .

Report Details

Plant Support

R 1

Radiological Protection and Chemistry (RP&C) Controls

R 1 . 1

Control of Radioactive Materials and Radiological Surveys

a.

Inspection Scope (83750)

The inspectors reviewed the control of radioactive materials and the posting of

radiological hazards within the radiologically controlled area (RCA) and RCAs

outside the power block. The inspectors made frequent tours of the radiologically

posted areas and reviewed radioactive material labelling and radiological postings.

b.

Observations and Findings

During these tours, the inspectors noted good control and labelling of radioactive

materials. The inspectors found high and very high radiation areas to be posted and

controlled in accordance with NRC requirements.

During one tour of the reactor buildings, the inspectors noted discrepancies

between some areas which had postings identifying "no loitering, high radiation

field" signs and other areas with about the same general radiation field levels that

did not have similar postings. The inspectors further noted that the licensee did not

have any specific criterion to be used for posting of areas with elevated dose rates.

This matter will be reviewed by the licensee who intends to develop guidelines

concerning posting of those areas. Verification of radiation levels in the reactor

buildings was performed and the inspectors found they were comparable to those

posted.

c.

Conclusions

Tours of the RCA and outside the power block identified that, with the exception of

elevated dose rate area discrepancies inside the reactor building, that areas were

properly posted and that radioactive material was properly controlled.

R1 .2

Unit 3 Outage Dose Control and ALARA Implementation

a.

Inspection Scope (83750)

The inspector reviewed the licensee's radiological controls, dose reduction/ALARA,

and work practices for the D3R 14 refueling outage. The inspection consisted

primarily of in-plant observations, attendance at pre-job meetings, review of records

(ALARA plans, radiation work permits (RWPs), work packages, etc), discussions

with workers and discussions with members of the work control groups. The

following high dose jobs were observed in progress (either remotely or on location):

2

b.

.,

reactor water cleanup (RWCU) system pipe replacement

RWCU removed pipe and heat exchanger shipping activities

removal of waste activities associated with the RWCU

refuel floor work activities.

aspects of the control rod drive (CAD) removal activities.

Valve work activities

Drywell work activities

Observations and Findings

During a recent NRC maintenance team inspection of work activities during D3R 14

it was found that the licensee effectively implemented ALARA controls. The

findings of the inspection are documented in Inspection Report Nos. 50-10/97007,

50-237 /97007, and 50-24 7 /97007. During that inspection it was noted that

ALARA tools implemented for the outage included the use of additional shielding,

RWCU chemical decontamination, and the incorporation of lessons learned from

previous outages which effectively mitigated the effects of the increased dose

rates. In addition, major outage activities were assigned a manager/overseer who

was responsible for developing and implementing the ALARA plans and for ensuring

effective radiological controls were used, good oversight by radiation protection

personnel and sufficient coordination between working groups occurred, and that

there were good radiological controls established for Unit 3 drywell, RWCU, and

refuel floor work activities.

As of May 23, 1997, the licensee had accrued about 180 rem with about eighty

five percent of the scheduled work completed. At that point the overall outage

dose was expected to meet the revised goal of 245 rem. The dose goals were

based on previous similar work and included the dose for added work scope,

rework, and emergent work of about 30 percent of the projected dose, most of

which was due to added scope. The added scope was due primarily to work that

was found to be required after post shut down surveillances were performed,

. however, there appeared to be sufficient planning and preparation time to provide

RP input and implement ALARA initiatives before the added work began. The

licensee's efforts to reduce the amount of rework which contributed to significant

station dose during previous outages, were effective during D3R 14. Contingencies

w.ere in place for the major dose producing jobs and RP was involved in the planning

process.

The inspectors observed that the RP department maintained close oversight of

outage tasks and dose was effectively controlled as a result. Although there were

some observations of persons loitering and of poor radworker practices (Inspection

3

c.

Report Nos. 50-10/97007, 50-237197007, and 50-249/97007), there was

considerable improvement from previous outages.

Roles and responsibilities of individuals were clearly discussed at the pre-job

meetings and special instructions were prepared for those jobs observed by the

team. The RP staff clearly communicated RWP requirements, dose and dose rate

alarms, and radiological hold points. In general, the inspectors observed good

radiation worker (radworker) practices and workers properly donned and removed

protective clothing and demonstrated a good knowledge of electronic dosimetry

alarm setpoints. The licensee provided additional support at the Drywell step-off-

pads which were effective in improving worker performance and correcting errors.

Workers demonstrated good awareness of radiological conditions and appropriate

use of low dose waiting areas.

The inspectors also noted that because the licensee found alpha contamination on

smears taken in the Unit 3 main steam top valve and some other areas, it

implemented conservative actions for all work in those areas and on certain

systems. Increased air samples and smears were taken for condenser work, main

steam line valve (MSIV) work in the X area, drywell MSIV work, isocondenser work,

and high pressure cooling injection (HPCI) work. ALARA/Total Effective Dose

Equivalent (TEDE) reviews were performed and respirators were worn until

conditions existed such that it would not be ALARA/TEDE to wear them. In

addition the inspectors found that the licensee has been aggressive in, identifying

those areas of the station with the highest probability for alpha contamination, in

identifying the alpha isotopes, and in developing a program to reduce and control

the alpha contamination.

Conclusions

The licensee's measures to control Unit 3 outage (D3R14) dose were effective. The

licensee effectively used past outage work critiques to apply lessons learned to

existing work. Rework, which had troubled the station during previous outages was

markedly reduced through better planning, supervisory oversight, and work control.

During outage work evolutions, workers generally demonstrated good radiological

practices, and aggressive measures to control the potential for alpha radiation

airborne activity, were taken. Pre-job ALARA meetings ensured workers were

aware of radiological requirements, and specific work contingencies.

R1 .3

Radiation Work Practices

a.

Inspection Scope (83750)

The inspectors reviewed the licensees initiatives to prevent and control poor

radworker practices which had been a continuing problem, especially during

refueling work outages.

4

b.

Observations and Findings

The inspectors observed general radiation worker practices of those personnel

working in the Unit 3 drywell and the RWCU. Radiation worker practices observed

included, personal monitoring techniques, use of protective clothing, dosimetry

placement (thermolumenescent dosimetry (TLDs) and electronic dosimeters (EDs)),

ALARA practices (use of low dose zones, controlling crew size), working conditions,

understanding general and specific area dose rates and RWP requirements, and

station housekeeping.

c.

Conclusions

The inspectors found that other than the poor radiation work practices that were*

observed and documented in Inspection Report Nos. 50-10/97007, 50-237197007,

and 50-249/97007, radworker practices have generally improved from those noted

during previous outages. Initiatives such as the greeter program, increased

emphasis on worker responsibility, first line supervisory oversight, and stronger RP

control point oversight were instrumental in reducing poor radworker practices.

R1 .4 . Facilities and Equipment

a.

Inspection Scope (83750)

The inspectors reviewed the operation and calibration methodology for the whole

body friskers, tool monitors, and the portable alpha counting detectors. The

inspection included a walk down of the whole body friskers, independent testing of

whole body frisker and tool monitor alarms and set points, observation of

radioactive source condition, and review of procedures, detector operability history,

and calibration and test results.

b.

Observations and Findings

The calibrations and instrument tests were performed as required. Frisker alarms

were nominally set at about 5000 dpm with detector efficiencies at about 10 to 15

percent. The gamma portal whole body frisker can detect down to about 50

nanocuries cobalt-60 at about a 90 percent confidence level. Calibration and test

methodology is technically sound for all detectors inspected, and availability of

monitors is high, running at about 90 percent. Several new whole body friskers

were noted to be onsite but were not yet operable. The purchase of the monitors is

part of a long term program to generally upgrade radiation monitoring equipment.

The licensee hired a contractor to review and upgrade calibration procedures for all

portable hand held detectors. The inspectors found that several of the alpha

standards appeared degraded; the licensee was aware of those conditions and new

standards (alpha and beta-gamma) had been ordered. There did not appear to be

any significant difference between the observed and expected output of the

degraded standards.

Several discrepancies were found in the alpha counting equipment calibration and

5

Several discrepancies were found in the alpha counting equipment calibration and

maintenance program logs. The inspectors noted that the record for one of the

alpha detectors showed about a 50 percent different detection efficiency using one

calibration source compared to the use of others. The inspectors subsequently

learned that the licensee had previously observed the same discrepancy, and as a

result identified and disposed of a defective alpha source. The licensee's

investigation of this matter found that the defective source had not been

electroplated and was producing about one half of its original radioactive output,

which in this case resulted in a conservative error. The inspectors had not observed

similar defective sources during the inspection.

c.

Conclusions

Several equipment calibration and maintenance program log discrepancies and an *

error in the use of an alpha calibration source were identified. However, the overall

calibration and maintenance program for those monitors reviewed was well

implemented, and the monitors were noted to have good operability history.

R 1 . 5

High Radiation Area Event

a.

Inspection Scope (83750)

The inspectors reviewed the circumstances associated with a self revealing event in

which workers were prevented from exiting a posted and controlled high radiation

area (HRA). The inspection included a review of the licensee's investigation, and a

review of applicable procedures and documentation.

On April 21, 1997, electrical maintenance (EM) personnel were working in the Unit

2 drywall, which was designated as a locked high radiation area (LHRA). The

entrance and egress into the drywall was through the personnel hatch which was

accessible only through the drywall anteroom. During normal operation the drywall

personnel hatch is posted as a very high radiation area (VHRA) and locked.

Because Unit 2 was in a forced outage, the controls were removed from the

personnel hatch and the door leading into the anteroom was posted as a LHRA and

controlled with a lock. On April 1, the anteroom was unlocked while the EMs were

performing their work and a RPT was assigned to perform duties as the LHRA

attendant. The attendant was responsible for ensuring all regulatory requirements

for HRA controls were implemented.

During the day, numerous entries into and out of the area were made. At about mid

afternoon, four of the EMs exited the area and the RPT thought they were the last

group of EMs working in the drywall. Based on a discussion the *RPT had with the

EMs, the RPT felt confident that everyone was out of the drywall. The RPT did not

enter the drywall to verify that all workers had left and after a few minutes he

placed the lock on the hasp of the door leading into the anteroom. The RPT then

left the area to find a person to verify that the anteroom door was locked. Shortly

after the RPT left the area another drywall worker tried to exit through the anteroom

door but was unable to because the door was locked from the outside. One of the

6

EMs who had exited the drywell earlier saw the lock on the door moving and

discovered two workers were locked inside the anteroom. After RP was informed

of this condition the door was unlocked and the workers left the area. Dose rates in

the anteroom were less than 1 mrem/hour. The workers were in the anteroom for

about 1 2 minutes and their personal exposure for the day was 37 mrem and 48

mrem, respectively. Failure to provide individuals an exit from the locked and

posted LRHA is a violation of 1 O CFR 20. 1601 (d) which requires that the licensee

establish the controls required by this section in a way that does not prevent

individuals from leaving a HRA. (Violation 50-2371249-97010-01)

The causes of the event included the failure of the RPT to ensure that all personnel

that entered the area exited the area, and the failure to establish a written log or

some other mechanism to track personnel entry into the LHRA; the RPT tried to

maintain a mental log of entries.

Corrective actions taken to prevent recurrence included the development of a

method to ensure tracking of personnel accountabiliW for LHRANHRA entries,

physical verification to ensure all personnel have exited from the HRAs, and a

station wide review of all HRAs to determine the status of accessibility for egress of

all HRAs.

c.

Conclusions

The inspectors concluded that the licensee's investigation and immediate corrective

actions were appropriate. Several problems were identified including, the RPT in

attendance failed to ensure there were no persons remaining in the drywell before

locking the door I and there was no mechanism in place to track workers entry and

egress from the HRA. A violation was identified for failure to allow egress from a

locked HRA.

R1 .6

Intake of Radioactive Material During Decontamination Work in the Unit 2 Torus

Basement

a.

Inspection Scope (83750)

The inspectors reviewed the circumstances surrounding a self revealing event in

which a worker had a intake of radioactive material during decontamination work in

the Unit 2 basement. The review consisted of interviewing workers involved in the

job, reviewing the licensee's preliminary investigation and reviewing applicable

procedures and documentation.

b.

Observations and Findings

On May 4, 1997, a contract station decon technician (CDT) was performing

decontamination activities in the trench area of Unit 2 torus bays 9 and 10 and part

of the non-trenched area of bay 11. The work consisted of wetting the material,

using a scraper and/or rags to remove the contaminated material, and then

7

collecting it into a plastic bag. The CDT wore protective clothing including vinyl

pants, double rubbers and gloves and safety eye glasses.

After completing the job, the worker alarmed a personnel contamination monitor at

the RP control point prompting an investigation by the licensee. The licensee's

evaluation concluded that the worker had received an intake of radioactive material

resulting in a committed effective dose equivalent (CEDE) of 5 mrem and a total

effective dose equivalent (TEDE) of 22 mrem. The inspectors independently

reviewed this evaluation and agreed with the dose estimate.

The inspectors independent review agreed with the licensee's conclusion that the

root cause was the failure to properly evaluate the job. Specifically, the contract RP

supervisor was aware of a 500,000 dpm/100 cm2 area in bay 11, but failed to

recognize that an ALARA briefing was procedurally required at these contamination

levels. The failure to perform this briefing, resulted in the licensee's failing to

consider additional controls for the job, including continuous RPT coverage, air

sampling or engineering controls. Additionally, the CDT used a routine survey map

which did not include surveys of the trenches in bays 9 and 10. Subsequent

surveys of these areas identified smear results ranging up to 1 . 5 million dpm beta-

gamma and 1,800 dpm alpha.

A significant contributing cause was poor communications between the contract RP

supervisor, CDT foreman, CDTs and contract RPTs. The contract RP supervisor

instructed the CDT foreman to decon the trench area of bay 11 in the Unit 2 torus

basement. However, the foreman instructed the CDTs to decon the trench areas in

bays 9 and 10 instead of bay 11. After the first CDT completed his inspection of

bays 9 and 10, he left to obtain a vacuum cleaner for the job, (the second CDT

never entered the torus for this inspection because he was the outman). At about

the time the first CDT left the area and found that a vacuum cleaner was not

available, he was removed from the job and reassigned to perform fire watch duties.

Subsequently, the second CDT was assigned to the torus job, but without receiving

a turnover from the first CDT. Because there was no RPT control point in Unit 2,

the second CDT discussed this job with an RPT at the Unit 3 control point.

Although this RPT was unfamiliar with the Unit 2 basement conditions and was not

told by the CDT of the job specifics, the RPT did not question the CDT or

investigate the job. This evolution occurred without licensee oversight indicating a

weakness in the control of contractor activities.

Poor communication was a contributing cause for a previous violation for a similar

event documented in Inspection Report Nos. 50-237/249/96009. Specifically, in

that event, the duty RP shift supervisor (RPSS) was not informed of the scope of

work activities and job scope changes. Although none of the corrective ac1ions for

this event would have prevented the torus decon event, the inspectors concluded

that the previous corrective actions were weak because they were not sufficiently

broad enough to prevent similar events from occurring. The licensee planned to

evaluate this observation during the development of corrective actions for this

event.

8

Immediate corrective actions for this event included instructing all RP and decon

personnel that evolutions performed in either unit that does not have a dedicated RP

control point, be discussed at the station RP desk.

The failure to perform an ALAR A review to evaluate the radiological hazards that.

could be present is a violation of 10 CFR 20. 1501, which requires that surveys be

conducted to ensure compliance with the regulations in part 20. Because an

ALARA review was not accomplished, the licensee did not perform a thorough

radiological survey of the actual work areas and did not evaluate other appropriate

ALARA controls to assure compliance with 10 CFR 20.1201(a)(1)(i), which limits

the total effective dose equivalent to 5 rems per year. (Violation

50-237 /249-97010-02)

c.

Conclusions

The licensee's weak oversight, worker's lack of familiarity and knowledge of station

requirements, and work conditions caused a personal intake. Contributing to the

root cause was poor communication and contact between all persons involved in

this event. One violation was identified for the failure to perform an adequate

survey to ensure 10 CFR 20. 1201 dose limits.

R4

Staff Knowledge and Performance in RP&C

R4. 1

Implementation of the Greeter Program

a.

Inspection Scope (83750)

The inspector interviewed RP staff, reviewed RP policies, and observed performance

regarding implementation of the greeter program during D3R14.

b.

Observations and Findings

In late 1996, the licensee initiated a greeter program to improve ALARA practices

by ensuring radworker understanding of radiological conditions in their specific work

areas and of station requirements for working in radiologically posted areas (RPAs).

The workers were challenged by personnel at the main access control points before

entering the RCA. For D3R 14, the station trained individuals with no nuclear

experience to function as greeters. These individuals received N-GET training and

instruction from ADM-10 . .The program was described in RP Policy Memo ADM-10,

Rev. 01.

The inspectors observed greeters at the main access control points and noted that

the greeters maintained a log of personnel that demonstrated insufficient

knowledge. Personnel refused entrance to the RPA by greeters were subsequently

denied access to the APA, and the access was restored only after a meeting with

RP management. The greeters generally quizzed workers from ADM-10 guidance.

However, the inspectors identified that the greeters were not routinely reminding

workers of high radiation area control responsibilities and the responsibility to return

9

the work area to the "as found" condition. The greeters stated that they had not

been instructed to ask these questions. The failure to train greeters to remind

workers of responsibilities for high radiation areas and housekeeping was contrary

to commitments made to the NRC in letters dated January 13 and February 26,

1997. RP management indicated that these commitments applied during plant

operation, but not outage activities. The inspector discussed with RP staff that the

letters did not state this restriction and RP stated that greeters would receive

instruction to challenge workers in these two issues.

The overall success of the greeter program was demonstrated by the fact that 70% *

( 114/153) of RP deficiencies identified in April 1997 were attributed to greeters.

Observation of greeter activities and interviews with RP staff further indicated that

radworkers were sufficiently aware of their responsibilities.

c.

Conclusion

The greeter program successfully identified numerous outage personnel who lacked

sufficient knowledge or preparation for work in the RPA. The inspectors observed

that greeters were not instructed to implement commitments made to the NRC and

this issue will be reviewed as an Inspection Follow-up Item. (IFI

50-237,249/97010-04)

RS

Staff Training and Qualification in RP&C

R5.1

Training for Contract Radiation Protection Technicians (CRPTs)

a.

Inspection Scope (83729)

The inspectors interviewed Professional Training Center (PTC) staff, contract

radiation protection technicians (CRPTs), and RP supervisors (RPS) regarding the

training and qualifications required for CRPTs working D3R 14. The inspectors also

reviewed training procedures, lesson plans, and records.

b.

Observations and Findings

The inspectors noted that the procedure for processing CRPTs (NRP 5000-4, Rev.

2) stated that prospective CRPTs should attend Core training, must pass a ComEd

approved Health Physics Theory Test (80%), and receive 80% or higher on the

standardized Northeast Utilities HP Theory Test. After On-the-Job (OJT) training

with RP instrumentation, the individuals were required to pass a radiation detection

meter reading test and successfully complete two survey scenarios, one of which

covered a routine RP survey and the other which addressed a personnel

contamination event.

The inspectors noted that the classroom training covered the practical aspeGtS of

over 60 CAPT activities. Then, OJT was conducted by both PTC and corporate

Com Ed staff. Training records indicated that prospective CRPTs received the full

training program in accordance with the PTC instructions prior to working in D3R 14.

10

The records also revealed a failure rate of 8% for prospective CRPTs, with most

failures occurring on the written tests. Individuals who failed the test were denied

employment at the station. Although documentation for each TPE failure was

required by PTC core training instructions, the PTC did not document the first TPE

failure.

Interviews with RPSs and CRPTs working in D3R14 indicated that the CAPT training

adequately prepared the workers for outage tasks. In addition to the tasks covered

in the PTC training, CRPTs were also trained for other instrumentation and tasks. A

CAPT qualification matrix was maintained by an outage coordinator to document

this information and to. ensure that only qualified CRPTs were assigned to specific

tasks.

c.

Conclusion

The training for prospective CRPTs was comprehensive and well implemented. One

discrepancy was noted in the training documentation.

R5.2

Continuing Training for Dresden RPTs

a.

Inspection Scope (83750)

The inspector interviewed training and RP personnel, and reviewed site training and

evaluation documentation regarding the APT continuing training program for new

instrumentation.

b.

Observations and Findings

Continuing APT training consisted of classroom instruction, OJT, and TPE. Within

the training program, a Radiation Protection Training Advisory Committee (APT AC),

composed of RP and training staff, met monthly to review training needs.

Regarding new instrumentation, classroom instruc.tion was optional, however, the

OJT and TPE are required.

The inspector reviewed lesson plans and instructions contained in the training

program. Training Department Instruction, "Conduct of On-the-Job Training and

Evaluation" (TDl-206, Rev. 10), stated that OJT and TPE are separate processes,

and that the evaluator is not to guide, prompt, or coach the trainee during TPE.

Interviews with training instructors and coordinators, evaluators, and RPTs indicated

that plant staff understood the distinction between OJT and TPE.

Review of training for new RP instrumentation indicated weaknesses in

. communication and documentation. Training records demonstrated that the initial

performance evaluations for the PASSPORTPersonal Alarm (which measures air

quality in confined spaces) were conducted from October 1995 to January 1996.

A review of training records for six RPTs revealed that only three of the training files

contained the sign-off sheets which showed successful completion of the training.

However, the Person Course History List from the Training Administration System

11

listed completed PASSPORT training only for the RPT files which did not have the

sign-off sheet. None of the training records had the PASSPORT information in the

training file and on computer file. This was a weakness in the recordkeeping for

completed training.

An evaluation conducted by the licensee regarding the initial PASSPORT training

determined the following:

The RPTAC meeting minutes for March 1995 failed to document the TAC's

intention that an evaluation phase be required for PASSPORT training, and

this failure to document the need for an evaluation provided RP trainers with

inadequate guidance;

Although electronic records indicated that RPTs received this training, the

lack of hardcopy PASSPORT evaluation records indicated that training staff

failed to complete the documentation required by TOI 702, "RPT Continuing

Training";

Eight of the nine RPTs interviewed by the licensee did not recall any

evaluation phase for PASSPORT training.

The licensee's evaluation concluded that the initial PASSPORT training consisted of

instruction and OJT, without any subsequent evaluation (TPE). The failure to

conduct an evaluation for the PASSPORT was contrary to TOI 206 (OJT Trainer and

Evaluator Qualification) which stated that evaluations of task performance must be

conducted .in a consistent and objective manner to ensure that the required

knowledge and skills have been acquired by the trainees. In addition, TOI 702

required that the training program structure include Performance Training which

evaluates the trainee's ability to actually perform a task. The failure to conduct

PASSPORT evaluations was a procedural violation of Training Department

Instruction (TOI) 206 which required evaluations of trainee task performance. The

licensee has subsequently conducted OJT and TPE for the PASSPORT in

accordance with training instructions. Although problems with PASSPORT training

were identified, no safety problems associated with the use of this instrument

occurred and the RPTs were confident in their ability to use the instrument.

(Violation 50-237 /249-97010-03).

The licensee evaluation further noted that although training for several other tasks

was conducted in accordance with TD ls and TAC review, the TAC did not review

training for the IPM-90 whole body monitor. Interviews indicated that RP staff

procured and trained RPTs to source' check the IPM-90 without the knowledge of

the training department. Subsequently, RPTAC minutes for December 20, 1996,

stated that all RPTs would be disqualified from the IPM-90 until the proper OJT/TPE

was completed.

This was another example of the communication weakness which

existed between the training and RP departments.

To improve the training program, the licensee is considering a task qualification

system rather than the current position qualified system. This would allow the plant

12

to qualify and disqualify RPTs for individual tasks rather than all tasks collectively.

In addition, RP management recently added Line Management Observation (LMO) to

the RPT training program. LMO consisted of first line RPSs accompanying RPTs

during performance of routine and non-routine tasks and evaluating the RPT

performance. To date, the RPS staff has not identified any adverse trends in RPT

performance.

c.

Conclusions

Although weaknesses were identified, the training department and RP staff

generally conducted continuing training for RPTs in accordance with station

practice$. One procedural violation was identified for failure to conduct evaluations

during the initial PASSPORT training. In addition, weaknesses in training

documentation and communication were identified.

RS

Miscellaneous RP&C Issues

R8.1

(Closed) Violation (50-237,249/96006-07(DRS), LER 96-010: failure to perform

'

Technical Specification required monthly analysis for tritium on the Unit 1 Main

Chimney, Units 2/3 Main Chimney, and Reactor Building Vent Stack samples. Due

to personnel error, the lack of an operational liquid scintillation counter, and an

inconsistent Pre-Define method to control sampling and analysis, the licensee failed

to complete the required monthly tritium analyses from June 1995 to May 1996.

The licensee analyzed the chimney and stack samples on June 20 and 21, 1996

and the 1995 Annual Radiological Environmental Operating Report and the

applicable Semiannual radioactive Effluent Release reports were revised. In

addition, the Pre-Define was revised to require completion of the analysis prior to

being signed and the analysis of the tritium samples was added to the Chemistry

Technician assignment sheet. This item is closed.

R8.2

(Closed) Violation 50-237;249/97010-03: failure to conduct Task Performance

Evaluations for initial PASSPORT training. Interviews with $taff and review of a

licensee evaluation and training records revealed that the initial training for the

operation of the PASSPORT Personal Alarm, conducted from October 1995 to

January 1996, did not include an evaluation phase. Evaluations of personnel were

required to ensure that the required knowledge and skills have been acquired by the

trainees.

Subsequently, the licensee trained plant RP staff on the use of the PASSPORT by

conducting the OJTffPE phases with the appropriate sign-offs. The inspector's

review of training records and interviews with staff showed that the PASSPORT re-

training was successfully conducted from December 1996 to February 1997. This

item is closed.

13

...

V. Management Meetings

X1

Exit Meeting Summary

On May 23, 1997, the inspectors presented the inspection results to licensee

management. The licensee acknowledged the findings presented.

The inspectors asked the licensee whether any materials examined during the

inspection should be considered proprietary. No proprietary information was

identified.

14

..

  • .

PARTIAL LIST OF PERSONS CONTACTED

Com Ed

M. Heffley, Station Manager

F. Spangenburg, Regulatory Assurance Manager

C. Howland, Radiation Protection Manager

J. Moser, ALARA Manager

L. Aldrich, Assistant RPM

J. Hill, Lead Radiation Protection Supervisor

M. Friedmann, Lead Health Physicist

J. Kuczynski, Internal Dosimetry Health Physicist

L. Jordan,

INSPECTION PROCEDURES USED

IP 83750:

Occupational Radiation Exposure

Opened

50-237;249/97010-01

50-237;249/97010-02

50-237;249/97010-03

50-2371249/97010-04

Closed

50-2371249-96006-07

50-2371249-97010-03

Discussed

None.

ITEMS OPENED, CLOSED, AND DISCUSSED

VIO

Failure to provide egress from a HRA (Section R1 .5)

VIO

Failure to provide an adequate evaluation (Section R1 .6)

VIO

Failure to follow requirements of training procedure

(Section R5. 1) *

IFI

Verify actions taken to ensure implementation of

commitments made to NRC (Section R4. 1)

VIO

Failure to complete the required monthly tritium analysis

for Units 1 ,2, 3 Chimney and Units 2/3 Reactor Building

stack samples from June 1995 to May 1996

VIO

Failure to conduct Task Performance Evaluations for

PASSPORT air quality monitor

15