ML17187A756

From kanterella
Jump to navigation Jump to search
Insp Repts 50-237/97-03 & 50-249/97-03 on 970114-23. Violations Noted.Major Areas Inspected:Maint & Engineering
ML17187A756
Person / Time
Site: Dresden  
Issue date: 02/06/1997
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML17187A754 List:
References
50-237-97-03, 50-237-97-3, 50-249-97-03, 50-249-97-3, NUDOCS 9702100369
Download: ML17187A756 (7)


See also: IR 05000237/1997003

Text

U.S. NUCLEAR REGULATORY COMMISSION

Docket Nos.:

License Nos.:

Report Nos.:

Licensee:

Facility:

Location:

Dates:

Inspector:

Approved by:

9702100369 970206

PDR

ADOCK 05000237

a

PDR

REGION 111

50-237; 50-249

DPR-19; DPR-25

50-237 /97003(DRS); 50-249/97003(DRS)

Commonwealth Edison Company

Dresden Generating Station, Units 2 and 3

6500 North Dresden Road

Morris, IL 60450

January 14 - 15, and 23, 1997

M. S. Holmberg, Reactor Inspector

Wayne Kropp, Chief

Engineering Specialists Branch 1

Division of Reactor Safety

Report Details

II. Maintenance

M2

Maintenance and Material Condition of Facilities and Equipment

M2.1 Torus Inspections

a.

Inspection Scope (73753. 73755. 73052)

Degradation of protective coatings on containment structures had recently been

observed at *other reactor sites. Therefore, the inspector performed a walkdown of

the exterior of the Unit 2 and Unit 3 torus and reviewed past internal visual

inspection results to assess the integrity and materiel condition of this portion of

the containment structure.

b.

Observations and Findings

External Suppression Chamber Walkdown

The inspector identified several external areas (typically patches less than six inches

by six inches) of the suppression chamber on both units with missing paint and

light corrosion, (mostly at thermoweil penetrations and vacuum breaker line support

pads). Additionally, the inspector identified a minor gouge on the Unit 3 torus at

Bay 13 (at approximately the 492 foot elevation) and on the Unit 2 torus at Bay 4

(at the 496 foot elevation). These gouges were estimated by the inspector to be

less than 1 /1 6 inch deep. The engineering staff initiated condition reports for these

conditions. Preliminary evaluation of the minor gouges and areas of missing paint

with light corrosion by vendor and licensee engineering staff, indicated that these

conditions were not structurally significant. The inspector reviewed procedure

DTS 1600-11 "Primary Containment Structure General and Coating Inspections"

Revision 04, issued on December 3, 1996, which included implementation of

American Society of Mechanical Engineers Code,Section XI, 1992 Edition,

Class MC requirements for inspection of the torus (including the exterior). Since

this procedure revision was recently issued, the inspector could not-assess the

effectiveness of this new procedure, however the inspector considered that periodic

inspection of the torus exterior would be expected to result in an improved materiel

condition.

The inspector identified a pump mounted in a skid that was bolted to the Unit 2

torus basement floor (4 76 foot elevation) at Bay 10. The system engineer stated

that this pump was used to pump down the torus (an infrequent event). The

inspector reviewed drawing M5 "General Arrangement Basement Floor Plan"

. Revision G, which did not identify this pump. Engineering staff could not identify

an engineering modification, drawing revision or other documentation that

authorized the permanent mounting of this pump at Bay 10. Additionally, a written

safety evaluation had not been performed for installation of this pump.

The

licensee located a purchase order, which indicated that this pump had been

purchased in 1984. The inspector postulated that if the mounting of this pump

was inadequate, a seismic event could free this pump and damage the torus

2

suppression chamber. The licensee performed a walkdown of the area where the

pump was installed and determined that no potential seismic concern existed and

stated that no unreviewed safety question existed. The licensee staff stated that

they intended to initiate a 50.59 safety evaluation for installation of this pump and

were considering removal of this pump. The inspector considered the installation of

a pump in the Unit 2 torus basement (476 foot elevation), to be a change to the

facility as described in the Updated Final Safety Analysis Report (UFSAR)

Section 6.2 "Containment Systems." The failure to perform a written safety

evaluation in accordance with 10 CFR 50.59(b)(1) for.the installation of this pump

is considered a violation (50-237/97003-01 (DRS)).

Review of Internal Suppression Chamber Inspections

The inspector reviewed the Final Engineering Report (FER) FER-7 209 "Torus

Underwater Desludging, Inspection and Coating Repair for ComEd Dresden Nuclear

Power Station, Unit 2" prepared by S. G. Pinney and Associates, Inc., and dated

August 29, 1995. This report documented the 1995 inspection results from an

internal inspection of the Unit 2 torus for all sixteen Bays. Twenty-two areas of

pitting corrosion with pits that ranged from 0.0162 inches to 0.1062 inches deep in

the immersion areas of eight Bays were identified. Coating repairs had been made

on all areas with identified corrosion. Other minor deficiencies which included

blistered coating, rust sta:ning pinpoint rusting and localized corrosion cells were

recorded. No evidence of incipient general coating failure was identified.

In FER-7 209, results were also identified from an internal inspection of the Unit 2

torus immersion area that had been performed in February of 1993 which had been

documented in another FER entitled "Underwater Desludging, Inspection and

Coating Repair of the Torus Pressure Boundary." This inspection included six Bays

and had identified similar findings to the 1995 inspection, with corrosion pits that

ranged from 0.0145 inches to 0.1515 inches deep.

The inspector reviewed FER-7133 "Underwater Desludging, Inspection, Coating

Repair and Bolt Replacement" prepared by Underwater Engineering Services, Inc. a

subsidiary of S. G. Pinney and Associates, Inc., and dated July 15, 1994. This

report documented the 1994 internal inspection, repair and T-quencher bolt

replacement results for the Unit 3 torus. The inspection scope included a

  • qualitative internal inspection of Bays one through five. Minor deficiencies were

recorded which included (blisters, rust staining, pinpoint rusting and localized

corrosion cells).

Pits were measured and recorded that ranged from 0.006 inches

to 0.1185 inches deep. Coating repairs had been made on* all areas with identified

corrosion. No evidence of incipient general coating failure was identified.

In UFSAR Section 6.2.1.2.3 the suppression chamber shell wall thickness was

.recorded as typically 0.585 inches above and 0.653 inches below the horizontal

centerline. No specific corrosion induced wall loss allowance was identified within

the UFSAR. Therefore, inspectors reviewed the following vendor Calculations

prepared for Commonwealth Edison:

,

3

CWE-084-218. "Dresden 3 Torus Pitting Evaluation." Revision 0. prepared

by NUTECH Engineers

This calculation evaluated the suppression chamber pitting (below the

horizontal centerline) for the Unit 3 torus identified during a 1991 inspection.

This calculation demonstrated that ASME Code Section Ill, Subsection NE

margins were maintained for pitting of 0.099 inch in depth, repaired by

contouring the pit edges with a four to one taper.

CWE084.0222, "Evaluation of Suppression Chamber Pitting at Dresden

Unit 2." Revision 0. prepared by NUTECH Engineers

This calculation evaluated the suppression chamber pitting (below the

horizontal centerline) for the Unit 2 torus identified during a 1993 inspection.

This calculation demonstrated that ASME Code Section Ill, Subsection NE

. margins were maintained for pitting of 0.1515 inch in depth, repaired by

contouring the pit edges with a four to one taper.

64.305.1027, "Evaluation of Torus Pitting Identified During D2R14,"

Revision 0. prepared by VECTRA

This calculation evaluated the suppression chamber pitting for the Unit 2

torus pitting identified during a 1995 inspection. This calculation provided

generalized curves for accepting torus pitting (in either unit) without repairs

(e.g., tapering of the edges) based on depth (maximum of 0.25 inches),

width of the pit and clustering of pits.

The coating deficiency records (from 1991 and 1993 inspections) reviewed by the

inspector, recorded only pit depth. No detailed information on* individual pit width

or clustering (spacing proximity to adjacent pits) had been recorded. Due to the

short duration of this inspection, the licensee staff were unable to provide repair

records (e.g., faring pit edges to a four to one taper) or documented

characterization/evaluation of this pitting as assumed in the bounding calculations.

Thus, the inspector was unable to determine:

if pits had been repaired with a four to one taper as assumed in Calculations

CWE-084-218 and CWE084.0222, or

if pit depth, width and clustering had been recorded and evaluated against

acceptance criteria found in Calculation 64.305.1027.

The inspector considered this issue to be an unresolved item (50-237 /97003-

02CDRS); 50-249/97003-01 (DRS)) pending further review by the licensee and NRC

of the documented corrective actions taken for the torus suppression chamber

pitting. The licensee staff agreed to look into this issue and stated that they would

respond to this issue within 60 days.

In FE Rs 7133 and 7 209 the carbon steel portions of the main steam relief valve

lines in the Unit 2 and Unit 3 torus immersion area were identified as being coated

with Carboline Carbo Zinc #11. Additionally, the emergency core cooling system

4

suction strainer cover shrouds for the Unit 2 torus were identified in FER 7209 as

being coated with inorganic zinc. UFSAR Section 6.1.2 allowed the use of

Carboline Carbo Zinc #11 on the containment and torus for touch up. UFSAR

Section 6.1.1.2, evaluated the affect on carbon steel corrosion rates from a

postulated event that results in introduction of sodium pentaborate solution into the

torus. However, the UFSAR did not include an evaluation of the potential effect of

sodium pentaborate solution with Carbo Zinc #11 nor inorganic zinc coating found

within the torus. The inspector's questions on the potential for hydrogen

generation from reactions with zinc based coatings and sodium pentaborate

solutions prompted the licensee staff to initiate a condition report on this issue.

The licensee subsequently provided the inspector a copy of an NRC letter "SEP

Topic Vl-1, Organic Materials and Post Accident Chemistry, Dresden Nuclear Power

Station, Unit 2" dated June 30, 1982, which indicated that this issue had been

considered and Unit 2 had been found to meet the current licensing basis criteria for

this topic. The inspector had no further concerns on this issue.

Conclusion

The inspector identified a pump installed in the Unit 2 torus basement that lacked

installation documentation and for which an installation safety evaluation had not

been performed. The inspector considered the undocumented installation of a.

pump in the Unit 2 torus basement to be a change to the facility as described in the

UFSAR, without a written safety evaluation to ensure that an unreviewed safety

question did not exist.

Past licensee inspections had identified inside diameter pitting of the torus

suppression chamber in both units, for which vendor supplied calculations had been

performed to demonstrate the acceptability of these conditions.* Due to the short

inspection period, the licensee staff were unable to provide repair records or

documented characterization/evaluation of this pitting as assumed in the bounding

calculations. Thus, the inspector was unable to determine if appropriate corrective

actions (pitting repairs and/or pitting characterization) had been performed as .

assumed in the bounding engineering calculations. The inspector also identified

missing paint and minor gouges on the exterior of the torus which indicated that

more effort may be needed in this area. The inspector considered the

implementation of the ASME Code,Section XI, Class MC requirements, in

containment coating inspection procedures, to be a positive step toward

maintaining the torus and containment materiel condition.

Ill. Engineering

E2

Engineering Support of Facilities and Equipment

E2.1

Inspector Updated Safety Analysis Report Review

While performing the inspections discussed in this report, the inspectors reviewed

UFSAR sections:

6.1

Engineered Safety Feature Materials

5

6.2

Containment Systems

The inspectors identified one UFSAR discrepancy related to an undocumented

installation of a pump in the Unit 2 torus basement (see Section M 2.1 ).

V. Management Meetings

X1

Exit Meeting Summary

At the conclusion of the inspection on January 15, 1997, and final phone exit on

January 23, 1997, the inspector met with licensee representatives identified herein

and summarized the scope and findings of the inspection activities. The inspector

questioned licensee personnel as to the potential for proprietary information in the

likely inspection report material discussed at the exit. No proprietary information

was identified.

PARTIAL LIST OF PERSONNEL CONTACTED

Commonwealth Edison Company <ComEdl

E. Carroll

B. *casey

A. Casilla

R. Freeman

P. Holand

R. Radke

Regulatory Assurance

ISi Coordinator -

Design Engineering

Engineering Manager

Supervisor Regulatory Assurance

Plant Engineering

F. Spangenberg

Manager Regulatory Assurance

System Engineering lead

G. Tietz

J. Williams

D. Winchester

T. Woodroffe

Plant Engineering

SOV Director

System Engineering

U. S. Nuclea"r Regulatory Commission (NRC)

J. Hansen, Resident Inspector

IP 73753:

IP 73755:

IP 73052:

INSPECTION PROCEDURES USED

lnservice Inspection

lnservice Inspection, Data Review and Evaluation

lnservice Inspection, Review of Procedures

6

~*-

ITEMS OPENED, CLOSED, AND DISCUSSED

Opened

50-237 /97003-01 (DRS)

50-237 /97003-02(DRS)

50-249/97003-01 (DRS)

VIO

Undocumented installation of a pump in the Unit 2

torus basement

URI

Review of the corrective actions taken for torus pitting

7

[