Notice of Deviation Fron Insp on 920916-1109.Deviation Noted:Plant Operator Training Was Not Performed to Address motor-operated Valve Concerns
ML17179A578
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 11/18/1992
From: Beverly Clayton
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML17179A577 List:
References
50-237-92-26, 50-249-92-26, GL-89-10, NUDOCS 9211240039
Download: ML17179A578 (1)


Text

-*

NOTICE OF DEVIATION Commonwealth Edison Company Dresden Station, Units 2 and 3 Doc~et Nos:.

50-237; 50-249 _

License Nos. DPR-19; DPR-25 During an NRC inspection conducted on S-eptember-16 through November 9, 1992, a

  • deviation of your commitment to augment plant operator training to address motor operated valve coricerns was id~ntified. In accordance with the "General Statement of Policy ~nd Procedure for NRC Enforcement Actions,"

10 CFR Part 2, A~peridix C (1992), the deviation is listed below~

The respon~e to Generic Letter 89~1~, Supplement 3, "Consideraiion bf the Results of NRC Sponsored Test and Motor Operated Valves,"' dated March 11, 1991, stated a number bf moto~ operated valves had been determined.to be deficient.

Included in the response was a plant specific Safety Assessment verifying generic safety assessments, performed by the NRC and the BWR Owner Groµp, were applicable to Dresden. - Item 3 of the Safety Assessment, "Conduct

. of Training," stated plant operator training would be au~mented to address the motor operated valve concerns; including discussions regarding the potential for incomplete closure of the subject motor operated valv~s.

. Contrary to the above, as of October 10, 1992, the stated plant operator training was not perfotmed.

Please provide to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, D.C. 20555, wit~ a copy to the Regional Admi ni"strator, Region I II, and a copy to the NRC Resident Inspector, it1 _ * -

writing within 30 days of the date of this Notice, the reasons for the deviation, th~ corrective st~ps which have been taken and the results achieved, the corrective steps which will be taken to avoid fu~ther deviations, and the date whe~ your corrective action will be completed.

Where good cause is shown, consideration will be given to extending the response time.

_Dated. at Glen Ellyn, Illinois this / 8 day_.of November 1992.

. - Brent Clayton, cChief Reactor Projects Branch 1.