Notice of Violation from Insp on 920113-0302.Violations Noted:Corrective Actions to Condition Adverse to Quality Occurring on 901208,failed to Preclude Repetition of Unplanned Unit 3 Group II Isolation on 920115
ML17177A321
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 03/12/1992
From: Greenman E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML17177A320 List:
References
50-237-92-02, 50-237-92-2, 50-249-92-02, 50-249-92-2, NUDOCS 9203240031
Download: ML17177A321 (2)


Text

  • Commonwea 1th Edi son Company *
  • 50:...237, 50-249 License Nos. DPR-19, DPR-25 During an NRC inspection conducted on January-13,.through March 2, 1992, two*

violations of NRC requirements were identified. In.accordance with the "General Statement of Policy and Procedure for NRC Enforcement Actions,"

10 CFR Part 2~ *Appendix.C, (1991), the violations.are listed below:

1.

10 CFR 50 Appendix B, Criterion XVI, *corrective Actions,* states in partJ that measures shall *be established to assure that conditions adverse to qual itY are promptly identified and corrected.

  • In the case

.of significant. conditions adverse to quality, the measures shall assure

  • that the c~lise of the condition is determined and corrective action
  • taken to preclude repetition~

Contrary to the above:

  • a.

Corrective actions to a condition ad~erse to quality o~curring on

  • July 8, 1991, a non-qualified. instrument maintenance mechanic performi_ng a survei 11 ance without direct supervision from the
  • foreman, fa i1 ed_ to prec 1 ude repetition of a non-qua 1i f i ed instrument mechanic performing a surveillance without direct supervision on February 4, 1992..
  • w
b.

_Corrective-actions'to a condition *adverse to quality occurring on.

December 8, 1990, ari unplanned Unit 2 Group II isolation, failed to precl~de repetition of an Onplanned Unit 3 Group II isolation

  • on January 15, 1992, due to. the same cause.

This is a Severity Level IV violation (Supplement_ I).*

  • 2.

Technical Specificatfon 3.1.A and Table 3.1.1 requires a minimum of three operable intermediate range monitors operable in each reactor protection trip channel while in Refuel Mode.

Contrary to the above, on February 2, through February 3, 1992, only two i~t~rmediat~ range monito~s were operable in reactor protection lrip channel B while Unit 2 was in Refuel Mode.

This is a Severity Level IV viol at ion (Supplement I).

Pursuant to the provisions of 10 CFR 2.201, Commonwealth Edison is hereby required to submit a written statement or explanation to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington D.C. 20555.

  • with a copy to the U.S. Nuclear Regulatory Commission, Region Ill, 799 Rooseve 1 t Road, Glen Ellyn, 111 i no is, 60137, and a copy to the NRC
  • Resident Inspector at the facility that is the subject-of this Notice, within 30 days of the date of the letter transmitting this Notice of Violation*

. (Notke). This reply should'be:-Clearly-~*marked-as 0 *a ~*Repiy -to~a~-Notice**of. -

Violation* and should include for each violation: (1) the reason for the violation, or, if contested, the basis for disputing the violation, (2) the 9203240031 926j1~--

PDR ADOCK 05000237 Q

PDR

corrective steps that have been taken and the results achieved, (3) the corrective steps thlt will be taken to avoid further violations, and (4) the date when full compliance will be achieved. If an adequate reply is not received within the time specified fn this Notice, an order may be issued to show cause why-the license should not be modified, suspended, or revoked, or why such other action as may be* proper should not be taken.

Wh.ere good cause is sho~n, consideration will be given to extending the response time..

. this _ day of March,

  • 1992 *
  • ~~

.. ~.

Edward* G. Greenm-an, Di rector, Division of Reactor Projects *