See also: IR 05000237/1991031
Text
~p.R REG(JL _.
UNITED STATES
c,'-
'"'i>-
(¥-..
o;}
NUCLEAR REGULATORY COMMISSION
REGION Ill
0
....
'Y i; .
..,
. "
- 799 ROOSEVELT ROAD
GLEN ELLYN,.ILLINOIS 60137
"+-
o'
/)
~
. **** ..
Docket No. 50-237
Docket No. 50-249
Co:mlnonwealth Edison Company
ATTN:
Mr. Cordell Reed
Senior Vice President
Opus West III
1400 Opus Place
Downers Grove, IL
60515
Dear Mr. Reed:.
This refers to the routine safety inspection conducted by
W. Rogers, D.*Hills and M. Peck of this office and assisted by
R. Zuffa of the Illinois Department of Nuclear Safety on
October 20.through December 6, 1991, of activities at.Dresden
Nuclear Power Station, Units 2 and 3 authorized by NRC Operating
License Nos. DPR-19 and DPR-25 and to the discussion of our
findings with Mr. c. Schroeder and others at the conclusion of
the inspection.
The enclosed copy of our inspection report identifies areas
examined during the inspection..
Within these areas, the
inspection consisted of a selective examination of procedures and
representative records, observations, and interviews with
personnel.
As discussed in section 3.f of the report, the inspectors had
specific questions concerning the replacement of primary
containment isolation system relays.
These questions are
considered an open item *. In section 7.d of the report, the
inspectors discussed licensee identified cable separation
requirements that were not met and the need for a licensee's
operability evaluation.
The operability evaluation is considered
unresolved.
We request that you respond within 60 *days of the
date of this. letter to the questions identified in section* 3.f
and provide an operability evaluation as addressed in section
7.d.
No violations of NRC requirements were identified during the
course of this inspection.
In accordance with 10 C.FR 2. 7~0, of the *Commission's regulations,**
a copy of this letter and the enclosure(s) will be placed in the
NRC Public Document Room.
9201070008 911226
ADOCK 05000237
G
commonwealth Edison Company
2
DEC 2* .6 1991
We will* gladly discuss any questions you have concerning this
inspection.
Enclosure:
Inspection Reports
No. 50-237/91031(DRP); and
No.
50-249/~-1034 (DRP)
cc w/enclosure:
D. Galle, Vice President -
B~
Operations
T. Kovach, Nuclear
Licensing Manager
c. W. *Schroeder, Station Manager
DCD/DCB (RIDS)
OC/LFDCB
Resident Inspectors LaSalle,
Dresden, Quad Cities
Richard Hubbard
.
J. w~ Mccaffrey, Chief, Public
- Utilities Division
Robert Newmann, Off ice of Public
Counsel, State of Illinois Center
Licensing Project Manager, NRR
C~ J. Paperiello, RIII
- lJ(ht
Brent Clayton, Chief
Reactor Projects Branch 1