ML17164A605

From kanterella
Jump to navigation Jump to search
Insp Repts 50-387/95-03 & 50-388/95-03 on 950130-0203.No Violations Noted.Major Areas Inspected:Evaluation of Plant Licensed Operator Requalification Training Program During Wk of 950130
ML17164A605
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 02/21/1995
From: Florek D, Meyer G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML17164A604 List:
References
50-387-95-03, 50-387-95-3, 50-388-95-03, 50-388-95-3, NUDOCS 9503060009
Download: ML17164A605 (16)


See also: IR 05000130/2002003

Text

U. S.

NUCLEAR REGULATORY COMMISSION

REGION I

DOCKET/REPORT NOS:

50-387/95-03

50-388/95-03

LICENSEE:

Pennsylvania

Power and Light Company

FACILITY:

Susquehanna

Steam Electric Station

Salem Township,

Pennsylvania

DATES:

January 30-February 3,

1995

INSPECTORS:

D. Florek, Senior Operations

Engineer,

DRS,

RI

C. Tyn

NRC Consultant,

INEL

LEAD INSPECTOR:

. Florek, Senior Operations

Engineer

BWR Section

Division of Reactor Safety

D te

APPROVED BY:

G enn

W. Heyer, Chief

BWR

8

PWR Sections

Division of Reactor Safet

Da e

9503060009

95022i

PDR

ADQCK 05000387

8

PDR

INSPECTION SUMMARY

Combined Report Nos. 50-387/95-03

and 50-388/95-03

Two inspectors

evaluated

the Susquehanna

Steam Electric Station

(SSES)

licensed operator requalification training program during the week oF

January

30,

1995.

The annual

operating test

and written requalification

examination

were administered to an operating

crew.

~Oereti ens

Overall,

SSES performed

a very good requalification training program.

The

annual written examination'nd

operating test were high quality,

and the

evaluator s effectively reviewed operator performance to high standards.

This

resulted

in part of one operating

crew failing the simulator section of the

examination.

Further,

the relationship

between the training and operations

departments

was exceptionally good, the training feedback

and remedial

training programs

were effective,

and outstanding controls existed regarding

the status of active operator licenses

and reactivation of licenses.

Nonetheless,

some problems

and areas for improvement were identified.

A few

operators

involved in exam development

and review had

been inappropriately

exempted

from one year's

examination within the two year cycle.

This error

was corrected during the inspection.

JPNs

and scenarios

were not addressed

within the examination

sample plan, which had the potential to overemphasize

some training areas.

There

was

a scarcity of Unit 2 JPHs.

Event sequencing

within the simulator scenarios

was predictable,

and operators

seemed to

perform based

on the expected

sequence.

The STA's involvement in crew

activities

on the simulator was inconsistent

and often ineffective.

Training

records

had

some problems,

including misfiled records,

missing records,

and

weak guidance

on expected

records.

Two open items were closed

and related to corrective actions following the

submittal of an

SRO license

renewal without the applicant having successfully

completed the requalification program requirements

and secondary

containment

entry conditions

on area radiation levels.

11

DETAILS

1.0

BACKGROUND AND SCOPE (IP 71001)

During the week of January

30,

1995,

two inspectors

conducted

a performance-

based

inspection of the Susquehanna

Steam Electric Station

(SSES)

licensed

operator requalification training program using

NRC Inspection

Procedure

71001,

"Licensed Operator Requalification

Program Evaluation."

This

inspection took place

as part of Requalification Cycle 94-7 and evaluated

the

requalification training program, evaluators

and operators

during Week 4 of

their 1995 annual

exams.

The purpose of this inspection

was to eva'iuate

the acceptability of the

licensed requalification training program with respect to 10 CFR 55

regulations

and to assess

the effectiveness

of the training.

Also, the

inspectors

focused

on the training evaluation

process

and requalification

program revisions

made

as

a result of this evaluation process.

The inspection

included

a review of'the annual

operating

and written

examinations,

and observation of individual and crew performance for one

operating shift that was divided into three operating

crews for the simulator

portion of the examination.

In addition, interviews with licensed operators,

training instructors,

and supervisory

personnel

were conducted.

The

procedures for maintenance

and activation of operator licenses

were reviewed.

The inspectors verified that the requirements

were met to reactivate inactive

licenses.

The following administrative procedures

and documents

associated

with the training program

and its implementation

were also reviewed.

NTP-(A-31.2, "Licensed Operator Requalification Program

Implementation," Revision 3,

Change

94-007,

dated

May 20,

1994.

OP002,

"Licensed Operator Requalification," Revision 3,

Change 8, dated

March 24,

1994.

STCP-(A-323,

"Simulator Performance

Evaluation," Revision 3, dated

January

3,

1994.

The inspectors

used

NUREG-1021,

"Operator Licensing Examiner Standards,"

Revision 7,

as

a basis for determining the adequacy of the Susquehanna

Steam

Electric Station operator examination

process.

2. 0

EXAMINATION DEVELOPMENT

SSES administered

annual written examinations

and operating tests

(job

performance

measures

(JPMs)

and simulator scenarios)

to an operating

crew.

Each portion of the examination is discussed

below.

2. 1

Examination

Sample Plan

The inspector

concluded that the examination

sample plan was not effectively

used to integrate all portions of the examination,

because

each portion of the

examination

was developed

independently

by different individuals and the

sample plan was only used to develop the written examination.

This minor

problem could enable

overemphasis

of evaluation in a training area

and absence

of evaluation in another.

The inspector

found that each portion of the examination

was developed

by

different individuals or teams.

A developer of one portion of the examination

did not discuss

his portion of the examination with another developer of

another portion of the examination.

The examination

sample plan was developed

to emphasize

the training provided over the last

12 months.

Approximately 20X

of the sample plan covered training provided in other years.

However, the

sample plan was only used to develop the written examination.

The sample plan

was not used to integrate all portions of the examination.

The inspector concluded that by not using the sample plan to integrate all

portions of the examination the potential existed that could result in an area

being overemphasized

by the examination process.

For example,

a scenario

could focus

on HPCI (high pressure

coolant injection),

a JPM could be

developed for HPCI,

and the written examination could also

emphasize

HPCI.

For the examination

observed,

this overemphasis

had occurred to a small

extent,

in that the

JPM administered to reactor operators

(ROs),

"Respond to a

Failure of RPS to Scram the Reactor,"

was

a task observed to be performed

by

ROs during the simulator portion of the examination.

Interviews with training

department staff identified that no review was performed for examination

duplication.

2.2

Written Examination

The inspector

concluded that the written examinations

were good evaluation

tools.

The inspector concluded that the questions

were at the appropriate

level for an open reference

examination

and the examinations

were

a good

evaluation of operator

knowledge.

Six written examinations

were developed for

the examination cycle based

on the examination

sample plan.

Each written

examination

included

a static examination

as well as

a classroom

examination.

Each written examination

included

a different static simulator setup.

For the

three examinations that the inspector reviewed,

the classroom portion of the

written examination

had less

than

30X of the questions

from a previous

classroom

examination.

This seemed to be

a reasonable

approach to preserving

the security

and validity of the examination.

2.3

Job Performance

Measures

(JPNs)

In addition to the absence of JPM coverage

within the examination

sample plan

as noted in Section

2. 1, the inspector identified concerns

on JPM duplication

week-to-week

and the scarcity of Unit 2 JPMs.

The inspector

noted that in contrast to the written examination,

in which

administrative

procedures

control the duplication of questions

on the

subsequent

week's examinations,

there is no such control

on duplication of

JPMs during subsequent

examinations.

Specifically,

one

JPM set

can

be

administered

during

a particular week with a repeat of the set in a subsequent

week.

While the inspector did not identify any specific examination security breach,

the

SSES methodology

used this year to repeat

an entire

JPM set in a

subsequent

week could result in a compromise of examination security.

Further, the inspector

noted that no JPHs this cycle were performed

on Unit 2,

All JPMs were Unit I or common JPMs.

Further,

review of the

JPM examination

bank identified that the

JPM identified for Unit 2 are focused

almost

exclusively on remote

shutdown.

The inspector judged the scarcity of JPMs

on

Unit 2 in the facility examination

bank to be

a weak approach to evaluating

operator skills on both units

and

a potential

hinderance

to effectively

administering the operating test.

2.4

Simulator Examination

The inspector concluded that the scenarios

were good evaluation scenarios;

however,

event sequencing

in the scenarios

was predictable

and tended to

diminish the effectiveness

of the evaluation.

Further,

some critical tasks

lacked specific measures

for performance,

and

some

had been miscategorized

in

that the tasks

were not safety significant in the given scenario.

The inspector

concluded that the scenarios

were good evaluation

scenarios

and

provided numerous opportunities for the crew members to perform,

such that

their performance

could be evaluated.

However, the scenarios

were predictable

regarding event sequencing;

The first ma'ifunction resulted in a technical

specification determination

by an

SRO,

then entry into abnormal

procedures,

and then the major transient with emergency operating

procedure

(EOP) entry.

The crews

seemed

aware of this routine

and did not really concern themselves

with the plant until after the technical specification

problems

had been

resolved.

The inspector judged that this predictability could inadvertently

train the operators

in sequences

unrelated to actual plant performance

and

tended to diminish the effective evaluation of the operators'erformance.

Further,

the critical tasks identified in the scenarios

frequently lacked

objective performance

indicators for determining pass/fail

decisions,

and

some

did not appear to be safety significant within the scenario.

Many critical

tasks relied on the judgement of the evaluators

to determine pass/fail

determination.

For example, if the critical task was to perform emergency

depressurization,

there were no specification

as to when the emergency

depressurization

was required to be completed.

In addition,

a few examples

were identified in which tasks that might be safety significant in other

situations

were not in the given scenario.

For example, inhibiting ADS (auto-

depressurization

system)

was not always critical to the safety impact

on the

plant in all scenarios.

The scenarios

used

on the operating test

had

been developed with good

involvement from the operating

crews, in an acceptable

manner to preserve

examination security,

and with a wide range of evaluated

malfunctions

and

events.

3.0

EXAMINATIONADMINISTRATION, RESOLTS

AND OBSERVATION

3.1

Written Examination

The written examination

was administered

in appropriate

environments,

and all

operators

passed

the examination

administered

during the inspection visit.

However, the inspector concluded that

a few operators

had been inappropriately

exempted

from the written examination,

but subsequent facility action

corrected the concern.

The inspector

concluded that

a few SSES licensed operators

were not receiving

a comprehensive

biennial written examination,

in that they could be exempted

from one year's

examination within the two year cycle based

on their

involvement in the exam's

development.

Specifically, the inspector

found that

administrative

procedures

allowed

an operator

who was involved with the

development,

grading or review of the written examination to be excused

from

that year's written examination.

An individual could not be exempted for two

consecutive

years.

A review of the

1994 records

and plans for the

1995

examination identified that two licensed operators

were exempted

from an

examination in 1994 and two different operators

were planned to be exempted in

1995.

The inspector

concluded that since the written examination is focused

on the

training received in the last year,

both examinations

would be necessary

to

assure that the written examination is comprehensive for the entire two year

requalification program cycle.

The

SSES

approach to written examination

results in each examination

being

a segment of the requalification cycle, with

some look back at previous training.

When brought to the attention of the

SSES training management,

the

SSES training management

determined that

a

change to the administrative

procedure

would be initiated and the exemption

from the annual

examination eliminated.

An annual'ritten

examination

would

be prepared

and administered to those

two individuals initially exempted

from

the

1995 written examination.

This was acceptable

to= the inspector.

3.2

JPMS

The inspector concluded that the JPHs were well administered

and that the

operators

performed well.

Some areas for improvement were noted with regard

to allowing operators

to observe other operators

and the understanding

of in-

plant equipment at the

SRO level.

The inspector monitored the administration of JPHs to three

ROs

and two SROs.

Four evaluators

administered in-plant JPHs in parallel,

and two evaluators

administered

the simulator JPHs in parallel.

All JPHs observed

were successfully

performed.

The inspectors

observed that

the

SROs were weak in stating what they expected

to see

by their actions

when

controls were manipulated during in-plant JPHs.

The

SROs simply simulated

operating the controls

as specified in the procedure with little discussion of

the consequences

of their actions.

The inspector concluded that

SROs

appeared

to have weak understanding

of in-plant equipment controls.

In general,

the facility evaluators

did a very good job of providing the

appropriate

cues

when required.

However, the cues contained

in the

JPM to

initiate SBGTS (standby

gas treatment

system)

in an emergency

were

inappropriately stated in the

JPM and did not allow the operator to determine

if his actions

were correct

and the system response

was consistent with his

actions.

The in-plant JPMs observed. were all on Unit I, and the four exam teams

kept

meeting

up with each other.

Also, the

SSES examination

team used the

technical

support center

above the control

room as

a meeting place for

operators to take the examination.

Some of the JPMs required the operators

to

go into the control

room.

The inspector

observed

some of the operators

who

would be taking the second

wave of examinations

in the control

room,

as the

first wave of operators

were conducting their examinations.

This was not

conducive to examination security.

The inspector did not consider that any of

the observations

in the control

room to be

a direct breach of examination

security.

However, the inspector judged that improvement in the

SSES

method

for in-plant JPM administration is desirable to avoid the potential for

examination

compromise.

3.3

Simulator

The inspector concluded that the simulator evaluation

was thorough, effective,

and complete,

and based

on

some

weak operator performance,

that the evaluators

appropriately failed one crew and two individuals within that crew.

Evaluated

crews demonstrated

a range

oF performance

from poor to superior.

During six simulator scenarios

on three evaluated

crews,

each consisting of

two SROs,

two ROs,

and

a shift technical

advisor

(STA), the evaluator

teams

did a very thor ough and complete job of monitoring and evaluating the actions

of licensed operators.

Al'I crews completed the critical tasks;

however,

the

evaluators

measured

operator

performance to high standards

of performance.

One crew was judged to have little or no weaknesses,

one crew was judged to

have minor weaknesses,

and the third crew was judged to have significant

weaknesses.

The evaluators

determined that one crew failed the examination.

Since

SSES also performed individual evaluations,

two individuals within that

crew were also failed.

The inspectors

independently

assessed

the crew performance

in the simulator.

The inspector 's assessment

of crew performance

was consistent with. the

evaluation

team's

assessments.

Also, the inspector determined that, despite

having the one

STA, the

STA involvement with each

crew was inconsistent,

and

the

STA was not utilized effectively .in two of the three examination

crews.

Some of the emergency

support

(ES) procedures

that implement in-plant operator

tasks to carry out emergency operating

procedure actions

were performed in an

accelerated

time.

This was done in order to obtain

a target simulator time of

about

50 minutes.

This had the potential to provide negative training to the

operators.

The inspector considered that real time implementation of ES

procedures

would reinforce real time expectations

and also provide meaningful

information as to adequacy of the

ES procedure

methodology to the overall

emergency operating

procedure strategy.

3.4

Other Observations

Based

on interviews with several

ROs,

SROs,

and trainer/evaluators

and other

inspector observations,

the inspector concluded that the relationship

between

the training and operations

departments

was exceptionally good.

The operators

felt that the training department

was there to support them,

and they

appreciated their ability to have

an input during training and examinations.

The inspector

also noted two other positive initiatives that contributed to

the exceptional

relationship

between operations

and training.

The first was

the ownership of each operating

crew of five evaluation scenarios

in the

simulator examination

bank.

This appeared

to help assure validation of the

scenario

scenarios

and enabled

an understanding

by the operators of the

examination

process

and management

expectations

on standards

of performance.

The second

was the use of an individual crew training week between the end of

one training cycle and the beginning of another cycle.

This week allowed the

shift supervisor to tailor individual training for noted weaknesses

on his

crew as well as allow the training staff to better establish

the training for

the next cycle.

The following observation is intended to provide feedback to the

SSES

NRC site

access training.

The read

and sign training did not provide any guidance

on

the expected

methods to enter the radiologically controlled area or

information on how to obtain

a self reading dosimeter.

4.0

TRAINING RECORDS

REVIEM

The inspector

found minor problems regarding

SSES training records that were

incomplete or misfiled.

Specifically, the inspector reviewed the

1994

examination records of five operators.

The results of the annual

1994

simulator and

JPH examinations

were not initially in the individual operator

folders, but had

been misfiled and were subsequently

found.

Four of the five

operators

had failed a portion of the

1994 examination

and remedial

programs

were required.

However,

one of the four operators'emedial

programs

was not

in his file and

as of the end of the inspection

had not been located.

Also,

the inspector

noted that incomplete procedural

guidance existed

on the

expected

contents of the training record files.

5.0

NANAGENENT OYERSIGHT

'AND CONTROLS

The inspector

reviewed guality Assurance

(gA) Audits94-030

and 94-067

and

found the audits to be generally effective management

oversight tools.

The

audits covered the effectiveness

of the

SSES training, retraining,

and

qualification programs for the entire plant staff and the

1994 annual

simulator certification testing.

The audits were complete

and findings were

transmitted to the appropriate level of SSES

management.

Also, the inspector noted

an audit finding that related to errors in the

training record

management

system,

similar to that discussed

above.

Training

management

stated that these findings were relatively recent

and that

a broad

approach to addressing'he

records

issues

was being formulated.

6.0

TRAINING FEEDBACK SYSTEN

The inspector concluded that the training feedback

system for operations

crews

has

been effective based

on review of training feedback records for the

current

and two previous requalification cycles

and

an interview with the

training instructor responsible for the program.

The training feedback

program provides weekly crew course critiques

and input

for future training.

This feedback is provided to training management

and is

discussed

at periodic meetings of the Training Curriculum Committee for a

determination

on incorporation into the training program.

An inspector

check

of some crew-identified weak training areas

showed that these

areas

had

been

incorporated into later requalification cycles.

The inspector noted that the

submittal of crew feedback

forms effectively involved the crew's supervision

in the feedback

process

but could potentially hinder the ability of

individuals to provide feedback.

No actual

problems

were identified in this

respect.

7.0

REMEDIAL TRAINING PROGRAN

The inspector

concluded that the remedial

program provided good retraining

and

support to operators

who have failed portions of their annual requalification

examinations.

The program addresses

individual

and crew failures or weak

areas resulting from the annual requalification examination.

The inspector reviewed the

SSES instructions for the remedial training program

and interviewed the instructor responsible for the program.

Additionally, one

operator

who failed the written examination during this cycle was interviewed

and his specific initial examination,

remedial

program,

and retake examination

were reviewed.

The operator

had

been

informed of his examination failure and was

made

aware

of his removal

from licensed operator duties until his remedial

program

and

reexamination

were completed.

The training department

developed

a remedial

program

based

on the operator's

demonstrated

weak areas

on the examination,

directed the operator's

remedial

actions,

and provided additional assistance

and simulator time as necessary

to support his efforts.

The operator stated

that

he received

good support during his remedial

program

and subsequent

reexamination.

8.0

ACTIVATION AND MAINTENANCE OF LICENSES

The inspector

concluded that the program for tracking status of active

operator licenses

and for reactivation of licenses

was outstanding.

The

inspector reviewed the

SSES instructions for maintaining licenses

active

and

for reactivation of licenses.

Two operators

who reactivated their licenses

within the last five months were interviewed,

as

was

an operations

department

supervisor.

The

SSES instructions for maintaining licenses

active

and for reactivation of

licenses

were very specific

and required actions of the operator

as well as

training and operations

management.

The instructions provided checklists,

including plant tours

and

an verbal examination, that must

be signed

by the

operator,

the shift supervisor,

and the manager

of nuclear operations.

Although the checklists

could have

been

more specific regarding expectations,

these checklists

appeared

to be effective mechanisms

to address

license

reactivation.

The inspector

concluded that both operators

interviewed

knew

their responsibilities for a license reactivation.

9.0

LICENSEE ACTION ON PREVIOUS INSPECTION FINDINGS

Closed

Unresolved

Item 50-387 94-25-01

This item related to the root cause

and corrective actions following the submittal of an

SRO license

renewal

application without the applicant having successfully

completed the

requalification program requirements.

An event

team was created to determine

the root causes

of the event.

As a

result of the event

team assessment,

changes

were being processed

to

Procedures

NTP-gA-31.2 and .OP002 to define the requirements for being current

within the requalification program.

It included time period limits that may

not be exceeded for missed training or weekly quizzes

as well as

end of

requalification year limits.

Additional training cycle reports will be

generated

to identify missed training and quizzes.

During the inspection

week, the

SSES training cycle reports indicated that no licensed individuals

had any missed training.

Based

on the

SSES event

team report

and actions

taken

by SSES to improve the procedures

and records

management

system, this

item is closed.

Closed

Unresolved

Items 387 93-06-02

and 388 93-06-02

This issue related to

establishment

of a single value for maximum normal radiation level

(500 mR/hr)

for areas

in secondary

containment.

SSES

has

changed

the secondary

containment

EOP entry condition for area radiation levels to any unexplained

area radiation level

above

maximum normal.

Maximum normal

has

been redefined

as

a high alarm on the specified radiation monitors.

This will eliminate

delay in implementing

EOP strategies

and is in line with the

BWROG EPGs.

Evaluation scenarios

observed

during the inspection

confirmed that using the

maximum normal radiation levels

as

a high alarm on the specified radiation

monitors resulted

in timely action by the operators to mitigate secondary

containment

challenges.

This item is closed.

10.0

EXIT MEETING

An exit meeting

was conducted

on February 3,

1995, during which the

NRC

inspectors

reviewed the scope

and findings of the inspection.

At the exit

meeting,

PP8L personnel

acknowledged

the inspector's

conclusions

and findings.

Personnel

at the exit meeting are listed below:

Pe

ns lvania

Power

and Li ht

K. Chambliss,

Manager,

Nuclear Operations

C.

Fedako,

Nuclear Operations Training Supervisor

A. Fitch, Nuclear Training Supervisor

M. Lowthert, Manager,

Nuclear Training

T. Markowski, Dayshift Supervisor Operations

E. Stanley,

Vice President,

Nuclear Operations

U. S. Nuclear

Re ulator

Commission

0. Mannai,

NRC Resident

Inspector