ONS-2017-042, Additional Information Regarding License Amendment Request for Temporary Completion Time for One Keowee Hydro Unit Inoperable for Generator Stator Replacement, License Amendment Request No. 2015-08, Supplement 2
| ML17159A526 | |
| Person / Time | |
|---|---|
| Site: | Oconee |
| Issue date: | 06/01/2017 |
| From: | Teresa Ray Duke Energy Carolinas |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| ONS-2017-042 | |
| Download: ML17159A526 (6) | |
Text
el_"-) DUKE *.
~ ENERGY ONS-2017-042 June1,2017 A TIN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Duke Energy Carolinas, LLC Oconee Nuclear Station (ONS), Units 1, 2, and 3 Docket Numbers 50-269, 50-270, and 50-287 10 CFR 50.90 Renewed Operating Licenses DPR-38, DPR-47, and DPR-55 Thomas D:Ray Vice President Oconee Nuclear Station Duke Energy ON01 VP I 7800 Rochester Hwy Seneca, SC 29672 o: 864.873.327 4
- f. 864.873.4208 Tom.Ray@duke-energy.com
Subject:
Additional Information Regarding License Amendment Request for Temporary Completion Time for One Keowee Hydro Unit Inoperable for Generator Stator Replacement License Amendment Request No. 2015-08, Supplement 2
Reference:
Duke Energy Carolinas, LLC. (Duke Energy) letter to the U.S. Nuclear Regulatory Commission (NRC), "License Amendment Request for a Temporary Technical Specification Change to Add a Required Action Completion Time for One Keowee Hydro Unit Inoperable.for Generator Stator Replacement, License Amendment Request No. 2015-08," dated February 26, 2016.
On February 26, 2016, Duke Energy Carolinas, LLC (Duke Energy) submitted the referenced License Amendment Request (LAR). Duke Energy advised the Nuclear Regulatory Commission (NRC) Project Manager on May 23, 2017, of an inadvertent omission from one of the Technical Specification (TS) marked-up and retyped pages associated with that change.
Specifically, proposed Note 3 to Required Action (RA) C.2.2.5 requires administratively verifying the Standby Shutdown Facility (SSF), Protected Service Water (PSW), and Emergency Feedwater (EFW) Systems are operable prior to entering the extended Completion Time. Note 3 was correctly described in Enclosure 1 of the LAR; however, the TS marked-up page and corresponding TS retyped page in Attachments 1 and 2 of the LAR, did not include "PSW" in the Note. The NRC Project Manager requested we supplement the LAR to provide corrected pages.
The corrected TS marked-up and retyped pages are contained in the attachment to this letter.
These two pages replace the corresponding marked-up page and retyped page in Attachments 1 and 2 of the LAR. Duke Energy reviewed the No Significant Hazards Consideration and determined it is not affected by this change.
There are no regulatory commitments made in this submittal. A copy of this LAR supplement is being transmitted to the State of South Carolina in accordance with 1 O CFR 50.91 requirements.
License Amendment Request No. 2015-08, Supplement 2 June 1, 2017 Page 2 Inquiries on this LAR supplement should be directed to Boyd Shingleton, ONS Regulatory Affairs Group, at (864) 873-4716.
I declare under penalty of perjury that the foregoing is true and correct. Executed on June1,2017.
Thomas D. Ray Vice President Oconee Nuclear Station
Attachment:
Corrected Technical Specification Marked-Up Page, and Retyped Page
License Amendment Request No. 2015-08, Supplement 2 June1,2017 cc w
Attachment:
Ms. Catherine Haney, Administrator, Region II U.S. Nuclear Regulatory Commission Marquis One Tower 245 Peachtree Center Ave., NE, Suite 1200 Atlanta, GA 30303-1257 Ms. Audry Klett, Project Manager (ONS)
(by electronic mail only)
Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Mail Stop 0-8G9A 11555 Rockville Pike Rockville, Maryland 20852 Mr. Eddy Crowe NRG' Senior Resident Inspector Oconee Nuclear Station Ms. Susan E. Jenkins, Manager, (by electronic mail only: jenkinse@dhec.sc.gov)
Infectious and Radioactive Waste Management, Bureau of Land and Waste Management Department of Health & Environmental Control 2600 Bull Street Columbia, SC 29201 Page 3
License Amendment Request No. 2015-08, Supplement 2
.*June 1, 2017 ATTACHMENT CORRECTED TECHNICAL SPECIFICATION MARKED-UP PAGE AND RETYPED PAGE
ACTIONS CONDITION C. (continued)
D.
KHU or its required underground power path inoperable.
OCONEE UNITS 1, 2, & 3 REQUIRED ACTION
- PSW, AC Sources - Operating 3.8.1 COMPLETION TIME AND
NOTE------------
- 1. No di~cretionary maintenance or testing allowed on
- SSF, FWand 1--11--_.;...e-ss-e"'""'ntial AC Power Systems.
- 2. Only applicable one time for each KHU due to eneratod field)
GG1e--Rewi~work and September 30, 2021 stator replacement administratively verified OPERABLE prior to entering the extended Completion Time.
D.1
,PSW, 55 Perform SR 3.8.1.4 for OPERABLE KHU.
1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> if not performed in previous 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> D.2 Energize either 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> standby bus from LCT via isolated power AND path.
3.8.1-6 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> from subsequent discovery of deenergized required standby bus (continued)
Amendment Nos. 383, 385, & 384
ACTIONS CONDITION C. (continued)
I D.
KHU or its required D. 1 underground power path inoperable.
AND D.2 OCONEE UNITS 1, 2, & 3 REQUIRED ACTION Perform SR 3.8.1.4 for OPERABLE KHU.
Energize either standby bus from LCT via isolated power path.
AC Sources - Operating 3.8.1 COMPLETION TIME AND
NOTE------------
- 2. Only applicable one time for each KHU due to generator stator replacement work and expires on September 30, 2021.
- 3. Only applicable if the SSF, PSW, and EFW are administratively verified OPERABLE prior to entering the extended Completion Time.
55 days from initial inoperability when Condition due to an inoperable KHU to perform generator stator replacement work 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> if not performed in previous 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> 24 hours AND 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> from subsequent discovery of deenergized required standby bus (continued) 3.8.1-6 Amendment Nos. xxx, xxx, & xxx