ML17157C177

From kanterella
Jump to navigation Jump to search

Forwards Util 930128 Telecopy Transmitting Corrected Page 3 of 921218 Application for Amends to Revise Ts,In Accordance W/Guidance in GL 88-16 Re Removal of cycle-specific Parameter Limits from TS
ML17157C177
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 02/04/1993
From: Clark R
Office of Nuclear Reactor Regulation
To:
Office of Nuclear Reactor Regulation
Shared Package
ML17157C178 List:
References
GL-88-16, TAC-M83426, TAC-M83427, NUDOCS 9302100428
Download: ML17157C177 (3)


Text

February 4, 19 Docket Nos.

50-387 and 50-388 NOTE TO:

File FROM:

Richard J. Clark, Project Manager Project Directorate I-2 Division of Reactor Projects - I/II

SUBJECT:

PLACING A TELECOPY IN THE FILE REGARDING REMOVAL OF CYCLE-SPECIFIC PARAMETER LIMITS FROM TECHNICAL SPECIFICATIONS, GENERIC LETTER (GL) 88-16, SUSQUEHANNA STEAN ELECTRIC STATION, UNITS 1

AND 2 (TAC NOS.

M83426 AND H83427)

By letter dated December 18,

1992, Pennsylvania Power and Light Company (PP8IL) submitted an application for amendments to revise the Technical Specifications (TSs) in accordance with the guidance in GL 88-16.

In reviewing the licensee's No Significant Hazards Consideration determination, it appeared that there were two superfluous words ("are anticipated")

in the last line of item 1.

This typographical error does not change the original no significant hazards determination.

By telecopy, dated January 28,

1993, the licensee confirmed that.this was a typographical error and that the two words "are anticipated" should be deleted.

Enclosed is the telecopy transmitting the corrected page 3.

Original signed by'ichard J. Clark 930210042B 930204 PDR ADOCK 05000387 P

PDR

Enclosure:

Telecopy Transmittal DISTRIBUTION IDocket File NRC and Local PDRs PDI-2 Reading CMi1 1 er OFFICE RClark HO'Brien PDI-H Richard J. Clark, Project Manager Project Directorate I-2 Division of Reactor Projects - I/II PDI-2 D

NAME DATE ri n

/93 RC

rb 93 CHi 93 OFFICIAL RECO D COPY OOCUNENT NAN:

LI834 26. NOT Q 8 Q Q ] ~P

o I

~g AEQy~

(4 p,

0 I

g p

Cy 0

++*++

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555 February 4, 1993 Docket Nos.

50-387 and 50-388, NOTE TO:

File FROM:

Richard J. Clark, Project Manager Project Directorate I-2 Division of Reactor Projects I/II

SUBJECT:

PLACING A TELECOPY IN THE FILE REGARDING REMOVAL OF CYCLE-SPECIFIC PARAMETER LIMITS FROM TECHNICAL SPECIFICATIONS, GENERIC LETTER (GL) 88-16, SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1

AND 2 (TAC NOS.

'M83426 AND M83427)

By letter dated December 18,

1992, Pennsylvania Power and Light Company (PP&L) submitted an application for amendments to revise the Technical Specifications (TSs) in accordance with the guidance in GL 88-16.

In reviewing the licensee's No Significant Hazards Consideration determination, it appeared that there were two superfluous words ("are anticipated")

in the last line of item 1.

This typographical error does not change the original no significant hazards determination.

By telecopy, dated January 28,

1993, the licensee confirmed that this was a typographical 'error and that the two words "are anticipated" should be deleted.

Enclosed is the telecopy transmitting the corrected page 3.

Enclosure:

Telecopy Transmittal J.

lark, Project Manager Project Directorate I-2 Division of Reactor Projects I/II