ML17156B004

From kanterella
Jump to navigation Jump to search
Special Insp Repts 50-387/88-21 & 50-388/88-24 on 881205-09. No Violations Noted.Major Areas Inspected:Safe Shutdown Capability in Event of Fire,Emergency Lighting & Corrective Actions Taken in Response to Violations Previously Noted
ML17156B004
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 01/13/1989
From: Anderson C, Krasopoulos A
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML17156B003 List:
References
50-387-88-21, 50-388-88-24, NUDOCS 8902020111
Download: ML17156B004 (14)


See also: IR 05000387/1988021

Text

U.S.

NUCLEAR REGULATORY COMMISSiON

REGION I

50-387/88-21

Report

Nos.

50-388/88-24

50-387

Docket Nos.

50-388

NPF-14

License

Nos.

NPF-22

Pr iority

Licensee:

Penns

lvania Power and Li ht Co.

2 North Ninth Street

Allentown

PA

18101

Category

C

Facility Name:

Sus

uehanna

Steam Electric Station

Units

1 and

2

Inspection At:

Allentown

Penns

lvania and

Salem Townshi

Penns

lvania

Inspection

Conducted:

December

5-9

1988

Inspector:

A. G. Krasopoulos,

R actor Engineer

ate

Also participating

and contributing to the report were

R. Hodor, Mechanical

Systems Specialist,

BNL

K. Sullivan, Electrical

System Specialist,

BNL

Approved by:

C. J. Anderson,

Chief, Plant Systems

Section,

DRS

"/v

date

Ins ection Summar:

Ins ection

on December

5-9

1988

Ins ection

Re ort

Nos.

50-387/88-21

and 50-388/88-24

h

d

capability of the plant in the event of a fire, and of, the

emergency lighting,

provided for that purpose.

The corrective actions

taken in response

to

violations previously identifed in this area

were also reviewed.

Results:

No violations were identified.

The actions

taken to correct the

deficiencies

previously identified in this area

were determined

to be adequate.

PD9R0~0~0>> i 8901pg

GDR 'DOCK 0500008~

PNU

DETAILS

1.0

Persons

Contacted

- Penns

lvania

Power and Li ht

PPBL

J. Blakeslee,

Assistant Plant Superintendent

F. McCreesh,

Project Engineer

J..Rothe,

Supervising

Engineer,

Electrical

S. Davis, Site Fire Protection

Engineer

G. Stanley, Assistant

Outage Superintendent

R. Prego,

QA Supervisor

A. Dominguez,

Sr.

Results

Engineer,

Operations

C. Coddington,

Sr. Project Engineer

D. Klinger, Appendix

R Project Site Manager

W. Williams, Licensing

D.

Kohn, Fire Protection

Engineer

B. Slusser,

Outage

Management

D. Roth, Sr.

Compliance

Engineer

W. Barberich,

Manager,

Nuclear Planning

and Licensing

M. Gorski, Project Engineer

D. 2aprazny,

Project Engineer

A. Mihalic, Sr.

Engineer

G. Wetzel,

Sr. Project Engineer

A. White,

Systems

Engineering

R.

Tombasco,

Electrical Analyst

T. Gorman,

Supervisor

Nuclear Design

K. Backenstor,

Sr. Project Engineer

B. Palmer,

Project Engineer,

I&C Engineering

J.

Delgado,

Project Engineer,

NPE

CED

D. Parsons,

Supervising

Engineer,

NPE

2.0

Pur ose

and

Sco

e

makaaa r

a

This inspection

was conducted

to verify compliance with the

10 CFR 50,

Appendix

R Sections III.G and III.J.

This regulation requires that the

licensee

be capable of shutting

down the reactor in the event of a fire

and that emergency lighting be installed for this purpose.

The corrective actions for the violations identified in this area

from

a

previous inspection

conducted

during February

11-15,

1985 were

also'eviewed.

3.0

~Back round

The licensee

via

a license condition is required to comply with the

requirements

of 10 CFR 50a48

and

10 CFR 50 Appendix

R Sections III.G and

J.

Section III.G of Appendix

R requires that fire protection features

be provided to ensure that

one train of equipment

necessary

to achieve

and maintain

s'afe

shutdown

remains available

in the event of a fire at

any location within the facility.

Section III.J of Appendix

R requires that emergency lighting be installed

to facilitate the

shutdown of the reactor in the event of a fire.

The

NRC during the week of February

11-15,

1985 conducted

an inspection

to verify the licensee's

abili.ty to safely

shutdown the reactors

(Susquehanna

Units 1&2) in accordance

with the requirements

described

above.

The inspection results

were documented

in combined inspection

Report

No. 50-387/85-06

and 50-388/85-06.

These results'included

a number of Unresolved

Items that were later

determined

to be violations of the requirements.

An enforcement

conference

was held

on October

1,

1985 at, the

NRC Region I offices.

A Notice of Violation was transmitted

to the licensee

by letter dated

June

15,

1987.

This notice contained

two violations of the Appendix

R

requirements.

Violation I contained

three

examples of violations from the

10 CFR 50,

Appendix

R Section III.G requirements.

These

three

examples

were

described

as Unresolved

Items 50-387/85-06-02,

50-388/85-06-02,

50-388/85-06-03

and 50-388/85-06-04.

The resolution of these

items

and

the closure of the violations is described

in the section that follows.

Violation II described

a violation of the Appendix

R,Section III.J

requirements.

The corrective actions to this violation were reviewed

by

the

NRC resident staff and were found acceptable.

This was previously

documented

in report

No. 50-388/86-04.

In addition to the violations listed above,- the inspection report contained

an unresolved

item regarding

a concern that the licensee's fire hazard

analysis,

performed to verify the plant's

safe

shutdown capability was

inadequate.

This concern

was listed

as Unresolved

Item 50-387/85-06-01

and 50-388/85-06-01.

The licensee

committed to perform

a reanalysis

of the safe

shutdown

methodology to address

this concern.

A letter dated

December

18,

1985,

from the. licensee

stated that this reanalysis

had been initiated and would

be completed

by the fourth quarter of 1986 or the first quarter of 1987.

The licensee

completed

and docketed this

new Fire Hazard Analysis, on

June

30,

1988.

4.0

Follow u

of

revious

ins ection findin

s

Closed

Unresolved

Item

50-387/85-06-01

5 50-388/85-06-01

Fire= Hazard Analysis inade

uate to

show

com liance with A

endix

R

The

NRC determined

that the licensee's

fire hazard analysis

was

inadequate

in that it failed to demonstrate

that redundant

safe

shutdown

components

would be available if a fire occurred "anywhere

in the plant.

The licensee

committed to review and revise their Fire Hazard Analysis

to'ssure

that if a fire occurred

anywhere

in the plant one safe

shutdown

train would remain free of fire damage.

The licensee initially planned to revise the original docketed

Fire Hazard

Analysis.

This is the document reviewed'y the

NRC team in February of

1985.

Because

of problems associated

with document retrieval,

the licensee

determined that it would be better to develop

a

new fire hazard analysis

which would be developed with in-house expertise.

They had difficulty in

retrieving the data

base

used

in the original fire hazard analysis.

The

licensee

completed this

new analysis titled Fire Protection

Review Report,

Revision 3,

and placed it on the docket

on June

30,

1988.

The team reviewed this document

and did not identify any unacceptable

'onditions.

The analysis

reviewed,

provides

assurance

that one

shutdown

train will remain free of fire damage.

However,

the

team stated

to the

licensee

that the analysis

and

shutdown methodology contained

in this

document

has not been

reviewed by the

NRC office at

NRR.

Since

an

SER has

not been

issued

on the

new methodology,

the final acceptance

of the

analysis will be based

on the acceptability of this document

by NRR.

This item is resolved.

Closed

Violation

50-387/85-06-02

and 50-388/85-06-02

.

Inade uate fire

barriers

se gratin

the redundant

residual

heat

removal

RHR

um s.

The

NRC identified the concern that the fire barriers

separating

the

RHR

pumps were not fire rated because

the doors installed

on these fire

barriers did not have

a fire rating.

Additionally these barriers

contained

a seismic

gap not sealed with a fire sealant'his

was

deemed

to be

a violation of the fire separation criteria set forth in Appendix

R.

The licensee

acknowledged this violation and instituted corrective

actions that included the following:

1.

The licensee

requested

a deviation from the requirement to have

three hour rated doors

on the wall separating-the

RHR Pumps.

The

justification given was that the doors installed,

although unrated,

are of substantial

construction

having been built out of steel

plate

and they are watertight.

These

doors were evaluated

by Factory

Mutual

and

found to be

an adequate fire bar rier for the existing fire

hazard.

The licensee

has

sealed

the seismic

gap with a fire rated seal.

The

design

and installation of this seal

does

not compromise

the

function of the seismic

gap

~

The licensee

has established

a fire watch to patrol

the

RHR pump

room pending

NRC approval of the above deviation request.

This violation is closed.

Closed

Violation

50-388/85-06-03

Inade uate Fire Wra

enclosure

on

safe

shutdown

racewa

s.

The

NRC determined that certain electrical

raceways

containing cables

required for shutdown

were improperly wrapped.

The specific concern

was

,

that the wrap did .not extend

the entire length of th'e fire area.

Thus,

a

fire in the fire area

where the raceway

was not wrapped could subject the

raceway to fire damage.

The licensee

acknowledged

the violation.

However, their response

indicated that three

raceways identified in the violation were not

required for shutdown.

The fourth raceway

needed fire wrap protection

because

the

new analysis

indicated that this raceway is now required

(Raceway

No.

E2KJ19) to be protected.

In addition, the licensee

completed

the -analysis that identified all

raceways

containing safe

shutdown cables.

The raceways requiring protec-

. tive wrap were also identified.

The work to provide this wrap has

com-

menced

and is scheduled

to be completed

by December

31,

1989.

This

completion date

was committed to via a letter to

NRC dated

June

30,

1988.

This was previously discussed

in a management

meeting held at the Region I

offices

on March 31,

1988.

The inspector

observed

work in progress

and did not identify any

unacceptable

conditions.

This violation is closed

5.0

Post-Fire

Safe

Shutdown

Ca abilit

and Shutdown Methodolo

The Fire Protection

Review Report,

Revision 3, docketed

on June

30,

1988,

describes

the post-fire safe

shutdown capability with and without offsite

power and the remote

shutdown capabi-lity (from outside

the main

control room).

1

The analysis

in the report uses (with one exception)

the fire area

concept.

The analysis

assumes

the loss of all safe

shutdown

equipment

within the fire area.

Fire barriers

assure

that the fire will not

propagate

beyond the fire area

boundaries.

The analysis

then assures

that

either redundant

or alternative

shutdown

systems exist'o

compensate

for

the

systems

assumed

lost in the fire.

With regard to the exception

mentioned

above,

in the Reactor Building, the

licensee

uses

a fire break

zone referred to as the wrap-around

zone.

Within

this zone,

the licensee

wrapped all safe

shutdown cables

and raceways with

fire protective wrap.

Thus, the, reactor building is divided into two fire

areas

separated

by the wrap-around

zone.

This zone

separates

the

Division I from the Division II equipment.

For post-fire safe

shutdown,

the licensee

has identified Safe

Shutdown

Paths

1, 2,

and 3.

The Division I train of ADS/Core Spray, Alternate

Shutdown Cooling,

and Suppression

Pool Cooling is utilized for Path

1.

The Division II train of ADS/Core Spray, Alternate

Shutdown Cooling and

Suppression

Pool Cooling is used for Path 3.

Simultaneous

shutdown of

both units is achieved

by using safe

shutdown path

1 or 3 for the affected-

unit (the unit where the fire occurred).

The

HPCI or RCIC systems

along

with the associated

support

systems

are

used to provide reactor coolant

makeup for the unaffected Unit.

Alternate

Shutdown Cooling and Suppression

Pool Cooling capability for the unaffected unit is provided by using

Paths

1 or

3 described

above.

Path

2 is the Alternative Shutdown

Path

and is the path

used for a

Co'ntrol'oom

fire.

This requires

shutdown

from outside the Control

Room using the

remote

shutdown panels.

The Reactor Coolant Inventory Control for Paths

1 and

3 is provided by

the Core Spray

System taking suction, from the suppression

pool after

the reactor is de-pressurized

by-the

ADS.

Safety Relief Valves (SRV's)

RCIC and

HPCI are

assumed

either

damaged

by fire or unavailable.

The

licensee

has submitted Appendix

R Deviation Request

No.

33 to address

the

fact th'at the reactor coolant process

variables

are not maintained

strictly within those predicted for a loss of offsite power (a faster

de-pressurization

rate,

and lower level than level 2).

For the Control

Room fire and subsequent

evacuation

scenario,

the

RCIC system taking

suction from the Condensate

Storage

Tank is used for reactor vessel

inventory control

(Shutdown

Path 2).

For Reactor

Pressure

Control

and

Decay Heat

Removal for Paths

1 and

3, the licensee is using Manual

ADS operation

along with the

RHR in

the suppression

pool cooling mode.

The A, B, and

C SRV's and Suppression

Pool cooling are

used for Path

2.

6.0

Ins ection Methodolo

The inspection

team examined

the licensee's

capabilities for separating

and protecting equipment,

cabling

and associated

circuits necessary

to

achieve

and maintain hot and cold shutdown conditions.

The inspection

sampled

selected fire areas

which the licensee

had identified as being

bounded with fire rated walls and also

reviewed the wrap around

zone.

The following functional requirements

were reviewed for achieving

and

maintaining hot and cold shutdown:

React,ivity control

Pressure

control

Reactor coolant

makeup

Decay heat

removal

Support

systems

Process

monitoring

The inspection

team also

examined

the licensee's

capability'o achieve

and maintain hot shutdown

and the capability to bring the plant to cold

shutdown condition in the event of a fire in areas

where

remote

shutdown

capability is provided.

The examination

included

a review of the drawings

for the remote

shutdown capability and

a review of the procedures

for

achieving

remote

shutdown.

Drawings were reviewed to verify electrical

independence

from the areas of concern.

Procedures

were reviewed for

general

content

and feasibility.

Also, inspected

were fire detection

and suppression

systems

and the degree

of physical

separation

between

redundant trains of Safe

Shutdown

Systems

(SSSs).

The team review included

an evaluation of the susceptibility of

the

SSSs for damage

from fire suppression

activities or from the rupture

or inadvertent operation of the fire .suppression

systems.

4

The inspection

team examined

the licensee's

fire protection features

provided to maintain

one train of equipment

needed for safe

shutdown free

of fire damage.

Included in the

scope of this effort were fire area

boundaries.

This included walls, floors and ceilings,

and the protection

of openings

such

as fire doors, fire dampers,

and penetration

seals.

The inspection

team also examined

the emergency lighting for areas

of the

plant necessary

for safe

shutdown.

7.0

Ins ection of Protection

Provided to Safe

Shutdown

S stems

7. 1

Protection

in Various Fire Areas

The team randomly reviewed the protection provided to SSSs

in

selected fire areas for compliance with the applicable

NRC

requirements

and licensee

commitments

towards Appendix

R.

No unacceptable

conditions were identified.

,

7.2

Safe

Shutdown

Procedures

7.2. 1

Procedure

Review

The team reviewed the following safe

shutdown

procedure

~

E0-100-009,

Plant

Shutdown

from Outside Control- Room,

Revision

11.

(Unit 1)

~

E0-200-009,

Plant Shutdown

from Outside Control

Room,

Revision

12.

(Unit 2)

The

scope of review was:

to ascertain

that the

shutdown

could be attained

in

a safe

and orderly manner;

to

determine

the level of difficulty involved in operating

equipment;

and to verify that there

was

no dependence

on

repairs for achieving hot shutdown.

For the purpose of the

review,

a repair would include installing electrical

or

pneumatic jumpers, wires or fuses

to perform an action

required for hot shutdown.

The team did not identify any unacceptable

conditions.

7.2.2

Procedure

Walk-Throu

h

The team walked through selected

portions of the procedures

to determine that shutdown could be attained in an orderly

and timely fashion.

I

The team did not identify any unacceptable

conditions,

7.3

Protection for Associated Circuits

Appendix

R,Section III.G, requires that protection

be provided for

associated

circuits that could prevent operation

or cause

maloperation

of redundant trains of systems

necessary

for safe

shutdown.

The circuits of concern

are generally associated

with

safe

shutdown circuits in one of three ways:

~

Common bus concern

~

Spurious

signals

concern

~

Common enclosure

concern

The associated

circuits were evaluated

by the team, for common bus,

spurious

signal

and

common enclosure

concerns.

Power, control,

and

instrumentation circuits were examined

on

a sampling basis for

potential

problems.

Common

Bus Concern

The

common

bus concern

may be found in circuits, either

safety related

or non-safety related,

where there is

a

common

power source with shutdown

equipment

and the

power

source is not electrically protected

from the circuit of

concern.

The

team examined,

on

a sampling basis,

4160VAC,

480VAC,

250VOC,

125VOC and

120

VAC bus protective relay

coordination.

The team also examined,

on

a sampling

basis,

the protection for specific instrumentation,

controls,

and

power circuits, including the coordination

~ of fuses

and circuit

breakers.'he

following deficiencies

were identified:

Circuit Breaker Coordination

and Maintenance

The licensee

performed. an analysis

addressing

the

common

power source

concern.

.This analysis is contained

in

Report SEA-EE-40,

Revision l.

This report contains

recommendations

for modifications to

be performed

where

an acceptable

level of circuit coordina-

tion could not be demonstrated.

The team observed that

most of these modifications were already properly "dispositioned

and implemented.

However, this analysis identified the

following changes

that are required to be performed.

480V Load Center

1B210

28210

28230

Breaker

21

21

21

If

~Chan

e

For improved ground

fault coordination

all three breakers

sh'ovid have the

time delay band

changed 'from "MIN"

to "INTERMEDIATE"

2B210

2B220

1B220

1B230

1B240

13

13

13

2323'hort

time pickup

setting

from 3X-4X

Short time pickup

setting

from 3X-4X

Short time pickup

setting

from 6X-4X

Long'ime pickup

.

from 1.1 to 1.0

Long time, pickup

from "MAX" to

"INTERMEDIATE"

10

480V

MCC

2B247

Breaker

33

~Chan

e

Verify that the

instantaneous

setpoint is not

higher than

5>(

rated

Subsequent'o

this finding the'licensee

initiated

Engineering

Work Request

(EWR) Number M81474 dated

Oecember

6,

1988.

The intent of this

EWR is to evaluate

and resolve

the

480V circuit changes

identified in

SEA-EE-040.

The licensee

explained,

that the reason

these

required

modifications were not completed

was the erroneous

assumption

that these modifications were not required.

The team observed that the improperly coordinated circuits

identified represent

an isolated

example of non-coordinated

circuits.

Overall circuit coordination will be accomplished

when the modifications are complete.

With regard to circuit breakers,

an additional

concern

was

raised

by the

team

upon determining that the licensee

does

not perform scheduled

maintenance

on circuit breakers

at

the

480V load center level

and below.

Maintenance

should

be performed

on the breakers if credit for proper

breaker'oordination

is taken.

This is collectively an unresolved

item pending

a review

of the actions

taken

by the licensee

in response

to the

NRC

observations

(50-3987/88-21-01

and 50-388/88-24-01).

Anal sis of Hi

h

Im cdance

Faults

The inspection

team observed that the licensee

does not-

have specific procedures

to clear high impedance faults

nor do they have

an analysis

assuring

that

such faults

are not likely to occur.

The licensee

stated

that if such a-fault occurs

the

operators

would attempt to restore

the lost bus

by resetting

the upstream

breaker to the bus.

If this simple action is

unsuccessful,

the operators notify maintenance

to trouble-

shoot

and restore

the bus.

11

The

NRC concern is that maintenance

personnel

may not be

available

should high impedance faults occur during

a

fire.

This issue is currently being reviewed

by

NRR as part, of

the Fire Hazard Report Evaluation

and issuance

of the

Safety Evaluation Report.

7.3.2

S urious Si nals'oncern,

The spurious

signal

concern is made

up of two items:

False motor, control,

and instrument indications

can

occur

such

as those

encountered

during

1975 Browns

Ferry fire.

These could

be caused

by fire initiated

grounds,

short or

open ci rcuits.

~

Spurious operation of safety related or non-safety

related

components

can occur that would adversely

affect shutdown capability (e.g.,

RHR/RCS isolation

valves).

The team examined,

on

a sampling basis,

the following

areas

to ascertain .that

no spurious

signal

concern exists:

P

~

Current transformer

secondaries

~

High/low pressure

interface

~

General fire instigated

spurious

signals

Deficient conditions were identified as follows:

Communication

S stem Reliabilit

for a Control

Room Fire

The licensee's

alternate

shutdown

procedure,

indicates that

radio communication will be required for use

by the

operators

in the event of a Control

Room fire requiring

evacuation

and

shutdown

from outside the Control

Room.

However,

the licensee

did not include the communications

circuitry within the

scope of the Appendix

R analysis.

Mhile several

communication

systems

may be available,

the

ability of one communication

system to perform its function

in the event of a

Control

Room fire has not been conclusively

established.

The licensee initiated

NCR Number

88-0736'ated

December

6,

1988 to resolve this issue.

12

Pending

the licensee's

evaluation of the existing

'communication

system

and the implementation of any

modifications, this is an unresolved

item.

(50-387/88-21-02

and 50-388/88-24-02)

7.3.3

Common Enclosure

Concern

The

common enclosure

concern

may be found when redundant

circuits are routed together

in

a raceway or enclosure

and

they are not electrically protected

or when fire can

destroy both circuits due to inadequate fire barrier

penetrations.

A number of circuits, selected

on

a sampling basis,

were

examined for this concern.

No unacceptable

conditions. were identified.

8.0

Unresolved

Items

Unresolved

items are matters for which more information is required in

order to ascertain

whether they are acceptable,

violations, or

deviations.

Unresolved

items are discussed

in Sections

7.3. 1 and 7.3.2.

9.0

Exit Interview

The inspection

team met with the licensee

representatives,

denoted

in

Section 1.0, at the conclusion of the inspection

on December

9,

1988.

The team leader

summarized

the

scope

and findings of the inspection at

that time.

The team leader also confirmed with the licensee

that the documents

reviewed

by the

team did not contain

any proprietary information.

The

licensee

agreed that the inspection report

may be placed

in the Public

Document

Room without prior licensee

review for proprietary information

(10 CFR 2.790).

At no time during this inspection

was written material

provided to the

licensee

by the

team.