Category:Letter
MONTHYEARML23342A1162024-01-0909 January 2024 Independent Spent Fuel Storage Installation Security Inspection Plan L-23-019, Proof of Financial Protection 10 CFR 140.152023-12-18018 December 2023 Proof of Financial Protection 10 CFR 140.15 IR 05000219/20230022023-11-0909 November 2023 EA-23-076 Oyster Creek Nuclear Generating Station - Notice of Violation and Proposed Imposition of Civil Penalty - $43,750 - NRC Inspection Report No. 05000219/2023002 ML23286A1552023-10-13013 October 2023 Defueled Safety Analysis Report (DSAR) ML23249A1212023-09-0606 September 2023 NRC Inspection Report 05000219/2023002, Apparent Violation (EA-23-076) ML23242A1162023-08-30030 August 2023 Biennial 10 CFR 50.59 and 10 CFR 72.48 Change Summary Report January 1, 2021 Through December 31, 2022 ML23214A2472023-08-22022 August 2023 NRC Inspection Report 05000219/2023002 IR 05000219/20230012023-05-31031 May 2023 NRC Inspection Report No. 05000219/2023001 IR 07200015/20234012023-05-16016 May 2023 NRC Independent Spent Fuel Storage Installation Security Inspection Report 07200015/2023401 ML23114A0912023-04-24024 April 2023 Annual Radioactive Effluent Release Report for 2022 ML23114A0872023-04-24024 April 2023 Annual Radioactive Environmental Operating Report for 2022 L-23-004, HDI Annual Occupational Radiation Exposure Data Reports - 20222023-04-24024 April 2023 HDI Annual Occupational Radiation Exposure Data Reports - 2022 L-23-003, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-31031 March 2023 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23088A0382023-03-29029 March 2023 Stations 1, 2, & 3, Palisades Nuclear Plant, and Big Rock Point - Nuclear Onsite Property Damage Insurance ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities IR 05000219/20220022023-02-0909 February 2023 NRC Inspection Report No. 05000219/2022002 ML23031A3012023-02-0808 February 2023 Discontinuation of Radiological Effluent Monitoring Location in the Sewerage System ML23033A5052023-02-0202 February 2023 First Use Notification of NRC Approved Cask RT-100 ML23025A0112023-01-24024 January 2023 LLRW Late Shipment Investigation Report Per 10 CFR 20, Appendix G ML22347A2732022-12-21021 December 2022 Independent Spent Fuel Storage Installation Security Inspection Plan Dated December 21, 2022 ML22297A1432022-12-15015 December 2022 Part 20 App G Exemption Letter L-22-042, Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.152022-12-14014 December 2022 Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.15 IR 07200015/20224012022-12-0606 December 2022 NRC Independent Spent Fuel Storage Installation Security Inspection Report 07200015/2022401 (Letter & Enclosure 1) ML22280A0762022-11-0202 November 2022 Us NRC Analysis of Holtec Decommissioning Internationals Funding Status Report for Oyster Creek, Indian Point and Pilgrim Nuclear Power Station ML22276A1762022-10-24024 October 2022 Decommissioning International Proposed Revisions to the Quality Assurance Program Approval Forms for Radioactive Material Packages ML22286A1402022-10-13013 October 2022 NRC Confirmatory Order EA-21-041 IR 05000219/20220012022-08-11011 August 2022 NRC Inspection Report 05000219/2022001 ML22215A1772022-08-0303 August 2022 Decommissioning International (HDI) Proposed Revisions to the Quality Assurance Program Approval Forms for Radioactive Material Packages ML22214A1732022-08-0202 August 2022 Request for Exemption from 10 CFR 20, Appendix G, Section Iii.E ML22207B8382022-07-26026 July 2022 NRC Confirmatory Order EA-21-041 ML22130A6882022-05-10010 May 2022 Late LLRW Shipment Investigation Report Pursuant to 10 CFR 20, Appendix G L-22-026, Occupational Radiation Exposure Data Report - 20212022-04-29029 April 2022 Occupational Radiation Exposure Data Report - 2021 ML22118A6122022-04-28028 April 2022 Annual Radioactive Environmental Operating Report for 2021 ML22118A5822022-04-28028 April 2022 Annual Radioactive Effluent Release Report for 2021 ML22091A1062022-04-0101 April 2022 Nuclear Onsite Property Damage Insurance (10 CFR 50.54(w)(3)) L-22-022, and Indian Point Nuclear Generating Stations 1, 2, & 3 - Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations - Holtec.2022-03-25025 March 2022 and Indian Point Nuclear Generating Stations 1, 2, & 3 - Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations - Holtec. ML22069A3762022-03-10010 March 2022 Late LLRW Shipment Investigation Report Pursuant to 10 CFR 20, Appendix G ML22032A0582022-03-0808 March 2022 EA-21-139; EA-150: Oyster Creek Nuclear Generating Station - NRC Investigation Report Nos.. 1-2021-002 & 1-2021-014 ML22060A2202022-03-0202 March 2022 NRC Office of Investigations Case No. 1-2021-009 ML22049B2452022-02-19019 February 2022 Late Low Level Radwaste Shipment Report Pursuant to 10 CFR 20 Appendix G IR 05000219/20214022022-01-26026 January 2022 EA-21-041: Confirmatory Order Related to Oyster Greek Nuclear Generating Station - NRC Investigation Report I-2020-007; NRC Inspection Report Nos. 05000219/2021402 & 07200015/2021401 ML22025A3422022-01-25025 January 2022 and Big Rock Point - Changes to Site Organization ML22025A2182022-01-25025 January 2022 Late LLRW Shipments Investigation Report Pursuant to 10 CFR 20, Appendix G ML22021B5512022-01-21021 January 2022 Compensatory Measures Not Implemented Per Site'S Physical Security Plan Due to Multiplexer (Mux) Power Supply Failure L-21-134, and Indian Point Nuclear Generating Stations 1, 2, & 3 - Report on Status of Decommissioning Funding for Independent Spent Fuel Storage Installations2021-12-17017 December 2021 and Indian Point Nuclear Generating Stations 1, 2, & 3 - Report on Status of Decommissioning Funding for Independent Spent Fuel Storage Installations ML21349A5192021-12-15015 December 2021 Commitment Change Summary Report ML21285A1912021-11-30030 November 2021 Nrc'S Analysis of Holtec Decommissioning International'S Decommissioning Funding Status Report for Oyster Creek Nuclear Generating Station and Pilgrim Nuclear Power Station, Docket Nos 50-219 and 50-293 IR 05000219/20210032021-11-16016 November 2021 NRC Inspection Report No. 05000219/2021003 L-21-118, Changes to Signature Authority & Addressee for Holtec Decommissioning International, LLC Correspondence Re to Oyster Creek Nuclear Generating Station, Pilgrim Nuclear Power Station, Indian Point Nuclear Generating Units 1, 2, 3, & Palisades2021-11-0909 November 2021 Changes to Signature Authority & Addressee for Holtec Decommissioning International, LLC Correspondence Re to Oyster Creek Nuclear Generating Station, Pilgrim Nuclear Power Station, Indian Point Nuclear Generating Units 1, 2, 3, & Palisades IR 05000219/20214042021-08-26026 August 2021 NRC Independent Spent Fuel Storage Security Inspection Report No. 07200015/2021402 and Security Decommissioning Inspection Report 05000219/2021404 - (Public) 2024-01-09
[Table view] Category:License-Operator
MONTHYEARML18005A4202018-01-0303 January 2018 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2018 ML17156A5502017-06-0505 June 2017 Requalification Program Inspection - Oyster Creek Nuclear Generating Station RS-17-070, Response to NRC Regulatory Issue Summary 2017-03, Preparation and Scheduling of Operator Licensing Examinations2017-05-0303 May 2017 Response to NRC Regulatory Issue Summary 2017-03, Preparation and Scheduling of Operator Licensing Examinations ML17018A2822017-01-17017 January 2017 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2017 RS-16-156, Response to NRC Regulatory Issue Summary 2016-09, Preparation and Scheduling of Operator Licensing Examinations2016-07-18018 July 2016 Response to NRC Regulatory Issue Summary 2016-09, Preparation and Scheduling of Operator Licensing Examinations ML17261B0602016-02-16016 February 2016 Final QA Related Forms (Folder 1) ML16064A1772016-02-10010 February 2016 Final Written Examination with Answer Key (401-5 Format) (Folder 3) ML17216A1722016-02-10010 February 2016 Draft Operating Exam (Sections a, B and C) (Folder 2) ML17216A1742016-02-10010 February 2016 Draft Written Exam (Folder 2) ML17261B1652016-02-10010 February 2016 Final Outlines (Folder 3) ML17261B1672016-02-10010 February 2016 Draft - Outlines (Folder 2) ML17261B1682016-02-10010 February 2016 NRC Comments on Draft Licensee-Developed Exam (Written) (Folder 2) ML17261B1692016-02-10010 February 2016 NRC Comments of Draft Licensee-Developed Exam (Operating) (Folder 2) ML16064A1712016-02-10010 February 2016 Final Operating Exam (Sections a, B, and C) (Folder 3) ML16026A5812016-01-26026 January 2016 Initial Operator Licensing Operating Test and Written Examination Approval - Oyster Creek Nuclear Generating Station ML14311A6622014-11-0303 November 2014 September 10, 2014, NRC Generic Fundamentals Examination Results - Oyster Creek Nuclear Generating Station Cover Letter ML15016A1462014-06-0404 June 2014 Miscellaneous Exam Material (Folder 1) ML14163A3872014-05-28028 May 2014 Handouts to Applicants, Summary of References (Folder 3) ML14139A0052014-05-16016 May 2014 Initial Operator Licensing Operating Test and Written Examination Approval-Oyster Creek Nuclear Generating Station ML15016A1522014-05-13013 May 2014 Final Outlines (Folder 3) ML14163A3882014-05-13013 May 2014 Final Operating Exam (Sections a, B, and C) (Folder 3) ML14163A3862014-05-13013 May 2014 Final Written Examination with Answer Key (405-5 Format) (Folder 3) ML14167A3122014-05-0707 May 2014 NRC Comments on Draft Licensee-Developed Exam (Operating) (Folder 2) ML14167A3232014-05-0505 May 2014 NRC Comments on Draft Licensee-Developed Exam (Written) (Folder 2) ML14167A3842014-04-0202 April 2014 Draft Operating Exam (Sections a, B, and C) (Folder 2) ML14167A2982014-04-0202 April 2014 Draft Outlines (Folder 2) ML14167A3682014-04-0202 April 2014 Draft Written Exam (Folder 2) RS-12-114, (EGC) - Response to NRC Regulatory Issue Summary 2012-07, Preparation and Scheduling of Operator Licensing Examinations2012-07-0505 July 2012 (EGC) - Response to NRC Regulatory Issue Summary 2012-07, Preparation and Scheduling of Operator Licensing Examinations IR 05000219/20123012012-06-18018 June 2012 Er 05000219-12-301; 5/14/2012 - 5/24/2012; Oyster Creek Nuclear Generating Station; Initial Operator Licensing Examination Report ML12172A0692012-06-13013 June 2012 Final Qa/Related Forms (Folder 1) ML12165A6092012-06-0606 June 2012 Final Written Examination with Answer Key (401-5 Format) (Folder 3) ML12165A6012012-06-0606 June 2012 Final Outlines (Folder 3) ML12159A2442012-06-0101 June 2012 NRC Comments on Draft Licensee-Developed Exam (Written) (Folder 2) ML12159A3912012-06-0101 June 2012 Draft Written Exam (Folder 2) ML12159A2582012-06-0101 June 2012 Draft - Outlines (Folder 2) ML12159A2522012-06-0101 June 2012 NRC Comments on Draft Licensee-Developed Exam (Operating) (Folder 2) ML12165A6352012-06-0101 June 2012 Handouts to Applicants (Folder 3) ML12128A2242012-05-0707 May 2012 Initial Operator Licensing Operating Test and Written Examination Approval - Oyster Creek Nuclear Generating Station, ML1130000532011-10-27027 October 2011 Announcement of Generic Fundamentals Examination 2012 Administration Dates IR 05000219/20113012011-08-11011 August 2011 Er 05000219-11-301, July 11-20, 2011, Oyster Creek Nuclear Generating Station; Initial Operator Licensing Examination Report ML12017A1642011-07-30030 July 2011 Draft - Outlines (Folder 2) ML1124903532011-07-28028 July 2011 Final Qa/Related Forms (Folder 1) ML1121305252011-07-11011 July 2011 Final Outlines (Folder 3) ML1121305282011-07-0606 July 2011 Final Written Examination with Answer Key (401-5 Format) (Folder 2) ML1121305342011-07-0606 July 2011 Summary of Handouts to Applicants (Folder 3) ML1121305412011-07-0606 July 2011 Final Operating Exam (Sections a, B, and C) (Folder 3) ML1118101102011-06-30030 June 2011 Operator Licensing Examination Approval (Oyster Creek) ML1118702612011-06-27027 June 2011 NRC Comments on Draft Licensee-Developed Exam (Operating) (Folder 2) ML1118701862011-06-27027 June 2011 NRC Comments on Draft Licensee-Developed Exam (Written) (Folder 2) ML1118702782011-05-27027 May 2011 Draft Operating Exam (Sections a, B, and C) (Folder 2) 2018-01-03
[Table view] Category:Requalification Program Audit
MONTHYEARML17156A5502017-06-0505 June 2017 Requalification Program Inspection - Oyster Creek Nuclear Generating Station 2017-06-05
[Table view] |
Text
B. Hanson UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BLVD.
KING OF PRUSSIA, PA 19406-2713 June 5, 2017 Mr. Bryan Hanson Senior Vice President, Exelon Generation Co., LLC President and Chief Nuclear Officer, Exelon Nuclear 4300 Winfield Rd.
Warrenville, IL 60555
SUBJECT:
REQUALIFICATION PROGRAM INSPECTION - OYSTER CREEK NUCLEAR GENERATING STATION
Dear Mr. Hanson:
In a telephone conversation on May 24, 2017, Mr. Brian Fuller, Senior Operations Engineer, and Mr. Michael Rossi, Licensed Operator Requalification Training Lead, made arrangements for the U.S. Nuclear Regulatory Commission (NRC) to inspect the licensed operator requalification program at the Oyster Creek facility. The inspection is planned for the week of June 12, 2017, which coincides with your regularly scheduled requalification examination cycle. The staff at your facility should prepare and conduct the requalification examinations in accordance with your NRC-approved requalification program.
In accordance with 10 CFR 55.59(c), the NRC may request facility licensees to submit their biennial comprehensive requalification written examinations or annual operating tests as necessary to support the NRC's inspection program needs. In order for the NRC to adequately prepare for this inspection, please furnish: 1) an index or summary of condition reports written in the past two years in which licensed operator errors were determined to be the root or contributing cause; 2) an index or summary of condition reports written in the past two years on simulator performance problems; 3) an index or summary of simulator performance test results in the past two years; and 4) the examination schedule, sample plan, written examinations and operating test scheduled for the week of the inspection to the NRC by June 12, 2017. Mr. Rossi has been advised of this request and provided with the name and address of the NRC lead inspector assigned to this inspection.
This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of Management and Budget, approval number 3150-0018.
The public reporting burden for this collection of information is estimated to average 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> per response, including the time for reviewing instructions, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of these information collections, including suggestions for reducing the burden, to the Records and FOIA/Privacy Services Branch (T-5 F52), U.S.
Nuclear Regulatory Commission, Washington, D.C. 20555-0001, or by Internet electronic mail to INFOCOLLECTS@NRC.GOV; and to the Desk Officer, Office of Information and Regulatory
B. Hanson 2 Affairs, NEOB-10202, (3150-0018), Office of Management and Budget, Washington, D.C.
20503.
The NRC may not conduct or sponsor, and a person is not required to respond to, a collection of information unless it displays a currently valid OMB control number. In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (The Public Electronic Reading Room).
Thank you for your cooperation in this matter. If you have any questions regarding this inspection, please contact Brian Fuller at (610) 337-5077.
Sincerely,
/RA/
Donald E. Jackson, Chief Operations Branch Division of Reactor Safety Docket No. 50-219 License No. DPR-16 cc: Distribution via ListServ