Forwards IE Insp Repts 50-387/79-41 & 50-388/79-22 on 791203-800104 & Notice of Violation
ML17138B273
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 02/01/1980
From: Robert Carlson
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Curtis N
PENNSYLVANIA POWER & LIGHT CO.
Shared Package
ML17138B271 List:
References
NUDOCS 8005020143
Download: ML17138B273 (3)


See also: IR 05000387/1979041

Text

6P,II RE00

~Ci+

'p0

Cy

  • 00

I

4~*~4

Docket Nos.

50-387

50-388

UNITEDSTATES

NUCLEAR REGULATORY COMMISSION

REGION I

631 PARK AVENUE

KING OF PRUSSIA, PENNSYLVANIA19406

tB c3 6@

Pennsylvania

Power

& Light Company

ATTN:

Mr. Norman

W. Curtis

Vice President

Engineering

and Construction

(N-4)

2 North Ninth Street

Allentown, Pennsylvania

18101

Gentlemen:

Subject:

Combined Inspection. Report Nos. 50-387/79-41;

50-388/79-22

This refers to the inspection

conducted

by Mr. R.

M. Gallo of this office on

December 3, 1979-January

4, 1980, of activities at Susquehanna

Steam Electric

Station Units

1 and 2, Salem Township, Pennsylvania

authorized

by

NRC License

Nos.

CPPR-101

and

CPPR-102

and to the discussions

of our findings held by Mr. R.

M. Gallo with Mr. J.

Green

and others of your staff at the conclusion of the

inspection.

Areas

examined during this inspection

are described

in the Office of Inspection

and Enforcement

Inspection

Report which is enclosed with this letter.

Within

these

areas,

the inspection consisted of selective 'examinations

of procedures

and representative

records,

interviews with personnel,

and observations

by the

inspector.

Based

on the results

of, this inspection, it appears

that one of your activities

was not conducted .in .full compliance with NRC requirements,

as set forth in the

Notice of Violation, enclosed

herewith

as Appendix A.

This item of noncompli-

ance

has

been categorized

into the levels

as described

in our correspondence

to

you dated

December

31, 1974.

This notice is sent to you pursuant to the pro-

visions of Section

2.201 of the NRC's "Rules of Practice," Part 2, Title 10,

Code of Federal

Regulations.

Section

2.201 requires

you to submit to this

office, within thirty (30) days of your receipt of this notice,

a written

statement

or expl'anation in reply including:

(1) corrective steps

which have

been taken

by you and the results

achieved;

(2) corrective steps

which will be

taken to avoid further items of noncompliance;

and (3) the date

when full com-

pliance will be achieved.

8005000 l+'0

Pennsylvania

Power

8l Light Company

In accordance

with Section 2.790 of the NRC's "Rules of Practice,"

Part

2, Title 10,

Code of Federal

Regulations,

a copy of this letter and the

enclosures will be placed in the NRC's Public Document

Room. If this

report contains

any information that you (or your contractor)

believe to

be proprietary, it is necessary

that you make

a written application

within 20 days to this office to withhold such information from public

disclosure.

Any, such application must be accompanied

by an affidavit

executed

by the owner of the information, which identifies the document

or part 'sought to be withheld,

and which contains

a statement of reasons

which addresses

with specificity the items which will be considered

by

the Commission

as listed in subparagraph

(b) (4) of Section 2.790.

The

information sought to be withheld shall

be incorporated

as far

as possible

into a separate

part of the affidavit. If we do not hear from you in

this regard within the specified period,

the report will be placed in

the Public Document

Room.

Should you have any questions

concerning this inspection,

we will be

pleased

to discuss

them with you.

Si'ncerely,

Robert T. Carlson,

Chief

Reactor Construction

qnd Engineering

Support Branch

Enclosures:

1.

Appendix A, Notice of Violation

2.

Office of Inspection

and Enforcement,

Combined Inspection

Report Numbers

50-387/79-41

and 50-388/79-22

cc w/encls:

A. R. Sabol,

Manager,

Nuclear guality Assurance

H.

E. Barberich, Licensing Enginee}

S.

H. Cantone,

Superintendent

of Plant