Forwards IE Insp Repts 50-387/79-36 & 50-388/79-19 on 791029-1102 & Notice of Violation
ML17138B183
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 01/23/1980
From: Robert Carlson
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Curtis N
PENNSYLVANIA POWER & LIGHT CO.
Shared Package
ML17138B181 List:
References
NUDOCS 8004070385
Download: ML17138B183 (2)


See also: IR 05000387/1979036

Text

~II IISCII

~C

'tp.0

Cy

e

C

UNITED STATES

NUCLEAR REGULATORY COMMISSION,

REGION I

63 I PARK AVENUE

KING OF PRUSSIA, PENNSYLVANIA19406

gag R3 I650

Docket Nos.

50-387

50-388

Pennsylvania

Power and Light Company

ATTN: Nr. Norman

M. Curtis

Vice President

Engineering

and Construction

2 North Ninth Street

Allentown, Pennsylvania

18101

Gentlemen:

Subject:

Combined Inspection Reports

50-387/79-36

and

50-388/79-19

This refers to the inspection

conducted

by Mr.. R. Paolino of this office

on October

29 - November. 2,

1979 at Susquehanna

Steam Electric Station

Units

1 and 2, located at Berwick, Pennsylvania'f activities authorized

by

NRC License

No.

CPPR-101

and

CPPR-102

and to the discussions

of our

findings held by Nr. Paolino with Nr. J.

D. Green

and other.

members of

your staff at the conclusion of the inspection.

Areas

examined during this inspection are described

in the Office of

~

~

~

~

~

~

~

~

Inspection

and Enforcement Inspection Report which is enclosed with this

letter.

Within these

areas,

the inspection consisted of selective

examinations of procedures

and representative

records,

interviews with

personnel,

and observations

by the inspector.

Based

on the results of this inspection, it appears

that certain of your

activities were not conducted in full compliance with NRC requirements,

as set forth in the Notice of Violation, enclosed

herewith

as Appendix

A.

These

items of noncompliance

have

been categorized

into the levels

as described

in our correspondence

to you dated

December

31,

1974.

This

notice is sent to you'pursuant

to the provisions of Section

2.201 of the

NRC's "Rules of Practice," Part 2, Title 10,

Code of Federal

Regulations.

Section

2.201 requires

you to submit to this office, within twenty (20)

days of your receipt of this notice,

a written statement,

or explanation

in reply including:

(1) corrective steps

which have

been taken by you

and the results achieved;

(2} correctiVe steps

which will be taken to

avoid further items of noncompliance;

and (3) the date

when. full compliance

will be achieved.

geIIcoto +g~

Pennsylvania

Power and Light Company

In accordance with Section

2.790 of the

NRC's "Rules of Practice,"

Part 2,

Title 10,, Code of Federal

Regulations,

a copy of this letter and the

enclosures will be placed in the

NRC's Public Document

Room. If this

report contains

any information that you (or your contractor) believe to be

proprietary, it. is necessary

that you make

a written application within 20

days to this office to withhold, such information from public disclosure.

Any such application must be accompanied

by an affidavit, executed

by the

owner of the information, which identifies the document or part sought to

be withheld,

and which contains

a statement of reasons

which addresses

with

specificity the items which will be considered

by the Commission

as listed

in subparagraph

(b) (4) of Section 2.790.

The information sought to be

withheld shall

be incorporated

as far as possible into

a separate

part of

the affidavit. If we do not hear from you in this regard within the specified

period, the report will be placed in the Public Document

Room.

Should you have any questions

concerning this inspection,

we will be

pleased

to discuss

them with you.

Sincerely

obert T. Carlsan,

Chief

Reactor

Construction

and Engineering

Support Branch

Enclosure:

l.

Appendix A, Notice of Yjolati.on

2.

Office of Inspection

and Enforcement

Inspection

Combined Report 50-'387/79-36

and

50-388/79-19

cc w/encls:

A.. R. Sabol,

Manager,

Nuclear guality Assurance

N. E. Barberich, Licensing Engineer

S.

H. Cantone,

Superintendent

of Plant