ML17138B040

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-387/79-37 on 791023-24.No Noncompliance Noted.Major Areas Inspected:Mods to Recirculation Sys & Inspectability of Sweepolet to Riser Double Weld Configuration
ML17138B040
Person / Time
Site: Susquehanna Talen Energy icon.png
Issue date: 11/19/1979
From: Jernigan E, Lester Tripp, Walton G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML17138B039 List:
References
50-387-79-37, NUDOCS 8001240099
Download: ML17138B040 (10)


See also: IR 05000387/1979037

Text

0

N

. ~50-38i 79-37

Docket No. 50-387

U.S.

NUCLEAR REGULATORY COMMISSION

OFFICE

OF INSPECTION AND ENFORCEMENT

Region I

License

No. CPPR-101

Priority

Category

C

Licensee:

Penns

lvania Power

8 Li ht

Com an

2 North Ninth Street

Allentown

Penns lvania

18101

Facility Name:

Sus

uehanna

Steam Electric Station, Unit

1

Inspection at:

Berwick and Allentown,. Pennsyl'vania

Inspection

conducted:

October 23-24,

1979

8 ../

Inspectors:

E.

p. Jernigan,reactor

Inspector

G. A. Walton, Reactor Inspector

$ >7

ate

s gne

ate sign

L. E. Tri

Chic

E

S

ranch

date signe

Approved by:

R. T;

Car iso

Chief

RCS

S

B

a

(

,5, Jn

.

E. Tripp

liief, Engineering

Support Section

No. 1,

RC8ES Branch

ate signe

//

/n

a e signe

Ins ection

Summar

ns ection

on October 23,

1979 and Meetin

on October 24,

1979

e ort

o.

-

/ 9-3

reas

Ins ecte,:

e inspection consisted of a routine,

unannounced

inspection

of on-going

mo ifications to the recirculation system

by one inspector

and one

supervisor

and of a scheduled

meeting to discuss

the inspectability of the

sweepolet to riser double weld configuration attended

by two inspectors

and two

supervisors.

The onsite effort involved 4 inspector-hours

and the meeting

involved 26 inspector-hours.

Results:

No items of noncompliance

were identified.

The

NRC positions with

respect to sweepolet to riser weld inspections

are listed in item 4 of the

tached report.

DETAILS

1.

Persons

Contacted

a.

Site Visit on October'23;

1979

Penns lvania Power

8 Li ht Com an

G. Burvis,, QA Engineer.

b..

Attendees at October

24,

1979 Meetin

Penns lvania Power

8 Li ht

Com an

(PP8L

N.

W. Curtis,

VP and Project Directoi

R.. J. Shovlin, Assistant Project Director

A. R. Sabol,

Manager,

Nuclear Quality Assurance

A. M. Male, Assistant

Manager,

Nuclear Plant Engineering

C. T.. Coddington,

Licensing Engineer

R. A.. Beckley,

NDE Coordinator

R'..L. Moore,

NDE. (Consultant)

D. B. Ritter, Engineer,

Construction

T. F. Oldenhage,

Resident= Engineer

M. Strenk,

Engineer

W. J., Rhodes,

Engineer

Bechtel

Cor oration

L. C. Oesterich,

Senior

Mechanical

Engineer

W.

C.

Koepke, Supervisor,

NDE

M. M; Rosson,. Engineering Specialist,,

NDE:.

General

Electric

J.-C. Walker, Site

QA/QC Engineering

Representative

Southwest

Research

Institute

(SwRI

G. J. Gruber, Senior Research

Scientist

W. T. Flach, Director, Engineering Services

Nuclear Ener

Services

(NES

J. J. Hobin, Project Manager

F. T., Carr, Manager,

Field Operations

Factor

'Mutual

En ineerin

Association

R.

D. Biscotti, Authorized Inspector

(ANf).'uclear

Re ulator

Commission

(NRC

Re ion I

'.

T. Carl'son, Chief, Reactor. Construction

and Engineering

Support Branch

L.. E. Tripp, Chief, Engineering Support Section

No. 1,

RC8ES Branch

E.

P., Jernigan,

Reactor

Inspector

.. G. A. Walton, Reactor Inspector

2.

Recirculation

S stem Modification Pro ram (Site)

The. inspectors

reviewed the status of the recirculation system modification

and examined the following components

and activities:

a.

Reactor

Pressure

Vessel

RPV

Recirculation

S stem Inlet*Nozzles

Safe-End

Re

acement

The inspectors

observed that welding operations

associated

with the

safe-end

replacement

were almost complete.

The inspectors

examined

the welds attaching the safe-end

to the nozzle

and the thermal

sleeve

stub tube closing weld;

Additionally,. root area

and incomplete welds

were also checked.

b.

Recirculation

S stem Riser Pi

es

The inspectors

examined

the riser pipes to determine their status.

The riser pipes were extended

on the lower end by the addition of weld

metal.

This was, necessary

to compensate

for anticipated

shrinkage

during reinstallation.

These

welds. were in the as deposited

condition

with backing rings installed.

Subsequent

operations will remove the

back rings

and machine the end-joint weld prep.

The finished weld

prep will be located in the weld metal portion of the pipe on the

lower end.

c ~

Recirculation

S stem Rin

Headers

The inspectors

examined the recirculation system ring headers.

These

headers

are in position and are located outside the

RPY and bel'ow the

recirculation system inlet nozzles.

The inspectors

observed that

machining operations

had been

completed re-establishing

the weld

preparations

to'receive

the vertical portion of the external riser

pipes.

The inspectors

noted that the new weld will be installed

approximately 3/4 inch from the original weld that remains

on each

header'opening.

The weld will result in a double weld configuration.

Additionally, the inspectors

noted the outer surface of the fabricated

header

(sweepolets)

iranediately adjacent to the existing welds to

contain

a steep

ramp.

In the present configuration, this surface

does

not appear to be appropriate to permit ultrasonic testing

(UT) of the

welds from the lower (header)

side.

Machining has

been completed

on

the ring header

openings

and the surfaces

have

been surface

examined.

The inside of the openings

have not been machined

and will remain in

the as-welded (originally) condition.

The licensee is reviewing the

examination

requirements for the inside surface.

3.

Licensee/NRC Meetin

A meeting of representatives

of the

PPEL Co.

and their consultants

and the

NRC was held at Allentown, Pennsylvania

on October 24, 1979, to assess

the

inspectability of the double welds in =the recirculation system discussed

in

Paragraph

2.c above.

This situation

was identified during a previous site

inspection

and is discussed

in ISE Report 50-387/79-30.

The removal of the nozzle safe-ends

required that two cuts

be made in each

external jet pump riser pipe located

between the ring header

and the recir-.

culation nozzle.

The licensee

determined that one cut would be at the

safe-end

weld and the other cut would be about one-inch

above the sweepolet

to riser pipe weld.

The rationale

used for this decision was, in part,

that the complete weld and heat affected

zone

(HAZ) could not be removed

due to physical limitations.

The licensee

believes that maximum assurance

against potential intergranular stress

corrosion cracking

(IGSCC) could be

gained

by overlapping the two welds- in that the riser pipe ends are clad

with a. corrosion resistant

cladding

(CRC) on the inside and outside adjacent

to the closing welds.

Since the

new weld will not affect the. unclad

base

metal in the remainder of the riser pipe=which

has

been solution heat

treated,

the licensee believes that this has

been achieved.

Additionally,

the licensee is treating this weld configuration (overlapping welds)

as

a

single weld from the standpoint of both design

and examination

requirements

with respect to Section

XI of the

ASME Code.

The licensee further contends

that Section

XI requirements

can

be satisfied

by performing

a full-vee

UT

from only the riser side of the weld using

a standard calibration block

(one not containing

a weld).

The licensee's

contractor demonstrated

the calibration/examination

technique

developed to satisfy the minimum requirements

of Section XI.

This demon-

stration utilized a standard calibration block of the required curvature/thick-

ness

and contained transverse

and radial notches

machined into its inside

and outside surfaces.

Additionally, a section of pipe containing

an over-

lapping weld was used.

This mock-up essentially

represented

the proposed

weld configuration, the sweepolet restrictions not withstanding.

For

purposes of comparing signal

responses,

the mock-up contained

notches

similar to the calibration standard.

The

UT equipment

used for this demon-

stration

was not the type that will be used during actual

weld examinations.

PPBL and their contractors

maintained that the only area

where intergranular

stress

corrosion cracking might be initiated (at the inside unclad surface

of the

HAZ on the sweepolet

side of the sweepolet

to riser pipe weld) would

be- well covered

by this technique.

Using the code required cal'ibration standard,

the licensee's

contractor

concluded that the examination would meet the minimum requirements of

Section XI of the ASME'ode.

However, there appeared

to be

some degree of

uncertainty with respect to results interpretation/evaluation

due to the

unfavorably high signal to noise ratio (particularly for the second half of

the vee) that was observed

during the demonstration.

The licensee's

present

plans call for. the double weld configuration to be

examined from both sides.

To accomplish this examination

from the sweepolet

side, it will be necessary

to prepare

the surface

by weld buildup and

machining or grinding.

The licensee

plans to characterize

and

map the

subject weld areas

by UT and

RT during preservice

examinations.

NRC Positions

The

NRC representatives

observed

the above discussed

demonstration.

Based

on this observation

and discussions

with licensee/contractor

representatives,

the

NRC representatives

concluded:

a.

The proposed

weld configuration consists of overlapping welds

and must

be treated

as two welds,

hence falling outside the strict definition

of- a weld as defined in Section XI.

b.

Section

XI requires that the entire weld volume,

HAZ and adjacent

base

metal

be scanned

in two directions

from each side of the weld(s)

when

feasible.

Since only the first one-half vee path is effective for

examination of this configuration, examination from both the sweepolet

and riser side of the subject welds is required to provide adequate

coverage

and to meet the intent of the

ASME Code.

c.

A calibration standard

containing representative

welds must

be used

during actual

weld examinations.

This standard will provide

a block

ycousticallg representative

ai'.,the area

being examined.

d.

The use of a dual element transducer

during actual'xamination

is

required.

Although the demonstrated

equipment

was not of the field

variety, the dual element transducer

used

appeared

to be superior in

performance.

In addition, surface examinations of the exterior surface

is necessary.

e.

NRC will closely inspect the licensee's

preservice

(base line) examin-

ations/data

of the subject welds and-must

be satisfied with the weld

mapping

and characterization

to be used

as the basis for comparison

during subsequent

inservice inspections.

I'n summary, it was the

NRC position that the intent of Section

XI examination

requirements

is to detect service

induced type flaws of any nature (not

just intergranular stress

corrosion type cracks) in pressure

boundary

material

throughout the entire volume.

Since

each weld configuration

cannot

be specifically addressed

in the Code, it is important that careful

consideration

be given to all examination affecting attributes

and the

objectives

and intent of the Code.

It was understood that

some

RSD work is underway by the licensee's

contractor

relative to the signal processing

technique

associated

with clad materials.

The concept,

as presented,

seems to offer some promise.

Region I urged the

licensee

to pursue this endeavor.