Informs That NRC Completed Semiannual Plant Performance Review (PPR) of Plant on 970325 & Advises of Planned Insp Effort Resulting from Ppr.Enclosed Info Details Insp Plan for Next Six Months
ML17059B555
Person / Time
Site: Nine Mile Point  Constellation icon.png
Issue date: 05/14/1997
From: Doerflein L
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Sylvia B
NIAGARA MOHAWK POWER CORP.
References
NUDOCS 9705220384
Download: ML17059B555 (10)


Text

May 14, 1997 Mr. B. Ralph Sylvia Executive Vice President Generation Business Group and Chief Nuclear Officer Niagara Mohawk Power Corporation Nuclear Learning Center 450 Lake Road Oswego, NY 13126 SUBJECT'LANT PERFORMANCE REVIEW (PPR) - NINE MILE POINT UNITS 1 5 2 P

Dear Mr. Sylvia:

On March 25, 1997, the NRC staff completed the semiannual Plant Performance Review (PPR) of the Nine Mile Point Nuclear Station Units 1 and 2. The staff conducts these reviews for all operating nuclear power plants to develop an integrated understanding of safety performance.

The results are used by NRC management to facilitate planning and allocation of inspection resources.

The PPR for Nine Mile Point involved the participation of all technical divisions in evaluating inspection results and safety performance information for the period October 1996 through March 1997.

PPRs provide NRC management with a current summary of licensee performance and serve as inputs to the NRC Systematic Assessment of Licensee Performance (SALP) and senior management meeting (SMM) reviews.

This letter advises you of our planned inspection effort resulting from the Nine Mile Point PPR review.

It is provided to minimize the resource impact on your staff and to allow for scheduling conflicts and personnel availability to be resolved in advance of inspector arrival onsite.

The enclosure details our inspection plan for the next 6 months.

The rationale or basis for each inspection outside the core inspection program is provided so that you are aware of the reason for emphasis in these program areas.

Resident inspections are not listed due to their ongoing and continuous nature.

We will inform you of any changes to the inspection plan. If you have any questions, please contact me at (610) 337-5378.

Sincerely, Original Signed by:

Lawrence T. Doerflein, Chief Projects Branch 1

Division of Reactor Projects Docket No. 50-220, 50-410 License No. DPR-63, NPF-69 lilllllllllllllllmIIIIIIllllil

'7705220384

'770514 PDR ADOCK 05000220 8

PDR

')FFICIAL RECORD COPY

B. Ralph Sylvia

Enclosure:

Inspection Plan cc w/enclosure:

R. Abbott, Vice President

5. General Manager

- Nuclear C. Terry, Vice President-Safety Assessment and Support M. McCormick, Vice President

- Nuclear Engineering N. Rademacher, Unit 1 Plant Manager J. Conway, Unit 2 Plant Manager D. Wolniak, Manager, Licensing J. Warden, New York Consumer Protection Branch G. Wilson, Senior Attorney M. Wetterhahn, Winston and Strawn J. Rettberg, New York State Electric and Gas Corporation Director, Electric Division, Department of Public Service, State of New York C. Donaldson, Esquire, Assistant Attorney General, New York Department of Law J. Vinquist, MATS, Inc.

P. Eddy, Power Division, Department of Public Service, State of New York F. Valentino, President, New York State Energy Research and Development Authority J. Spath, Program Director, New York State Energy Research and Development Authority

B. Ralph Sylvia Distribution w/encl:

D. Screnci, PAO J. Lanning, DRM Region I Docket Room (with concurrences)

Nuclear Safety Information Center (NSIC)

PUBLIC NRC Resident Inspector J. Wiggins, DRS L. Nicholson, DRP DRS Branch Chiefs R. Correia, NRR D. R. Taylor, NRR

- L. Cunningham, NRR D. Barss, NRR L. Eckert, DRS L. Doerflein, DRP T. Moslak, DRP Marie Oprendek, DRP R. Junod, DRP Distribution w/encl:

(VIAE-MAIL)

W. Dean OEDO B. Norris - Nine Mile Point S. Bajwa, NRR D. Hood, NRR K. Cotton, NRR M. Campion, Rl Inspection Program Branch (IPAS)

DOCDESK DOCUMENT NAME: G:iBRANCH1iNMPLTR To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure Copy with attachment/enclosure "N" = No copy OFFICE RI/DRP NAME TMoslak DATE 05/rg/97 RI/DRP LDoerflein 05/I /97 OFFICIAL RECORD COPY

Nine IVlile Point Ins ection Plan Enclosure IP - Inspection Procedure Tl - Temporary Instruction CO - Core Inspection

- Minimum NRC Inspection Program (mandatory all plants)

".:::INSPECTION-::..::::;',:,'..:;::::.: ;.'::TITL'E/PROGRAV,::/AREA',';;:,;,':,',:,."" ::;INSPECTION'";:;;.:"::;;.":;TVPE:;'OFl'::","",'".,:,,::"!,-""i,~j';

START
,,',:DATES';,!.::

',',:INSPECTlOM/.!":)",",.'j"'P 64704 IP 71001 IP 83750 IP 82701 IP 84750 IP 82302 IP 40500 TI 2515/109 IP 86750 TI 2515/133 Fire Protection Program Unit 1 Licensed Operator Requalification Evaluation Occupational Radiation Controls Emergency Preparedness Program Effluent Monitoring Emergency Preparedness Exercise Review Objectives 5 Scenario Corrective Action Program MOV GL 89-10 Closure Solid Radwaste Management

5. Transportation Implementation of revised 49 CFR 100-179 and 10 CFR 71 6/2/97 5/26/97 6/1 6/97 7/14/9?

7/14/97 7/21/97 8/4 5 18/97 (5 inspectors/

2 weeks) 8/4/97 8/1 1/97 8/1 1/97 CO CO CO CO CO CO CORRI-Expanded effort to include identified weaknesses in Corrective Action Program including DER threshold, root cause analysis, the 50.59 process, and ISEG effectiveness.

Sl CO Sl

Enclosure IP 37550 IP 82301 IP 81700 IP 71001 Engineering EP Exercise - Full Participation Physical Security Unit 2 Licensed Operator Requalification Evaluation 9/8/97 9/22/97 9/29/97 10/20/97 CO - 3 inspectors for 2 weeks focusing on design controls, corrective actions, and management involvement in engineering activities.

CO CO CO