ML17059B397
| ML17059B397 | |
| Person / Time | |
|---|---|
| Site: | Nine Mile Point |
| Issue date: | 01/13/1997 |
| From: | Thompson H NRC OFFICE OF THE EXECUTIVE DIRECTOR FOR OPERATIONS (EDO) |
| To: | Rogers NRC COMMISSION (OCM) |
| References | |
| NUDOCS 9701160031 | |
| Download: ML17059B397 (12) | |
Text
,t gAS REGIJ (4
+A
~o A.fl
+~
~o
+rt*++
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON> D.c. 2055&4001 January 13, 1997 MEMORANDUMTO:
Com issi r Rog rs
~!
ugh ompson, Jr.
Acting cutive Director for Operations
SUBJECT:
TIMES TO INITIATIONOF BOILING SUBSEQUENT TO LOSS OF SPENT FUEL COOLING During the AEOD presentation of its assessment of spent fuel cooling on November 14, 1996, you raised questions about Viewgraph 13, "Reduced Time to Boil at Nine Mile Point Unit 2." Of particular interest was the apparent lack of smoothness in the plot of hours to boil as a function of outage number.
You also indicated that you were interested in seeing the plot of time to boil versus time after reactor shutdown.
The data plotted in Viewgraph 13 (attached) were provided by the Nine Mile Point Unit 2 licensee in a June 14, 1996, memorandum and discussed during a June 21, 1996, telephone conversation with AEOD staff.
In response to discussions with AEOD after the November 14, 1996, Commission meeting, Nine Mile Point Unit 2 re-evaluated their spent fuel pool heatup calculations and found that there were some anomalies in the data that had been provided in June 1996.
The original calculations supplied in June 1996 were inconsistent.
The original calculations for refueling outages 1, 2 and 3 assumed that the refueling pool gates were not installed ("gates out" configuration).
The original calculations for refueling outage 4 assumed that the refueling pool gates were installed
("gates in" configuration).
Note that when the refueling pool gates are installed they separate the fuel pool from the reactor cavity. When the refueling pool gates are not installed, there is a larger mass of water to be heated, i.e., the water in the spent fuel pool and the water in the reactor cavity. The data provided in June 1996 were further complicated because the calculated time to boil for the first refueling outage included, the effects of environmental heat losses while the calculated times to boil for the other three outages did not include these effects.
The attached figures provide consistent results of the Nine Mile Point Unit 2 reanalyses noting the positions of the refueling pool gates and neglecting environmental heat losses.
Figure 1 shows the time until boiling begins versus the number of days after reactor shutdown.
We believe this figure addresses the request you made on November 14, 1996, during the AEOD spent fuel cooling presentation.
This figure also shows the effect of the refueling pool gates'ositions.
CONTACT:
Harold L. Ornstein, AEOD/SPD/RAB 41 5-7574 f7-'/d 970iih003i 970ii3 PDR COMMS NRCC CORRESPONDENCE PDR
t
Commissioner Rogers Figure 2 shows the time from reactor shutdown until completion of the full core offload.
Note that this is different than the information provided in Viewgraph 13 which indicated time from reactor shutdown until start of core offload. As Figure 2 indicates, the period from shutdown until completion of the offload decreased from 35 days in the first outage to 13 days in the fourth refueling outage.
Figure 3 shows the time to initiate boiling as a function of outage number with the refueling pool gates in and out.
During the first four refueling outages the refueling pool gates were out at Nine Mile Point Unit 2. However, if maintenance work would have been required on the reactor vessel or appurtenances during those times it would have been necessary to have the refueling pool gates installed, thereby leading to shorter times to spent fuel pool boiling.
These figures will be accompanied by explanatory text in the AEOD report when it is finalized for publication as a NUREG report.
Attachments:
Viewgraph 13 "Reduced Time to Boil at Nine Mile Point Unit 2" Figure 1 "Time to Boil vs. Time After Reactor Shutdown" Figure 2 "Full Core Offload Times vs. Outage Number" Figure 3 "Time to Boil vs. Outage Number" cc w/ atts.:
Chairman Jackson Commissioner Dicus Commissioner Diaz Commissioner McGaffigan SECY OCA OPA OGC Distribution w atts.:
RAB R/F KRaglin SMeador (AEOD 96-103)
AEOD R/F PBerenoweky t
Filet C~enter,-'~.
'EDO R/F (WITS 9600190)
JMitchell, OEDO Public DOCUMENT NAME: C:WP51iWPDOCSiSFPiICROGERS.HLO "See previous concurrence:
To receive a copy of this document, Indicate In the boxr C
~ Copy without anachment/enclosure E
ee Copy with attachment/enclosure "N
n No copy OFFICE NAME DATE RAB E
HOrnstein:mmk 12/23/96" D'SPD E
AD:AEOD DEDO. ~':
CRossi DRoss EJo afi H
mpson 01/08/97" 01/ /97 01/ 97
(
01/ /97 OFFICIAL RECORD COPY
1
Reduced Time to Boil at Nine Mile Point Unit 2 108 23 HOURS TO BO1L 5 DAYS TO OFFLOAD 39 13 29 s
Outage Number (Viewgraph 13)
I I
50 50 40 M
O M
~~
30 Q) m CO 0
20 6)
EI=
10 g,ass
$n 40 30 20
~o 0
0 0
10 15 20 25 Days After Reactor Shutdown to Full Core Offload 30 35 t
Figure 1
Time to Boil vs. Time After Reactor Shutdown
I
40 O~ 35
~ 30
~25 O
u 20 O
~15 O10 O0 5
0-0 35 24 14 REFUEL OUTAGE NUMBER Figure 2 Full Core Offload Times vs. Outage Number'
I
60 50 40 30 20 10 17.6 38.8 13.6 29.4
~
GATES OUT Q
GATES IN 24.2 10.1 0
REFUEL OUTAGE NUMBER Figure 3 Time to Boil vs. Outage Number
C
~
4
~
~
r<'