ML17059A026

From kanterella
Jump to navigation Jump to search

Discusses Schedule Extension for Implementation of GL 89-10 Program for MOVs at Facility,Per Util .Util Extension of Implementation Schedule Acceptable Subj to Listed Conditions
ML17059A026
Person / Time
Site: Nine Mile Point Constellation icon.png
Issue date: 08/26/1993
From: Menning J
Office of Nuclear Reactor Regulation
To: Sylvia B
NIAGARA MOHAWK POWER CORP.
References
GL-89-10, TAC-M86321, NUDOCS 9309090302
Download: ML17059A026 (16)


Text

a gpPq 4 ggtr, (4

o eve UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D. C. 20555 August 26, 1993 Docket No. 50-410 Hr. B. Ralph Sylvia Executive Vice President, Nuclear Niagara Mohawk Power Corporation 301 Plainfield Road

Syracuse, New York 13212

Dear Hr. Sylvia:

SUBJECT:

SCHEDULE EXTENSION FOR IMPLEMENTATION OF GENERIC LETTER 89-10 PROGRAM FOR MOTOR-OPERATED VALVES AT NINE MILE POINT NUCLEAR STATION, UNIT 2 (TAC NO. H86321)

In Generic Letter (GL) 89-10, "Safety-Related Motor-Operated Valve Testing and Surveillance,"

the NRC staff requested nuclear power plant licensees to develop programs to verify the capability of safety-related motor-operated valves (HOVs) to perform their safety functions by June 28, 1994, or three refueling outages after December 28,

1989, (whichever is later).

Niagara Mohawk Power Corporation (NMPC) indicated in a letter dated February 5,

1992, that it intended to meet the schedule and recommendations of GL 89-10 at Nine Mile Point Unit 2 (NMP-2).

By letter dated April 15,

1993, NHPC informed the NRC staff of its decision to extend the schedule for completing the recommended actions of GL 89-10 beyond June 28, 1994.

Specifically, NHPC proposed to test 57 HOVs that have a more significant contribution to overall plant safety by June 28, 1994.

The remaining HOVs within the scope of the GL 89-10 program would be tested within 3 months of the end of the fourth refueling outage.

The NRC staff reviewed NHPC's letter of April 15,

1993, and determined that additional information was needed to complete evaluation of the justification for the schedule extension.

Accordingly, the staff issued a request for additional information on June 24, 1993.

On July 16, 1993, the staff met with NMPC in the NRC One White Flint North Office in Rockville, Maryland, to review and discuss the additional information that had been requested.

During the meeting on July 16,

1993, NHPC informed the staff that there were 41 HOVs within the scope of its GL 89-10 program that would not receive either static or dynamic testing prior to June 1994.

The staff explained that the approach being fol'%owed by NMPC for these valves would not provide adequate assurance of their rt~liability, except possibly for those valves with a sizable mar~iIn bct>..en their estiIiiated capability and their requirements.

The staff recommended tpat'NMPC consider revising its test plan for the upcoming outage (scheduled to begin in October 1993) to ensure that all the valves in the program undergo. at least static testing before June 1994.

The staff also recommended that the information learned on valve requirements from dynamic testing be used in setting up valves that only undergo static testing.

During g

the meeting on July 16,

1993, NHPC was requested to provide certain additional l

9309090302'930826 t

PDR

" ADOCN'~'05000410 t

ec mE MTS~,

P, PDR Q"-

t J

1 x v 1

h 1

fl"v

Mr. B. Ralph Sylvia information related to test acceptance criteria, grouping, and capability evaluations.

This information was transmitted to the staff on July 21, 1993.

NMPC advised the NRC staff of revisions to its test plan for the upcoming outage during a telephone conference on August 5, 1993.

(Participants in this telephone conference included Messrs.

Jones, Ward, and Baker from NMPC and Hessrs.
Eapen, Drysdale, Scarbrough,
Sullivan, and Menning from the NRC staff.)

Specifically, during the telephone conference NMPC committed to statically test all 15 gate valves in the group of 41 low priority valves during the next refueling outage.

NMPC also stated that every effort would be made to statically test the remaining 26 non-gate valves in the low priority group.

As a result of rearranging its test plan, NMPC stated that three additional globe valves with significant capability margin would not be statically or dynamically tested before June 1994.

During the telephone conference on August 5, 1993, the staff discussed NMPC's basis for the safety significance and capability margin for the 29 MOVs that will not be statically or dynamically tested before June 1994.

The staff did not identify any concerns with the NMPC's assignment of low safety significance.

Although NMPC indicated that each of the 29 MOVs has capability margin available, the staff noted that globe valves 2RHS*MOV26A/B and 2RHS*MOV27A/B had less thrust margin than the other globe valves.

The staff advised NMPC that the revised test plan for NHP-2 was considered to be acceptable.

However, the staff requested that NMPC attempt to test as many of the 29 remaining MOVs at least statically before June 1994.

In particular, the staff requested that NMPC make a strong effort to test globe valves 2RHS*MOV26A/B and 2RHS*MOV27A/B because of their small capability margin compared to other globe valves.

The NRC staff has concluded that NMPC's extension of the implementation schedule for the GL 89-10 program for MOVs is acceptable subject to certain conditions.

Those conditions are as follows:

1.

For those MOVs that are only tested at partial design basis conditions, NMPC is required to demonstrate the operability of those components at full design basis conditions.

2.

for those MOVs that are only statically tested, NMPC is required to demonstrate operability based on the best industry test data available.

Based on industry experience, the staff does not consider the original vendor valve factor of 0.3 to be the best data available for gate valves on a generic basis.

3.

For those MOVs tha" will riot be statically or dynamically tested before June

1994, NMPC is required to set up those components using conservative theoretical predictions to ensure their capability.

4.

The grouping methodology that has been proposed to reduce the extent of dynamic testing must be justified.

Mr. B. Ralph Sylvia August 26, 1993 The staff's comments on the NMPC documents related to test acceptance criteria, grouping, and capability evaluations that were transmitted to the staff on July 21,

1993, are being forwarded as an enclosure to this letter for NMPC's consideration.

When issued, Supplement 6 to GL 89-10 will provide additional information in these areas.

The staff will review NMPC's actions in response to the above-stated conditions and the enclosed comments during future inspections.

Sincerely, John E. Menning, Project Manager Project Directorate I-1 Division of Reactor Projects I/II Office of Nuclear Reactor Regulation

Enclosure:

NRC Staff Comments on Licensee Documents Transmitted on July 21, 1993 cc w/enclosure:

See next page

I

Mr. B. Ralph Sylvia Niagara Mohawk Power Corporation CC:

Hark J. Wetterhahn, Esquire Winston

& Strawn 1400 L Street, NW.

Washington, DC 20005-3502 Hr. Richard Goldsmith Syracuse University College of Law E. I. White Hall Campus

Syracuse, New York 12223 Resident Inspector Nine Mile Point Nuclear Station P. 0.

Box 126

Lycoming, New York 13093 Gary D. Wilson, Esquire Niagara Mohawk Power Corporation 300 Erie Boulevard West
Syracuse, New York 13202 Hr. David K. Greene Manager Licensing Niagara Mohawk Power Corporation 301 Plainfield Road
Syracuse, New York 13212 Hs.

Donna Ross New York State Energy Office 2 Empire State Plaza 16th Floor

Albany, New York 12223 Supervisor Town of Scriba Route 8, Box 382
Oswego, New York 13126 Nine Mile Point Nuclear Station Unit 2 Regional Administrator, Region I U. S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Charles Donaldson, Esquire Assistant Attorney General New York Department of Law 120 Broadway New York, New York 10271 Mr. Richard H. Kessel Chair and Executive Director State Consumer Protection Board 99 Washington Avenue
Albany, New York 12210 Mr. John H. Hueller Plant Manager, Unit 2 Nine Mile Point Nuclear Station Niagara Mohawk Power Corporation P. 0.

Box 32

Lycoming, New York 13093 Vice President Nuclear Generation Nine Mile Point Nuclear Station Niagara Mohawk Power Corporation P. 0.

Box 32

Lycoming, New York 13093

Enclosure NRC STAFF COMMENTS ON NIAGARA MOHAWK POWER CORPORATION NMPC DOCUMENTS TRANSMITTED TO THE STAFF ON JULY 21 1993 Nine Jul Mile Point Unit 2 En ineerin S ecification NMP2-386M Revision 1

dated 21 1993 "D namic Flow Testin of Safet Related Motor 0 crated Valves to Com l with GL 89-10" 1.

2.

3.

4, 5.

The criteria established in Section 5.1 of NHP2-386M do not ensure operability of the tested motor-operated valve (HOV) before it is returned to service.

NHPC only requires this determination after return to service in Section 5.2.

The criteria must ensure that the operability of all tested HOVs is verified prior to return to service.

In Section 5.2, it is stated that only test data from differential pressure tests above 80X of the design basis will be evaluated.

All test data must be evaluated for information on HOV operability regardless of the percentage of design basis conditions.

The discussion of'test acceptance criteria after return to service must be more specific.

For example, Section 5.2.3 states that margin must exist between thrust at torque switch trip and extrapolated differential pressure thrust but does not provide detailed information to determine whether margin exists.

Section 2.6 defines a dynamic test as either a test with differential pressure and/or flow.

The definition needs to reflect that a dynamic test with low or no flow might not provide reliable information on the thrust required to open or close the valve although differential pressure is within the desired range.

Section 4.4 in paragraph A.4 states that locations of pressure measurement instruments are based on an allowable 5X pressure drop in the pipeline between the pressure instruments and the HOV under test.

In addition to other uncertainties, the actual pressure drop across the valve must be determined regardless of location of measurement instruments.

Nine Mile oint Unit NER-2M-003 Revision 0

dated J l 6

1993 "Generic Letter 89- 0 D namic estin Valve Grou in "

2.

The grouping method in Section 3.0 focuses on external attributes but allows different sized valves to be grouped together.

HHPC's grouping method is similar to the grouping allowed under. NRC Bul:etin 85-03, wnich was found to be inadequate.

NHPC should review the information to be provided in Supplement 6 to GL 89-10 on grouping'.

In Section 4.0, NHPC asserts

that, because valve groups will be of the, same manufacturer,'imensional attributes will be equal or proportional, thereby assuring similar stress distributions in the valve assembly.

However, manufacturing tolerances have been shown to have a significant effect on the thrust required to operate a valve such that apparently identical valves perform differently under dynamic conditions.

NMPC's grouping method must provide sufficient justification to demonstrate that the grouped HOVs will perform similarly under dynamic conditions.

NMP2 Detailed Anal sis for Out ut Thrust Ca abilities in the Sco e of the NMP2 GL 89-10 Pro ram Extension 2.

3.

In Section 2. 1.A, NHPC predicts the required thrust based on a 0.3 valve factor for gate valves from original vendor guidance and NHP-2 "design basis."

The NRC regulations require that safety-related components be capable of performing their design-basis functions.,

A specific valve factor would not be part of that design basis requirement for the valve.

Industry HOV tests have shown the 0.3 valve factor to be unreliable in conservatively predicting the thrust required for all gate valves.

In

addition, Westinghouse has recommended approximately 0.5 valve factors for some of their valves (2HCS*HOVIA/B and HOV2A/B are Westinghouse valves).

Use of a 0.3 valve factor creates a significant uncertainty in NHPC's prediction of the thrust required to operate gate valves.

NHPC must use best available data in verifying the sizing and settings of its MOVs.

In Section 2.2.A, NHPC predicts the thrust capability of MOVs that have not been statically tested with diagnostic equipment using either (1) laboratory test data from Limitorque of the MOV at various torque switch

settings, or (2) standard Limitorque spring pack curves and an assumed
0. 15 stem friction coefficient.

The NRC staff discussed concerns about the use of Limitorque laboratory test data in NRC Inspection Report 99900404/92-01 from an inspection of the Westinghouse Electric Corporation.

For example, the stem friction coefficient during the Limitorque testing could have been much lower than present at NHP-2.

As discussed in NRC Inspection Report 99900100/93-01, Limitorque does not have any information on the uncertainty in its spring pack curves, but stated that it could be significant.

NMPC's prediction of thrust capability may be overly optimistic.

During the telephone conference

'on August 5,

1993, NMPC stated that, of the HOVs that will not be dynamically tested by June 1994, all of the gate valves would at least be statically tested to determine their thrust capability under those conditions.

NMPC must continue to be aware of the uncertainties in assessing the capability of HOVs tested only under static conditions as well as the capability of non-gate valves.

In Attachment C,

NHPC lists thrust/torque margin for the Ci HOVs tu be tested after June 1994.

However, the minimum required thrust for 2CCP*MOV122 and 124 does not match this thrust in Attachment A.

NMPC must check the table for accuracy and make necessary corrections.

V 4.

NNPC must review problems (such as at Catawba) with vendor estimates of required torque for operating butterfly valves to determine if its predicted torque requirement is justified.

5.

NHPC must continue to assess the calculated margin of the valves that will not be dynamically tested based on plant-specific test data and other available test data.

0

Hr. B. Ralph Sylvia August 26, 1993 The staff's comments on the NHPC documents related to test acceptance criteria, grouping, and capability evaluations that were transmitted to the staff on July 21,

1993, are being forwarded as an enclosure to this letter for NHPC's consideration.

When issued, Supplement 6 to GL 89-10 will provide additional information in these areas.

The staff will review NHPC's actions in response to the above-stated conditions and the enclosed comments during future inspections.

Sincerely, Original signed by:

John E. Henning, Project Manager Project Directorate I-l Division of Reactor Projects I/II Office of Nuclear Reactor Regulation

Enclosure:

NRC Staff Comments on Licensee Documents Transmitted on July 21, 1993 cc w/enclosure:

See next page DISTRIBUTION:

Docket File PDI-1 Reading JCalvo CVogan OGC Cowgill, RGN-1 NRC 8 Local PDRs SVarga RACapra JHenning ACRS (10)

Plant File

PEapen, RI
AHansen, 13/E/21 TScarborough, 7/E/23
  • See revious concurrence 0FFIGE PDI-I;LA NAME CVo an g3 PDI-1'H JHennin

. vl

  • EHEB JNorber Re ion I

<> ~cking PEa en PDI-1: D RACa ra ~

DATE 9&93 V 93 8 24 93

~r 93 F

93 OFFICIAL RECORD COPY FILENAME: G: iNHP2iNM286321. LTR

0,

,e 0

E r