ML17058B044

From kanterella
Jump to navigation Jump to search
Notice of Environ Assessment & Finding of No Significant Impact Re Exemption from Requirements of 10CFR50,App J Re Periodic Retest Schedules for 39 Type C Tests
ML17058B044
Person / Time
Site: Nine Mile Point Constellation icon.png
Issue date: 11/10/1992
From:
Office of Nuclear Reactor Regulation
To:
Shared Package
ML17058B045 List:
References
NUDOCS 9211190092
Download: ML17058B044 (10)


Text

UN T D STATES NUCLEAR REGULATORY COMMISSION NIAGARA MOHAWK POWER CORPORATION DOCKET NO. 50-220 ENVIRONMENTAL ASSESSMENT AND FINDING OF NO SIGNIFICANT IMPACT The U.S. Nuclear Regulatory Commission (the Commission) is considering issuance of an exemption from certain requirements of 10 CFR Part 50, Appendix J, to Niagara Mohawk Power Corporation (the licensee) for Nine Mile Point Nuclear Station Unit No.

1, located at the licensee's site in Oswego County, New York.

ENVIRONMENTAL ASSESSMENT Identification of Pro osed Action:

By letter dated November 3, 1992, which superseded the licensee's application dated October 14; 1992, the licensee requested a schedular exemption pursuant to 10 CFR 50. 12(a) from the requirements of 10 CFR Part 50, Appendix J, Section III.D.3.

Specifically, the licensee requested temporary relief from the requirement to perform local leak rate tests (LLRTs) at intervals of no greater than 2 years for 39 Type C tests.

A one-time only

delay, up to a maximum of 7 weeks, was requested for the performance of these leakage tests.

The licensee's request was necessitated by a proposed delay in the start of the next refueling outage (RFO-12) of Nine Mile Point Nuclear Station Unit No.

1 from January 2,

1993, to February 19, 1993.

The Need for the Pro osed Action:

The schedular exemption is required to permit the licensee to operate the plant until February 19, 1993, the proposed start date for RFO-12.

The refueling outage is currently scheduled to begin on 92iii90092 92iii0 PDR ADOCK 05000220 "P

PDR

January 2,

1993, with an end date of about February 25, 1993.

However, based on projections from the New York Power Pool (NYPP), the current schedule may impact the ability of the NYPP to provide reliable power during the winter peak load period.

Accounting for planned maintenance, required reserve, and normal unplanned

outages, the NYPP is projecting net margin deficiencies during the period from January 3,
1993, through February 20, 1993.

Consequently, the licensee has determined that the most prudent and effective course of action would be to delay the start of RFO-12 approximately 7 weeks until February 19, 1993.

The licensee has stated that during the forced outage that began on Hay 1,

1992, and ended on August 8, 1992, it recognized that the start of RF0-12, originally scheduled to begin on September 11,
1992, would be impacted due to insufficient fuel burnup.

The current outage start date of January 2,

1993, was established at that time, and the licensee performed the Types B and C leak tests during the forced outage required to support the revised start date.

The licensee became aware of the NYPP projections of net margin deficiencies for the period January 3,

1993, through February 20,
1993, subsequent to the startup from the forced outage.

Environmental I

acts of the Pro osed Action:

The proposed schedular exemption would allow the licensee to continue to operate the plant from January 2,

1993, until February 19,

1993, when the 39 Type C tests would be performed during RFO-12 in accordance with the requirements of 10 CFR Part 50, Appendix J.

The remaining Type B penetrations

1 and Type C tested valves are within the 24-month frequency or are scheduled for testing prior to RFO-12.

The penetrations included in the licensee's schedular exemption request represent approximately 45 percent of the Type C

penetrations at Nine Mile Point Unit 1, but only 6.2 percent of the total "as-left" leakage at the beginning of the current operating cycle.

The total "as-left" leakage for all Types B and C penetrations was 0.24 La and the total "as-left" leakage from the penetrations covered by the proposed exemption was 0.015 La.

The combined leakage from the penetrations addressed in the exemption went from an "as-left" value to 0.016 La to an "as-found" value of 0.05 La during the 2-year interval prior to the current operating cycle.

During the 2-year interval prior to that, the combined leakage from these penetrations went from an "as-left" value of 0.0224 La to an "as-found" value of 0.095 La.

Based on the most recent "as-left" leakage of 0.015 La, the historical performance of these penetrations, and a maximum increase of 7 percent in the surveillance interval, the licensee has determined that the maximum combined leakage from these penetrations would not be expected to exceed

0. 1 La.

This provides reasonable assurance that the requested surveillance interval extension will not result in the Types B and C leakage rate total exceeding the 0.6 La limit of 10 CFR Part 50, Appendix J.

Therefore, the Commission concludes that there are no significant radiological environmental impacts associated with the proposed schedular exemption.

With regard to potential nonradiological

impacts, the proposed schedular exemption only involves LLRTs on containment isolation valves.

The exemption does not affect nonradiological plant effluents and has no other environmental impact.

Therefore, the Commission concludes that

there are no significant nonradiological impacts associated with the proposed schedular exemption.

Alternatives to the Pro osed Action:

Since the Commission has concluded that these are no significant environmental effects that would result from the proposed schedular exemption, any alternatives with equal or greater environmental impacts need not be evaluated.

The principal alternative would be to deny the licensee's exemption request.

Such action would not reduce environmental impacts of the Nine Mile Point Nuclear Station Unit No.

1 and would result in an unwarranted shutdown of the plant.

Alternative Use of Resources:

The actions associated with the granting of the proposed schedular exemption as detailed above do not involve the use of resources not previously considered in connection with the "Final Environmental Statement Related to Operation of Nine Mile Point Nuclear Station, Unit No. 1," dated January 1974.

A encies and Persons Consulted:

The NRC staff reviewed the licensee's submittal that supports the proposed schedular exemption discussed above.

The NRC staff did not consult other agencies or persons.

FINDI G 0 N

GNIF CANT IMPACT The Commission has determined not to prepare an environmental impact statement for the proposed schedular exemption.

Based upon the foregoing environmental assessment, the Commission concludes that the proposed action will not have a significant effect on the quality of the human environment.

1 l

~

+

~

I

~

~

~

~

For further details with respect to this action, see the licensee's application for the schedular exemption dated November 3, 1992, which superseded the licensee's application dated October 14, 1992.

This document is available for public inspection at the Commissions's Public Document

Room, 2120 L Street, NW., Washington, D.C.

and at the Penfield Library, State University of New York, Oswego, New York 13126.

Dated at Rockville, maryland, this 10thday of November 1992.

I FOR THE NUCLEAR REGULATORY COMMISSION.

Robert A. Capra, Director Project Directorate I-l Division of Reactor Projects I/II Office of Nuclear Reactor Regulation

~

~

V