Forwards Insp Repts 50-220/92-26 & 50-410/92-30 on 921019 Through 921029.No Violations Noted.Unresolved Item Noted Re Semismic Review for Simple Design Change
ML17056C142
Person / Time
Site: Nine Mile Point  
Issue date: 12/03/1992
From: Durr J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Sylvia B
NIAGARA MOHAWK POWER CORP.
Shared Package
ML17056C143 List:
References
NUDOCS 9212090242
Download: ML17056C142 (6)


See also: IR 05000220/1992026

Text

DEC Os

>992

Docket Nos.

50-220

50-410

Mr. B. Ralph Sylvia

Executive Vice President - Nuclear

Niagara Mohawk Power Corporation

301 Plainfield Road

Syracuse, New York 13212

Dear Mr. Sylvia:

SUBJECT:

COMBINED INSPECTION REPORT NOS. 50-220/92-26 AND 50-410/92-30

This letter transmits the NRC Region I inspection report for the engineering and technical

support inspection conducted by Mr. R. Mathew of this office on October 19 through

October 29, 1992, at Nine Mile,Point Units 1 and 2, and the Niagara Mohawk Salina

Meadows Office in Syracuse, New York. Mr. Mathew discussed

the findings of the

=

inspection with Messrs. A. DeGracia, J. Conway, K. Sweet, and other members of your staff

at the conclusion of the inspection.

This inspection was directed toward areas important to public health and safety.

Areas

examined during this inspection are described in the NRC Region I inspection report, which

is enclosed with this letter.

Within these areas,

the inspection consisted of selective

examinations of procedures

and representative

records, interviews with personnel,

and

observations by the inspectors.

Based on the results of this inspection, the engineering and technical support activities

appeared

to be effective and of good quality.

However, one item pertaining to the seismic

review for a simple design change remained unresolved.

We also noted that the-backlog of

Deviation/Event Reports remained high and in need of continued management

attention.

090olp

9212090242

921203

PDR

ADOCK 05000220

8.

PDR

0

Mr. B. Ralph Sylvia

~

~

Your cooperation with us in this matter is appreciated.

Sincerely,

Jacque P. Durr, Chief

Engineering Branch

Division of Reactor Safety

Enclosure:

NRC Region I Inspection Report Nos. 50-220/92-26 and 50-410/92-30

cc w/encl:

J. Firlit, Vice President - Nuclear Support

C. Terry, Vice President - Nuclear Engineering

J. Perry, Vice President - Quality Assurance

Vice President - Nuclear Generation

K. Dahlberg, Unit 1 Plant Manager

M. McCormick, Unit 2 Plant Manager

D. Greene, Manager, Licensing

J..Warden, New York Consumer Protection Branch

G. Wilson, Senior Attorney

M. Wetterhahn, Winston and Strawn

Director, Power Division, Department of Public Service, State of New York

C. Donaldson, Esquire, Assistant Attorney General, New York Department of Law

K. Abraham, (2)

Public Document Room (PDR)

Local Public Document Room (LPDR)

Nuclear Safety Information Center (NSIC)

NRC Resident Inspector

State of New York, SLO Designee

PEt; 03 BM

Mr. B. Ralph Sylvia

~

~

bcc w/encl:

Region I Docket Room (with concurrences)

C. Cowgill, DRP

J. Yerokun, DRP

L. Nicholson, DRP

S. Greenlee, DRP

W. Schmidt, SRI - Nine Mile

V. McCree, OEDO

R. Capra, NRR

J. Menning, NRR

D. Brinkman, NRR

DRS/EB SALP Coordinator

D. Holody, EO

RI:DRS

Mathew

11/zf92

RI:DRS

Ru~

11/Lf92

RI:DRS

Durr

12/EJ'92

OFFICIALRECORD COPY

A:NM92-26&30.RM