Responds to Re Estimated Restart Date for Facility.Util Anticipates That Facility Will Be Ready to Restart in mid-to-late Nov 1989.Address of Region IV Administrator Listed
ML17056A320
Person / Time
Site: Nine Mile Point Constellation icon.png
Issue date: 09/26/1989
From: Wiggins J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Peart W
AFFILIATION NOT ASSIGNED
Shared Package
ML17056A321 List:
References
NUDOCS 8910040080
Download: ML17056A320 (4)


Text

SEP 26 l989 Mr. Wendell G. Peart 1452 South Wood Way Roseville, California 95678

Dear Mr. Peart:

This is in response to your

letter, dated September 15,
1989, to Mr. William T. Russell, Regional

" Administrator, NRC Region I in which you requested an estimated restai t date for Nine Mile Point Unit 1

and the address of the Regional Administrator covering the State of Texas.

Regarding the restart schedule for Nine Mile Point Unit 1, a more appropriate source for this information would be the utility itself, since the completion schedule for hardware and programmatic improvements is wholly under its con-trol.

Nevertheless, it is our understanding that the utility anticipates the facility being ready to resume operations in the mid-to-late November 1989 timeframe.

However, as you
know, the Utility has agreed not to restart the facility without first obtaining the agreement of the NRC Regional Adminis-trator.

Several significant NRC inspections need to be completed to assemble the basis for this restart decision.

Our current inspection schedule would show 'these reviews completed in November also.

Regarding your second

question, the NRC Regional Administrator cove'ring the State of Texas can be contacted at the following address:

U.S. Nuclear Regulatory Commission ATTN:

Mr. Robert D. Martin Regional Administrator 611 Ryan Plaza Drive Suite 1000 Arlington, Texas 76011 I trust this has provided an acceptable

-answer to your questions.

Sincerely, OflgNal $!pp(,~~ g...

James T. Wiggins, Chief Reactor Projects Branch No.

1 Division of Reactor Projects OFFICIAL RECORD COPY WIGGINS 593 9/25/89 - 0001.0.0 09/26/89

/

Mr. Wendell G. Peart S EP 2 6 1989 bcc w/Incoming Letter dated 9/15/89:

W. Russell, RA W. Kane, DRP G. Meyer, DRP D. Limroth, DRP R. Barkley, DRP RI: DRP Wiggins/meed 9/~/89 a

9/8 /89 OFFICIAL RECORD COPY WIGGINS 593 9/25/89 - 0002.0.0 09/26/89