ML17055D801

From kanterella
Jump to navigation Jump to search
Insp Rept 50-410/88-04 on 880224-26.No Violations Noted. Major Areas Inspected:Overall Power Ascension Program, Including Test Procedure Review & Test Results Evaluation of Test Condition 3 & 5 Tests & QA Interfaces
ML17055D801
Person / Time
Site: Nine Mile Point 
Issue date: 04/21/1988
From: Florek D, Lange D, Lumb T, Sisco C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML17055D800 List:
References
50-410-88-04, 50-410-88-4, IEIN-86-110, NUDOCS 8805030103
Download: ML17055D801 (12)


See also: IR 05000410/1988004

Text

U.S.

NUCLEAR REGULATORY COMMISSION

REGION I

Report

No.

50-410/88-04

Docket No.

50-410

License

No.

NPF-69

Licensee:

Nia ara

Mohawk Power Cor oration

301 Plainfield Road

S racuse

New York

13212

Facility Name:

Nine Mile Point Nuclear Station

Unit 2

Inspection At:

Scriba

New York

Inspectors

Inspection

Conducted:

Februar

2 -26, 1988

F

ek, Senior Operations

Engineer,

DRS

ate

T.

umb,

Seni r Operations

Engineer,

DRS

C. Sisco,

Operation

Engineer,

DRS

9 /z.~lrs

date

0 (kg

date

Approved by:

D.

Lange,

Ch f,

BWR

ection

Operations

Branch,.

DRS

date

Ins ection

Summar

Ins ection

on Februar

24-28

1988

Re ort No.

~/

Areas

Ins ected:

Routine,

unannounced

inspection

by region-based

inspectors

of the overall

power ascension

test

program including test procedure

review and test results evaluation of Test Condition

3 and

5 tests,

neutron

flux oscillation observations

and

QA interfaces.

Results:

No violations were identified.

The licensee

satisfied the startup

test program requirement'for testing in Test Condition

3 and 5.

Note: for acronyms

not defined, refer to NUREG-0544,

"Handbook of Acronyms and

Initialisms."

3305030203

330420

PDr.'DOCK 0S0004~0

DCD

DETAILS

1.0

Persons

Contacted

Nia ara

Mohawk Power

Cor oration

~R. Abbott, Station Superintendent

"G. Carlisle,

Lead

STOMA Engineer

C.

Beckham,

Manager

gA Operations

  • J. Conway,

Power Ascension

Manager

  • P. MacEwan, Site Representative,

NYSEG

R. Pasternak,

Manager Nuclear Consulting Services

  • T. Perkins,

Generla

Superintendent

  • A. Pinter,

Licensing Engineer

R. Seifried, Assista'nt Superintendent

Training

D. Straka,

Supervisor

Ops Training Unit

1

L. Mott, Site Licensing Engineer

K. Zollitsh, Training Superintendent

New York State

PSC

P.

Eddy, Site Representative

NRC Personnel

W. Cook, Senior Resident

Inspector

"Denotes

those

present at the exit meeting

on November 6,

1987.

The inspector also contacted

other

members of the licensee's

Operations,

Technical,

Test

and

gA staffs.

2.0

Power Ascension

Test

Pro

ram

PATP

2. 1

References

Regulatory Guide 1.68,

Revision 2, August 1978, "Initial Test

Program for Water cooled Nuclear

Power Plant."

ANSI N18.7-1976,

"Administrative Controls

and guality Assurance

for Operations

Phase

of Nuclear Power Plants."

Nine Mile Point Unit 2 (NMP-2) Technical Specifications,

July 2,

1987.

Nine Mile Point Unit 2 Final Safety Analysis Report

(FSAR)

Chapter

14, "Initial Test Program."

Nine Mile Point Unit 2 Safety Evaluation Report.

Nine Mile Point

2 AP-1.4, Startup Test

Phase,

Revision 5.

f

A,

2.2

Overal

1

Power Ascension

Test

Pr o ram

The inspector held discussions

with the power ascension

manager

(PAM), the lead startup test,

design

and analysis '(STD&A) engineer

and other

members of the

PATP staff to assess

the status

of testing,

the test results evaluation

process

and the preparation

and approval

of test procedures.

In addition,

the inspector

attended

two daily

power ascension

management

meetings.

2.3

Power Ascension

Test Procedure

Review

~Sco

e

Procedure

N2-SUT-27-6 "Generator

Load Reject" Final Draft dated

February

1988 was reviewed for the attributes identified in

Inspection

Report

No. 50-410/86-38,

Section 4.3.

Discussion

The procedure

reviewed

was technically acceptable.

Final facility

approval of the procedure

is required.

~Findin

s

No unacceptable

conditions were identified.

2.4

Power Ascension

Test Results

Evaluation

~Sco

e

The power ascension

results listed in Attachment

A were evaluated

'for the attributes identified in Inspection

Report

No. 50-,410/86-64,

Section

2. 1.

Findin

s and Conclusion

All test results

evaluated

were determined to satisfy the test

criteria or where deficiencies

existed the licensee

processed

test

exceptions.

The licensee's

resolution of test exceptions

was

determined

to be acceptable.

The licensee

is following the

established

administrative

requirements

for the startup test program.

No violations were identified.

3.0

A Interface with the

PATP

The inspector

reviewed

QA Surveillance

Reports

88-10044

and 88-10047.

The inspector verified that the survei llances

were performed in

accordance

with applicable

QA procedures

and the commitments

made in the

surveillance

plan for the power ascension

test program.

\\r.

The inspector also observed

an on-shift gA engineer

preparing to perform

a surveillance of TC-6 steady

state testing activites.

A check list was

being utilized by the

gA engineer

to perform his surveillance

activities.

In addition, during the evaluation of power ascension

test

results,

the inspector verified that the results

had

been

reviewed

by gA.

No violations were identified.

4.0

Neutron Flux Noise Observations

During prior testing the licensee

had observed that when operating at

100%

core flow and

50% power, osci llations in APRM power and total core flow

exist.

These oscillations

are also quite evident

when operating

near

100% power

100% core flow.

The oscillations

were observed

by the

inspector to be nominally

10% on reactor flux with some higher peaks

and nominally

3% on total core flow with the plant operating at

100%

power.

The inspector inquired of the licensee activities to understand

the

reason for the osci llations and the analysis

to indicate that the facility

can operate with this condition.

The

NRC had issued

IE Information Notice

86-110

"Anomalous Behavior of Recirculation

Loop Flow in Jet

Pump

BWR

Plants"

on December

31,

1986.

The facility has

been obtaining data to try

to better understand

what is occurring.

Individual loop flows are

oscillating, with no change

in flow control valve position.

Current

reasons

theorize bi-stable flow regimes in the jet pump riser piping

relocating riser flows and thus changing overall

system resistance.

Each

individual loop has its own characteristics

response

with the flow regimes

sometimes

in phase.

and

sometimes

out of phase.

A loop may be in one

regime for periods

up to

a minute or as little as

a few seconds.

This

change

in total core flow is causing

a change

in neutron flux as

seen

by

the traces

in all the

APRNs (A-F) showing the

same flux shape

response.

The facility has utilized GE to analyze

and observe

plant response.

GE

BWR-5 product lines generally experience oscillation in neutron flux but

the response

at

NMP-2 is amplified by the recirculation

system

response.

GE has

responded

that the current plant oscillations did not result in

a

safety concern

and the plant can operate

as long as

NRC licensed

thermal

power limitations are not exceeded.

Fuel design considers

30% peak to

peak osci llations.

(Draft copy of GE response

was reviewed

by inspector).

The facility long term solution is to obtain

more data

and determine

a

course of action.

The facility is in contact

and

has results of an

overseas

plant that experienced

similar oscillations

and is aware of the

actions taken to mitigate the observed actions.

The licensee

has not yet

finalized their long range

plans in this regard.

5.

Exit Interview

At the conclusion of the inspection

on February

26,

1988

an exit meeting

was held with licensee

personnel

(identified in Section

1.0) to discuss

the inspection

scope,

findings and observations

as detailed in this

report.

At no time during the inspection

was written inspection findings

provided to the licensee

by the inspector.

Based

on the

NRC Region I

review of this report and discussions

held with licensee

representatives

during the inspection, it was determined that this report does

not

contain information subject to

10 CFR 2.790 restrictions.

ATTACHMENT A

TEST CONDITION 3 TESTING

Tests

Results

Reviewed

N2-SOT-1-3 Chemical

and 'Radiochemical

N2-SUT-02-3 Radiation

Measurements

N2-SUT-16-3 Selected

Process

Temperatures

and Water Level Measurement

N2-SUT-22-3 Pressure

Regulator Test

N2-SUT-23-3 Feedwater

System

N2-SUT-30-3 Reactor

Recirc System

N2-SUT-33-3 Drywell Piping Vibration

N2-SOT-35-3 Recirculation

Flow Calibration

N2-SUT-74-3 Off Gas

System

N2-SUT-79-3 Reactor Internal Vibration Measurement

N2-PP-3 Test Plateau

3 Procedure

TEST CONDITION 5 TESTING

N2-SUT-1-5 Chemi ca 1

and

Radi ochemi ca 1

N2-SUT-12-5

APRM Cal ibration

N2-SUT-16-5 Selected

Process

Temperatures

and Water Level Measurements

N2-SOT-19-5 Core Performance

N2-SUT-22-5 Pressure

Regulator

N2-SUT-23-5 Feedwater

System

N2-SUT-24-5 Turbine Valve Surveillance

N2-SUT-30-5 Reactor Recirculation

System

N2-SUT-.33-5 Drywell Piping Vibration

N2-SUT-77-5

BOP Piping Vibration

h