IE Bulletin 77-05, Electrical Connector Assemblies
ML17054D080
Person / Time
Site: Crane Constellation icon.png
Issue date: 11/08/1977
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE)
To:
Shared Package
ML17054D081 List:
References
IEB-77-05, IEB-77-5, NUDOCS 7909050218
Download: ML17054D080 (16)


Text

NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT WASHINGTON, 0.

C.

20555 ELECTRICAL. CONNECTOR ASSEMBLIES.,

~..

Description of Circumstances IE Bulletin 77-05 Date:

November 8, 1977 Page 1 of 2

~

%1 I Recent tests conducted by the Sandia Laboratories of electrical connector/

cable assemblies in a simulated post-LOCA containment environment (LWR) demonstrated that the assemblies failed to perform in an acceptable manner.

The connectors are the pin and socket type, with metal shell and screw couplings.

The specific test specimens were manufactured by Bendix, ITT Cannon and. Gulton Industries u'sing combinations of Anaconda and ITT Surprenant. cables.

Details of the specific connector/cable combinations, test conditions, test'esults and.other pertinent informa-tion are described in the Attachment.

While. electrical connectors of the type tested are not normally used in applications that are required to survive LOCA conditions, it is not possible in the absence of specific information to conclude that such applications do not exist.

Further, it is unknown whether other manu-facturers have supplied similar assemblies, whether such assemblies have

'een properly qualified for the intended service or whether these type of assemblies are utilized in applications that must continue to operate reliably in a LOCA environment.

Action To Be Taken By Licensees and Permit Holders:

FOR ALL POWER REACTOR FACILITIES WITH AN OPERATING LICENSE OR A CONSTRUCTION PERMIT:

~ 1.

. Determine whether, your. facility. utilizes or plans to uti.lize elec-trical connector assemblies of the t.~pe tested by Sandia Laboratories, or any other similar type, in systems that are located inside containment, are subject to a

LOCA environment and're required to be operable during a

LOCA.

2.

If any such applications are identified, review the adequacy of qualification testing for the assemblies and submit the documenta-tion for NRC review.

IE Bulletin 77-05 Date:

November 8, 1977 Page 2 of 2 3.

If evidence is not available to support a conclusion of adequacy, submit your plans and programs toward qualifying existing equipment or your plans for replacing unqualified assemblies with qualified equipment. ".

Provide your response in writing. within 30. days for facilities. with.

an, operating license and within 60"days foi faciTi'ties'ith,a construction permit.

Reports should be submitted to the Director of the appropriate NRC Regional Office and a copy should be forwarded to the U. S. Nuclear Regulatory Commission, Office of Inspection and Enforcement, Division of Reactor Construction Inspection, Washington,'.

C.

20555.

Approved by GAO, B-180225 (R0072); clearance expires 7-31-80.

Approval was given under a blanket. clearance specifically for identified generic.

problems.

Attachments:

A.

Trip Report by W. R. Rutherford Electrical Connector Assemblies B.

Test Profile, Figures 1 and 2

TRIP REPORT by W. R. Rutherford IE Bulletin 77-05 November 8, 1977

~. ELECTRICAL CONNECTOR ASSEMBLIES.

I

.On September I, 1977=.a meeting. was held in Albuquerque, New Mexico to investigate 'the electrical'onnector assembly 'malfunctions or failures.

that occurred during te'sts under LOCA conditions performed by Sandia Laboratories.

The following is a description of the equipment, test scope and results of these tests.

Equipment The test assemblies of particular interest consisted of three types of connectors:

Bendix,. ITT Cannon, and Gulton installed on two types of cables; Anaconda and ITT Surprenant.

1.

Bendix Connector:-

A 3 conductor/No.

12 AWG with crimp pin conductors, anodized aluminum shell, silicone rubber insert, rigid back plane potting, pliable over-potting.

2.

ITT Cannon Connector; A 3 conductor/No.

12 AWG with crimp pin conductors, anodized aluminum shell, silicone rubber 'insert, anodized aluminum back shell, rubber packing boot, mechanical retaining clamp.

3.

Gulton Connector:

A 3 conductor/No.

12 AWG with crimp pin conductor, stainless steel shell, hard fiber insert, pin back sealed with RTV 112, stainless

shell, back plane poured with Sylgard potting, mechanical clamp termination.

4.

. Anaconda Cable:

A 3 conductor/No.

12 AWG, tinned copper conductor, 30 mil ethylene-propylene rubber insulation 15 mil Hypalon jacket, cable asbestos

tape, 60 mil. Hypalon 'jacket, rated'00 volts, cable diameter 0..55".

5.

ITT Surprenant Cable:

A 3 conductor/No.

12 AWG, tinned copper conductor, 30 mil Exane II insulation, silicone glass tape, 65 mil Exane jacket, rated 600 volts, cable diameter 0.455".

Attachment A

Page 1 of 3

Test Scope IE Bulletin 77-05 November 8, 1977 The three tests performed by Sandia were composed of two sequential and one simultaneous exposure to LOCA'nvironments.

In each case the equip-ment was exposed to.radiation. and thermal. aging pr ior to operating under

., the simulated LOCA conditions.

Figures I and 2 describe the test pro-

., files. for sequential..and.

simultaneous. tests. respectively.(Sandia tests..",.

'ere designed to study synergistic effects).

Each of the tests satisfy the intent of IEEE 323-1974.

The assemblies were electrically loaded to 20 amperes and %00 volts at the start of the tests.

Insulation resist-ance and capacitance measurements wer e recorded during the tests to indicate damage.

The equipment assemblies with respect to the sequential and simultaneous tests performed.

wer e as follows:

1'.

Sequential Tests (Two)

Gulton Connector/ITT Cable Gulton Connector/Anaconda Cable Bendix Connector/ITT Cable ITT Connector/ITT Cable 2.

Simultaneous Test (One) 1 Assembly I Assembly 2 Assemblies I Assembly ITT Connector/ITT Cable Bendix Connector/ITT Cable Bendix Connector/Anaconda Cable I Assembly 1 Assembly 2 Assemblies Test Results Both ITT Cannon connector assemblies and both Gulton connector assemblies showed almost immediate damage in terms of insulation resistance and

. capacitance as the 70 psig steam was,applied.

.. The ITT'annon connector'assembTy.

failures appeared to be back plane boot seal leakage.failures.

The assembly construction did not contain potting compound (by design) to protect the pin backs.

Therefore, boot failure leads directly to connector failure.

In the case of the Gulton Assemblies, failures were attributed to both the mating surface interface and the back plane seal.

The design uses a rigid insert around the mating pins and the 0-ring seals are Attachment A

Page 2 of 3

~

~

IE Bulletin 77-05 November 8, 1977 bypassed by an alignment key slot.

This design may lead to leaks due to non-uniform confinement of the 0-ring which could cause arcing between pins.

Neutron radiography revealed inadequate amounts of potting compound

. (voids).:and cracki.ng of potting, compound.

These conditions, could, account for back plane failures.

Neutron radiography performed on untested connectors.revealed simi.lar condi.tions, i.e,, voids and cracking, thus

'ndicating an apparent quality control p'roblem at Gulton's facilsty..

Other problems detected were identified as:

1.

The shrink tube used over the pin cable interface was spl'it length-wise and had pulled away.

2.

The potting material showed virtually no adhesion to, or sealing

between, the cable jacket, insulation, and the connector shell.

3.

The mechanical clamp had: been secured so tightly that it cut the cable jacket.

The Bendix connector assembly was the only type to survive an entire test cycle.

One Bendix/Anaconda assembly malfunctioned after about eight days into the 10 psig profile and the Bendix/ITT assembly experienced decreasing resistance and increasing capacitance through the simultaneous tests until both readings were off scale at the end of the 10 psig profile.

A second Bendix/Anaconda assembly survived the simultaneous tests.

During the sequential tests only Bendix and ITT Cannon assemblies were involved and both assemblies failed.

The failures of these assemblies would be difficult to define as either connector or cable failures.

The ITT cable exhibited a shrinking characteristic which could have provided a leak path through the sealing medium of the connector.

Attachment A

Page 3 of 3

~ ~

PHASF X.- P<<<<ASK XX

'AGXNG gtl~CTBXCAlJ LOADING

~

'EQQEHTXAL TEST PBOFXLE

~

~

P<<CASE XXX LOCA SXHULATXOH

'V ~

BATED RhOIAVION/

i DSE 'BATE

<<ONE l'tn/t NONE

~

~

CN"":.<<ICAL SPiRAY NONE-NONE" CHEHXCAK SPRAY Hear s 157 C/70 PSXG/100$

/

~

~

1<<<<0 C/<<<<0 PSTQ/100$

to~

YH YYi E':PEBAVURB/.130 C/

. Ambient Pr.iSSgg"-/

0 PSZG HYL HL'HID'Y LA Co K

to

~ ~

jo ri tn H

A lh Iv)~

C I'7

~

IQ I

u o(/I 129. C/25 PSIO/100$

].:

113 C/10 PSXG/100$

/

Apb1ent

/

Q

~ M 0 tii l--

l

0

ELECTBICAK, LOADIllG RADI<'s a IO<'$/

OOS< RATE.

CilENICA4 scree PHASa I hGXllG

. BhTE llR/liR

)i.WR/ilR

~HONE SXYiULTAHEOUS TEST PBOPXLE

~

PHASE II LOCA SI)lUlTATXOX RATED

~

~

12 lhB

)6 llB~

140 NR 2 llR/llR 1 gR/HR

'.4 lrR/AIR CHElQCAL SPPAY gQ.Hauhg')

157 C/70 PSIG/100'

~

100 C/00 PSIG/100$

/

7E~rlPERhTUM/

1)0'/

PRE"Sun /

0 P$ IG habit ItUNEDiTY

~

~

129 C/25 PSZG/100$

))3.C/)0 PSXO/)00'NDI iiT

/

o w

CP..*

~

M

~

A th n

Pn n

cn

'D K

N l

W 4J N

0 0

'X CO C4.

0ll g)

~l H

0 Q

'N

0) P V M LD I

M O Ul

IE Bulletin 77-05 November 8, 1977 Bulletin..-Subject..

No.

77-04 Calcul ti a

onal" Error.

'ffecting the Design Performance of a System for Controlling pH of Containment Sump Water Following a LOCA 11/4/77 LISTING OF IE BULLETINS ISSUED IN 1977

~ '..

Date Issued Issued To All PWR Power Reactor Facilities with an Operating License (OL) or Contruction Permit (CP) 77>>03 77-02 On-Line-Tes ting of the W Solid State.

Protection System Potential Failure Mechanism in Certain W AR Relays with Latch Attachments 9/12/77 9/12/77 All W Power Reactor Facilities with an Operating License (OL) or Construction Permit (CP)

All Holders of Operating Licenses (OL) or Construc-tion Permits (CP) 77-01 Pneumatic Time 4/29/77 Delay Relay Set Point Drift All Holders of Operating License (OL) or Construc-tion Permit (CP)

Enclosure 2

Page 1 of 1