Audit Summary to Review KHNP APR1400 Non-LOCA Chapter 15, Transient and Accident Analyses - Memo
ML17013A146
Person / Time
Site: 05200046, PROJ0782
Issue date: 08/29/2018
From: Jim Steckel
NRC/NRO/DNRL/LB2
To: Michael Mccoppin
NRC/NRO/DNRL/LB2
Lauron C / 415-2736
Shared Package
ML17013A130 List:
References
Download: ML17013A146 (4)


Text

August 29, 2018 MEMORANDUM TO: Michael McCoppin, Chief Licensing Branch 2 Division of Licensing, Siting, and Environmental Analysis Office of New Reactors FROM: James Steckel, Project manager /RA Carolyn Lauron Acting for/

Licensing Branch 2 Division of Licensing, Siting, and Environmental Analysis Office of New Reactors

SUBJECT:

AUDIT

SUMMARY

FOR THE KOREA HYDRO AND NUCLEAR POWER CO. LTD ADVANCED POWER REACTOR 1400 NON-LOCA CHAPTER 15 TRANSIENT AND ACCIDENT ANALYSES REVIEW OF THE APR1400 DESIGN CONTROL DOCUMENT The purpose of this memorandum is to document for Licensing Branch 2, the summary of the Regulatory Audit conducted from June 10, 2015 through June 16, 2016. During this period a team from the U.S. Nuclear Regulatory Commission (NRC), Office of New Reactors (NRO),

performed an audit of Korea Hydro and Nuclear Power Co., Ltd. (KHNP), Advanced Power Reactor 1400 (APR1400) information related to Chapter 15 of the KHNP standard design certification application. The purpose of the audit was to gain a better understanding of the calculations supporting the safety analyses presented in the following sections of Chapter 15 of the APR1400 Design Control Document (DCD) and related documentation: 15.0.2, 15.1.1, 15.1.2, 15.1.3, 15.1.4, 15.4.1, 15.4.2, 15.4.3, 15.4.4, 15.4.8, 15.6.2, and 15.6.3. Information contained in the APR1400 Electronic Reading Room was reviewed, and information submitted by KHNP, as part of responses to requests for additional information, was evaluated.

The enclosed summary provides the observations made by the NRC staff during the audit, along with clarifications discussed with KHNP during the audit. A list of audit team members is provided in the audit summary, along with the list of documents reviewed by the NRC staff.

The Enclosure contains the Audit Summary. The plan for this audit, dated June 10, 2015, is documented and can be found in the Agencywide Documents Access System (ADAMS) under Accession No. ML15147A597.

CONTACT: James A. Steckel, NRO/DLSE/LB2 (301) 415-1026 Docket No. PROJ0782

Enclosure:

As stated cc: See next page

Package: ML17013A130 Pkg.

Letter: ML1717013A146 NRR-105 OFFICE DNRL/LB2: PM DLSE/LB2: LA DLSE/LB2: PM NAME JSteckel IBetts MMcCoppin DATE 01/13/17 08/22/18 08/29/18 KHNP Mailing List 7/4/2018 Daegeun (Tony) Ahn Director KHNP Washington DC Center 8100 Boone Blvd, Suite 620 Vienna, VA 22182 Page 1 of 2

E-mail yunho.kim@khnp.co.kr [Yun-Ho Kim]

hansang.kim@khnp.co.kr [Hansang Kim]

dohwan.lee@khnp.co.kr [Do-Hwan Lee]

junghokim@khnp.co.kr [Jung-Ho Kim]

jiyong.oh@khnp.co.kr [Jiyong Andy Oh]

ahn.daegeun@khnp.co.kr [Daegeun Tony Ahn]

jksuh@khnp.co.kr [Jeong Kwan Suh]

hachewung@khnp.co.kr [Che Wung Ha]

kang.deogji@khnp.co.kr [Deog Ji Kang]

sunguk.kwon@khnp.co.kr [Sun Guk Kwon]

ptmaster300@kepco.co.kr [Hyun Chul Park]

sisk1rb@westinghouse.com [Rob Sisk]

robert.sweeney@consultant.aecom.com [Robert Sweeney]

Page 2 of 2