Watts Bar Nuclear Plant, Post Office Box 2000 Spring City, Tennessee 37381 January 5, 2017 10 cFR 50.4 10 CFR 50, Appendix E, Section V 10 CFR 50.54(qX5) 10 cFR 72.4 10 cFR 72.44(f)

ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001

Subject:

Watts Bar Nuclear Plant, Unit 1 & Unit 2 Facility Operating License No. NPF-90 NRC Docket No. 50-390, 50-391 Emergency Plan Implementing Procedure Revision ln accordance with the requirements of 10 CFR Part 50, Appendix E, Section V, 10 CFR 50.54(qX5), and 10 CFR 72.44(f), the following Emergency Plan lmplementing Procedure (EPIP) has been revised to correct the location of the Rad Monitor 1&2-RE-90-61, added step 3.1.E to include information from the NRC lnterim Staff Guidance document about timeliness of classification, changed Shift Manager to SED as the responsible position in the Note prior to step 3.2.A for clarity, and added flood as a natural phenomena example in EAL 7.5, Spent Fuel Storage:

EPIP Revision Title Emergency Plan Classification Logic Effective Date 12t02t2016 0447 There are no regulatory commitments in this letter. Please direct all questions concerning this matter to Thomas Detchemendy, Emergency Preparedness Manager, at $23) 365-3232.

Paul Simmons Site Vice President Watts Bar Nuclear Plant Respectfully,

U.S. Regulatory Commission January 5, 2017 Page 2 cc:

NRC Regional Administrator - Region II NRC Senior Resident Inspector - Watts Bar Nuclear Plant NRC Project Manager - Watts Bar Nuclear Plant