Discusses 980727 Telcon Between to Mckernon & R Jett Re Arrangements Made for Administration of Licensing Exams at Diablo Canyon Power Plant During Week of 990125
ML16342E198
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 07/29/1998
From: Pellet J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Rueger G
PACIFIC GAS & ELECTRIC CO.
References
50-275-99-301, 50-323-99-301, NUDOCS 9808050099
Download: ML16342E198 (12)


Text

CATEGORY 2 ~

REGULATORY XNFORMATXON DISTRIBUTION SYSTEM (RIDS)

ACCESSION NBR:9808050099 DOC.DATE: 98/07/29 NOTARIZED: NO FACIL:50-275 Diablo Canyon Nuclear Power Plant, Unit 1, Pacific Ga 50-323 Diablo Canyon Nuclear Power Plant, Unit 2, Pacific Ga AUTH.NAME AUTHOR AFFILIATION PELLET,J.L.

Region 4 (Post 820201)

RECXP.NAME RECIPIENT AFFILIATION RUEGER,G.M.

Pacific Gas

'8 Electric Co.

SUBJECT:

Discusses 980727 telcon between TO McKernon E

R Jett re arrangements made for administration of licensing exams at Diablo Canyon Power Plant during week of 990125.

DISTRIBUTION CODE:

IE42D COPIES RECEIVED:LTR 1

ENCL 0 SIZE:

TITLE: Operator Licensing Examination Reports NOTES:

DOCKET 05000275 05000323 RECIPIENT ID CODE/NAME PD4-2 PD COPIES LTTR ENCL RECIPIENT ID CODE/NAME BLOOM,S COPIES LTTR ENCL R"

INTERNAL: ACRS NRR/DRCH/HOHB EXTERNAL: NOAC FX E CENTER NRC PDR 01 NOTE TO ALL "RIDS" RECIPIENTS:

PLEASE HELP US TO REDUCE WASTE TO HAVE YOUR NAME OR ORGANIZATION REMOVED FROM DISTRIBUTION LISTS OR REDUCE THE NUMBER OF COPIES RECEIVED BY YOU OR YOUR ORGANIZATION, CONTACT THE DOCUMENT CONTROL DESK (DCD)

ON EXTENSION 415-2083 Co TOTAL NUMBER OF COPIES REQUIRED:

LTTR 8

ENCL

~p,a REC(g, fp

~4 0

Cy I

O UNITED STATES NUCLEAR REGULATORY COMMISSION REGION IV 611 RYAN'PLAZADRIVE. SUITE 400 ARLINGTON,TEXAS 76011.8064 July 29, 1998 Gregory M. Rueger, Senior Vice President and General Manager Nuclear Power Generation Bus. Unit Pacific Gas and Electric Company Nuclear Power Generation, B14A 77 Beate Street, Room 1451 P.O. Box 770000 San Francisco, California 94177

SUBJECT:

NRC INSPECTION 50-275/99-301; 50-323/99-301 Dear Mr. Rueger.

In a telephone conversation on July 27, 1998, between Messrs. T. O. McKemon and R. Jett, arrangements were made for the administration of licensing examinations at the Diablo Canyon Power Plant during the week of January 25, 1999.

Your staff has agreed to prepare the examinations based on the guidelines in Revision 8 of NUREG-1021, "Operator Licensing Examination Standards for Power Reactors."

The NRC regional office willdiscuss with your staff any changes that might be necessary before the examinations are administered.

To meet the above schedule, it willbe necessary for your staff to furnish the examination outlines by September 27, 1998. The examinations and the supporting reference materials identified in Attachment 2 of ES-201 willbe due by November 30, 1998.

The NRC will review the finalized examinations and complete validation of the examinations at your facilityduring the week of or just prior to January 25, 1999. Any delay in receiving the required examination and reference materials, or the submittal of inadequate or incomplete materials, may cause the examinations to be rescheduled.

In order to conduct the requested written examinations and operating tests, it will be necessary for your staff to provide adequate space and accommodations in accordance with ESQ02 and to make the simulation facility available on the dates noted above, In accordance with ES-302, your staff should retain the original simulator performance data (e.g., system pressures, temperatures, and levels) generated during the dynamic operating tests until the examination results are final.

Appendix E of NUREG-1021 contains a number of NRC policies and guidelines that willbe in effect while the written examinations and operating tests are being administered.

To permit timely NRC review and evaluation, your staff should submit preliminary reactor operator and senior reactor operator license applications (Office of Management and Budget (OMB) approval number 3150-0090), medical certifications (OMB approval number 3150-0024),

980805009'F 980729 PDR ADOCK 05000275 V

PDR

Pacific Gas and Electric Company and waiver requests (ifany) (OMB approval number 3150-0090) at least 30 days before the first examination date.

Ifthe applications are not received at least 30 days before'the examination

'date, a postponement may be necessary.

Signed applications certifying that all training has been completed should be submitted at least 14 days before the first examination date.

This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.).

These information collections were approved by the Office of Management and Budget, approval number 3150-0101, which expires on April 30, 2000.

The public reporting burden for this collection of information is estimated to average 500 hours0.00579 days <br />0.139 hours <br />8.267196e-4 weeks <br />1.9025e-4 months <br /> per response, including the time for reviewing instructions, gathering and maintaining the data needed, writing the examinations, and completing and reviewing the collection of information.

Send comments on any aspect of this collection of information, including suggestions for reducing the burden, to the Information and Records Management Branch (T-6 F33),

U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by internet electronic mail at BJS1ONRC.GOV; and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0101), Office of Management and Budget, Washington, DC 20503.

The NRC may not conduct or sponsor, and a person is not required to respond to, a collection of information unless it displays a currently valid OMB control number.

Thank you for your cooperation in this matter.

Mr. R. Jett has been advised of the policies and guidelines referenced in this letter. Ifyou have any questions regarding the NRC's examination procedures and guidelines, please contact Mr. Tom McKernon at 817-860-8153 or Mr. John Pellet at 81 7-860-8159.

Sincerely, John L. Pellet, Chief Operations Branch Division of Reactor Safety Docket Nos.:

50-275; 50-323 License Nos.: DPR-80; DPR-82 CC:

Dr. Richard Ferguson Energy Chair Sierra Club California

'I 100 lith Street, Suite 311 Sacramento, California 95814

Pacific Gas and Electric Company Ms. Nancy Culver San Luis Obispo Mothers for Peace P.O. Box 164 Pismo Beach, California 93448 Chairman San Luis Obispo County Board of Supervisors Room 370 County Government Center San Luis Obispo, California 93408 Mr. Truman Burns(Mr. Robert Kinosian California Public Utilities Commission 505 Van Ness, Rm. 4102 San Francisco, California 94102 Robert R. Wellington, Esq.

Legal Counsel Diablo Canyon Independent Safety Committee 857 Cass Street, Suite D Monterey, California 93940 Mr. Steve Hsu Radiologic Health Branch" State Department of Health Services P.O. Box 942732 Sacramento, California 94234 Christopher J. Warner, Esq.

Pacific Gas and Electric Company P.O. Box 7442 San Francisco, California 94120 Robert P. Powers, Vice President and Plant Manager Diablo Canyon Power Plant P.O. Box 56 Avila Beach, California 93424 Managing Editor Telegram-Tribune 1321 Johnson Avenue P.O. Box 112 San Luis Obispo, California 93406

Pacific Gas and Electric Company Tim Blake, Learning Services Manager Pacific Gas and Electric Company Nuclear Power. Generation, B14A 77 Beale Street, Room 1451 P.O. Box 770000 San Francisco, California 94177

PaciTic Gas and Electric Company bcc to DCD (rsel)(EE~2 I

Regional Administrator Resident Inspector DRS Director DRS Deputy Director DRP Director DRS-PSB Branch Chief (DRP/E, WCFO)

Senior Project Inspector (DRP/E, WCFO)

Branch Chief (DRP/TSS)

M. Hammond (PAO, WCFO)

WCFO File MIS System RIV File R. Gallo (HOLB/NRR) (MS: 9 D4)

L. Hurley, Licensing Assistant, DRS(OB DOCUMENT NAME: R:5 DC>DC8301lt.tom To receive copy of document, Indicate in box: "C" = Cop without enctosures "E" = Copy with enctosures "N"= No copy RIV:RE:DRS/0 TMMcKernon:Im 07 98 C:OB E