UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON) D C 2055&4001 3une 24, 1997 Hr. Gregory H.
Rueger Pacific Gas and Electric Company NPG - Hail Code A10D P. 0.
Box 770000 San Francisco, Cali fornia 94177
SUBJECT:
SAFETY EVALUATION OF RELIEF REQUESTS FOR PUMPS AND VALVES INSERVICE TESTING PROGRAH - DIABLO CANYON NUCLEAR POWER PLANT, UNIT NOS.
1 AND 2 (TAC NOS.
H94391 AND H94392)
Dear Hr. Rueger:
By letter dated December 29, 1995, Pacific Gas and Electric Company submitted relief requests P-RRl, P-RR2, and V-RR12 for Diablo Canyon Nuclear Power Plant, Unit Nos.
1 and 2.
Second 10-year Interval Inspection Program Plan, for inservice testing of pumps and valves.
The staff has completed its review of the proposed relief requests.
The basis for the staff's conclusions are contained in the enclosed satety evaluation.
The staff has determined that, with respect to Request for Relief P-RR2, the proposed alternative testing is authorized pursuant to 10 CFR 50.55a(a)(3)(ii ), in that compliance would result in a hardship or unusual difficultywithout a compensating increase in the level of quality and safety.
This alternative testing is authorized for a interim period of six months from the date of this letter.
PG&E should provide the staff with a revised request indicating the actions taken and providing additional basis to raise the alert limit.
The staff has determined that. with respect to Request for Relief V-RR12, the proposed alternative is unacceptable because it does not show the impracticability of testing uarter ly and during cold shutdowns as required by ON-10.
Paragraph 4.2. 1.2.
herefore.
Request for Relief V-RR12 is denied.
The staff has determined that. with respect to Request for Relief P-RRl, the relief request does not have sufficient detail to justify the proposed alternative.
Therefore, Request for Relief P-RRl is denied.
. P1 MIIC IRILE Cm@II eIIPV ZoOO<"'P706260240 970624
'PDR ADQCK 05000275 P
POR
Mr. Gregory M. Rueger 3une 24, 1997 This submittal indicates weaknesses in the engineering organization in that in the case of V-RR12, there was an apparent lack of understanding of the requirements of OM-10, and in the case of P-RR1, there was-less than a
thorough argument presented to justify the request.
Docket Nos. 50-275 and 50-323
Enclosure:
Safety Evaluation cc w/encl:
See next page Sincerely, Original Signed By William H. Bateman, Director Project Directorate IV-2 Division of Reactor Projects III/IV Offi.ce of Nuclear Reactor Regulation DISTRIBUTION:
PDocket Filets PDIV-2 Reading PUBLIC JRoe EAdensam (EGA1)
WBateman SBloom EPeyton ACRS KDempsey TLH3 (SE)
GHill (4)
OGC MDapas
- PGwynn, RIV
- KPerkins, RIV/WCFO DOCUMENT NAME:
DC94391. SE
- See Previous Concurrence OFC PDIV- /PM PDIV-2/LA OGC*
PDIV-2 NAME DATE SBlo 6/~ /97 Eey n
668/97 AL EHoller 5/2/97 WBatema
I t
I
Hr. Gregory H. Rueger June 24, f997 cc w/encl:
NRC Resident Inspector Diablo Canyon Nuclear Power Plant c/o U.S. Nuclear Regulatory Commission P. 0.
Box 369 Avila Beach, California 93424 Dr. Richard Ferguson, Energy Chair Sierra Club California 1100 11th Street, Suite 311 Sacramento, California 95814 Hs.
Nancy Culver San Luis Obispo Mothers for Peace P. 0.
Box 164 Pismo Beach, California 93448 Chairman San Luis Obispo County Board of Supervisors Room 370 County Government Center San Luis Obispo, California 93408 Hr. Truman Burns Hr. Robert Kinosian California Public Utilities Commission 505 Van Ness, Room 4102 San Francisco, California 94102 Hr. Steve Hsu Radiologic Health Branch State Department of Health Services Post Office Box 942732 Sacramento, California 94232 Diablo Canyon Independent Safety Committee ATTN:
Robert R. Wellington, Esq.
Legal Counsel 857 Cass Street, Suite D
Monterey, California 93940 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission Harris Tower
& Pavillion=
611 Ryan Plaza Drive, Suite 400 Arlington, Texas 76011-8064 Christopher J. Warner, Esq.
Pacific Gas E Electric Company Post Office Box 7442 San Francisco, California 94120 Hr. Robert P.
Powers Vice President and Plant Manager Diablo Canyon Nuclear Power Plant P. 0.
Box 56 Avila Beach, California 93424 Telegram-Tribune ATTN:
Managing Editor 1321 Johnson Avenue P.O.
Box 112 San Luis Obispo, California 93406
'