Forwards Insp Repts 50-275/97-02 & 50-323/97-02 on 970202-0315 & Notice of Violation
ML16342D598
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 04/15/1997
From: Gwynn T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Rueger G
PACIFIC GAS & ELECTRIC CO.
Shared Package
ML16342D599 List:
References
NUDOCS 9704220098
Download: ML16342D598 (8)


See also: IR 05000275/1997002

Text

4

0

Cy

0

+**+~

UNITEDSTATES

NUCLEAR REGULATORY COMMISSION

~

REGION IV

611 RYAN PLAZADRIVE, SUITE 400

ARLINGTON,TEXAS 76011-8064

April 15, 1997

Gregory M. Rueger, Senior Vice President

and General Manager

Nuclear Power Generation

Bus. Unit

Pacific Gas and ElectricCompany

Nuclear Power Generation, B14A

77 Beale Street, Room 1451

P.O. Box 770000

San Francisco, California 94177

SUBJECT:

NRC INSPECTION REPORT 60-276/97002; 50-323/97002 AND NOTICE OF

VIOLATION

Dear Mr. Rueger:

This refers to the inspection conducted

on February 2 through March 15, 1997, at your

Diablo Canyon Nuclear Power Plant, Units

1 and 2 reactor facilities. The enclosed report

presents the scope and results of that inspection.

During the inspection period the conduct of activities at the Diablo Canyon facility was

characterized

by performance with good safety conscious

operations.

Operations

implemented management

expectations

and improved formality in the control room, and

maintenance

demonstrated

good work practices.

Engineering assessments

were self-

critical; however, one violation with three examples of failures to reflect design criteria in

procedures

and instructions was identified.

The examples involve the failure to incorporate

limiting design basis assumptions

into procedures

and instructions for the control of

refueling water storage tank level instruments

and for ITIaintaining spent fuel pool

, temperatures.

This violation demonstrates

the need to assure that the operation of plant

equipment is consistent with the design bases.

Additional attention appears warranted for

engineering organization to assure the actions to mariage and reduce the engineering

backlog are effective.

The violation is cited in the enclosed

Notice of Violation (Notice) and the circumstances

surrounding this violation is described

in detail in the enclosed report.

Please note that you

are required to respond to this letter and should follow the instructions specified in the

enclosed

Notice when preparing your response.

The NRC will use your response,

in part,

to determine whether further enforcement action is necessary to ensure compliance with

regulatory requirements.

lllllll]II7ll]t13llltlll]IIII

In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice,"

a copy of this letter,

its enclosures,

and your response

will be placed in the NRC Public Document Room (PDR).

To the extent possible, your response

should not include any personal privacy, proprietary,

or safeguards

information so that it can be placed in the PDR without redaction.

~<AA3i'I

9704220098

970415

PDR'DOCK 05000275

8

PDR

C

0

Pacific Gas and Electric Company

-2-

Should you have any questions concerning this inspection, we will be pleased to discuss

them with you.

Sincerely,

Thomas

P. Gwynn, Director

Division of Reactor Projects

Dockets:

50-275

50-323

Licenses:

DPR-80

DPR-82

Enclosures:

1.

Notice of Violation

2.

NRC Inspection Report

50-275/97002; 50-323/97002

cc w/enclosures:

Dr. Richard Ferguson

Energy Chair

Sierra Club California

1100 lith Street, Suite 311

Sacramento,

California 95814

Ms. Nancy Culver

San Luis Obispo Mothers for Peace

P.O. Box 164

~

Pismo Beach, California 93448

'hairman

San Luis Obispo County Board of

Supervisors

Room 370

County Government Center

San Luis Obispo, California 93408

Mr. Truman Burns>Mr. Robert Kinosian

California Public Utilities Commission

505 Van Ness, Rm. 4102

San Francisco, California 94102

t

Pacific Gas and Electric Company

-3-

Robert R. Wellington, Esq.

Legal Counsel

Diablo Canyon Independent

Safety Committee

857 Cass Street, Suite D

Monterey, California 93940

Mr. Steve Hsu

Radiologic Health Branch

State Department of Health Services

P.O. B'ox 942732

Sacramento,

California 94234

Christopher J. Warner, Esq.

Pacific Gas and Electric Company

P.O. Box 7442

San Francisco, California 94120

I

Robert P. Powers, Vice President

and Plant Manager

Diablo Canyon Power Plant

P.O. Box 56

Avila Beach, California 93424

Managing Editor

Telegram-Tribune

1321 Johnson

Avenue

P.O. Box 11'2

San Luis Obispo, California 93406

1

Pacific Gas and Electric Company

-4-

E-Mail report to T. Boyce (THB)

E-Mail report to NRR Event Tracking System (IPAS)

E-Mail report to Document Control Desk (DOCDESK)

bcc to DCD IE01

bcc distrib. by RIV:

Regional Administrator

DRP Director

Branch Chief (DRP/E, WCFO)

Senior Project Inspector (DRP/E, WCFO)

Branch Chief (DRP/TSS)

WCFO File

W. L. Brown, RC

OE:EA File, MS: 7-H5

Resident Inspector

DRS-PSB

MIS System

RIV File

M. Hammond (PAO, WCFO)

G. F. Sanborn,

OE

J. Lieberman, OE, MS: 7-H5

DOCUMENT NAME: R:t DCiDC702RP.MDT

To receive copy of document,

indicate In box: "C" = Copy without

nc

sures

"E" = Copy with enclosures "N" = No copy

RIV:RI:DRP/E

MDTschiltz

C:DRP/E

D:DRP

HJWong ~~ TPGw nn

04/ ~7

04

97

04/

97

04/ /97

OFFICIAL

ECORD COPY

04/ /97

~

~