UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION IV
611 RYAN PLAZADRIVE, SUITE 400
ARLINGTON,TEXAS 76011 8064
FEB T l995
Pacific Gas
and Electric Company
Nuclear Power Generation,
B14A
ATTN:
Gregory H. Rueger,
Senior Vice
President
and General
Manager
Nuclear
Power Generation
Bus. Unit
77 Beale Street,
Room 1451
P.O.
Box 770000
San Francisco,
94177,
SUBJECT:
NRC INSPECTION
REPORT 50-275/95-04;
50-323/95-04
In a telephone
conversation
on January
25,
1995 between
Messrs J.
Welsch
and J. Pellet,
arrangements
were
made for the administration of licensing
examinations
at the Diablo Canyon Nuclear
Power Plant.
The examinations
are scheduled for the week of May 22,
1995.
Your staff will
be given
an opportunity to review the licensing examinations
in accordance
with the guidelines in Revision
7 of NUREG-1021,
"Operator Licensing Examiner
Standards,"
(ES-201,
Attachment
4) during the week of May 8,
1995.
To prepare
the examinations
and meet the above schedule, it will be necessary
for your staff to furnish the reference materials identified in Attachment
2
of ES 201 by February
22,
1995.
Any delay in receiving approved
and indexed
reference
material or the submittal of inadequate
or incomplete reference
material
may result in the examinations
being rescheduled.
The
NRC will prepare
and administer the written examinations
in accordance
with ES-401
and
ES-402 of NUREG-1021.
In order to conduct the requested
examinations, it will be necessary
for your staff to provide adequate
space
and accommodations
on the date noted above.
The NRC's guidelines for
administering the written examinations
are described
in ES-402,
Attachment
1.
The
NRC will prepare
and administer the operating tests
in accordance
with
and
ES-302 of NUREG-1021.
In order to conduct the requested
operating
tests, it will be necessary
for your staff to make the simulation facility
available
on the dates
noted above.
Your staff should retain the original
simulator performance
data (e.g.,
system pressures,
temperatures,
and levels)
generated
during the dynamic operating tests until the examination results
are
final.
Attachment
2 of ES-402
and Attachment
1 of ES-302 contain
a number of
NRC policies
and guidelines that will be in effect while the written
examination
and operating tests
are being administered.
95O2qq0079
SS02
ADOCK 0
8
Pacific Gas
and Electric Company
Your staff should submit preliminary reactor operator
and senior reactor
operator license applications
and waiver requests
at least
30 days before the
first examination
date
so that the
NRC will be able to review the applications
and the medical certifications
and evaluate
any requested
waivers.
If the
applications
are not received at least
30 days before the examination date,
a
postponement
may be necessary.
Final, signed applications certifying that all
training has
been
completed
should
be submitted at least
14 days before the
first examination date.
i
This request is covered
by Office of Management
and Budget
(OHB) Clearance
Number 3150-0101,
which expires October 31,
1995.
The estimated
average
burden is 7.7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br /> per response,
including gathering,
photocopying,
and
mailing the required material.
Send
comments
regarding this burden estimate
or any other aspect of this collection of information, including suggestions
for reducing this burden,
to the Information and Records
Management
Branch,
T-6 F33, Division of Information Support Services,
Office of Information
Resources
Management,
U.S. Nuclear Regulatory Commission,
D.C.
20555;
and to the Paperwork Reduction Project
(3150-0101), Office of
Information and Regulatory Affairs, NEOB-10202, Office of Hanagement
and
Budget, llashington,
D.C. 20503.
Thank you for your cooperation
in this matter.
Hr. Welsch
has
been
advised of
the policies
and guidelines referenced
in this letter.
If you have
any
questions
regarding the NRC's examination
procedures
and guidelines,
please
contact Mr. S. H'Crory at (817)860-8265 or Hr. J. Pellet at (817)860-8159.
Sincerely,
Dockets:
50-275
50-323
Licenses:
DPR-82
omas
P.
Gw nn, Director
Division of
actor Safety,
RIV
CC:
ATTN:
Dr. Richard
Ferguson
Energy Chair
6715 Rocky Canyon
Creston,
93432
4
0
Pacific Gas
and Electric Company
-3-
San Luis Obispo
Hothers for Peace
ATTN:
Hs. Nancy Culver
P.O.
Box 164
Pismo Beach, California
93448
Hs. Jacquelyn
C. Wheeler
P.O.
Box 164
Pismo Beach, California
93448
The County Telegram Tribune
ATTN:
Hanaging Editor
1321 Johnson
Avenue
P.O.
Box 112
San Luis Obispo, California
93406
San Luis Obispo County Board of
Supervisors
ATTN:
Chairman
Room 370
County Government
Center
San Luis Obispo, California
93408
California Public Utilities Commission
ATTN:
Hr. Truman Burns)Hr. Robert Kinosian
505 Van Ness,
Rm.
4102
San Francisco,
94102
Diablo Canyon
Independent
Safety Committee
Attn:
Robert
R. Wellington,
Esq.
Legal
Counsel
857 Cass Street,
Suite
D
Honterey, California
93940
Radiologic Health Branch
State
Department of Health Services
ATTN:
Hr. Steve
Hsu
P.O.
Box 942732
Sacramento,
94234
State of California
ATTN:
Hr. Peter
H. Kaufman
Deputy Attorney General
110 West
A Street,
Suite
700
San Diego, California
92101
Pacific Gas
and Electric Company
Pacific Gas
and Electric Company
ATTN:
Christopher J. Qarner,
Esq.
P.O.
Box 7442
San Francisco,
94120
Diablo Canyon Nuclear
Power Plant
ATTN:
Mar ren H. Fujimoto, Vice President
and Plant Manager
P.O.
Box 56
Avila Beach, California
93424
Pacific Gas
5 Electric Co.
ATTN:
Jim Melsch
Operations Training Supervisor
P. 0.
Box 56
Avila Beach,
CA
93424
Pacific Gas
and Electric Company
E-Hail report to D. Sullivan
(DJS)
bcc to
DHB (IE42),
bcc distrib. by RIV:
L. J. Callan
DRSS-FIPB
Branch Chief (DRP/E,
WCFO)
RIV File
Leah Tremper
(OC/LFDCB, HS:
Resident
Inspector
HIS System
Senior Project Inspector
(DRP/E,
WCFO)
Branch Chief (DRP/TSS)
TWFN 9EIO)
B. Henderson
(PAO,
WCFO)
DOCUMENT NAME:
R:(DC504LT.SLH
To reoolve copy of document, indicate In bcx: "C"
Co
without enctosures
"E" i Copy with en
sures
N
No copy
RIV:RE:OB
SLHcCror
C:QB
N
ADD:
JLPellet
ATHo e
D:D
ABBeac
D:DRSi
TPGw
02/
/95
02/ / 5
02
/95
OF ICIAL RECORD
COPY
02/& 95
02/
/95
02/
/95
Pacific Gas
and Electric Company
I
II
E-Mail report to D. Sullivan
(DJS)
bcc to
DMB (IE42)
bcc distrib. by RIV:
L. J. Callan
DRSS-FIPB
Branch Chief (DRP/E,
MCFO)
RIV File
Leah Tremper
(OC/LFDCB, MS:
Resident
Inspector
MIS System
Senior Project Inspector
(DRP/E,
MCFO)
Branch Chief (DRP/TSS)
TMFN 9E10)
B. Henderson
(PAO,
WCFO)
DOCUMENT NAME:
R:ItDC504LT.SLM
Tc recelw copy of document, Indtcste inbcx: "C" ~ Co
without endo ures
"E" a Copy with enc
sures
N" ~ No copy
RIV:RE:OB
C:OB
N
ADD:
SLMcCror
JLPellet
ATHo e
D:D
ABBeac
D:DRS>
TPGw
02/
/95
02/& /95
02/
/95
02/ /
5
OF ICIAL RECORD
COPY
02
/95
02/
/95