ML16342A639
| ML16342A639 | |
| Person / Time | |
|---|---|
| Site: | Diablo Canyon |
| Issue date: | 01/06/1999 |
| From: | Powers D NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV) |
| To: | Rueger G PACIFIC GAS & ELECTRIC CO. |
| Shared Package | |
| ML16342A640 | List: |
| References | |
| 50-275-98-17, 50-323-98-17, NUDOCS 9901130038 | |
| Download: ML16342A639 (12) | |
See also: IR 05000275/1998017
Text
CATEGORY 2
REGULATORY INFORMATXON DISTRXBUTION SYSTEM (RIDS)
CCESSION NBR:9901130038
DOC.DATE: 99/01/06
NOTARIZED: NO
DOCKET
FACIL:50-275 Diablo Canyon Nuclear Power Plant, Unit 1, Pacific
Ga
05000275
50-323 Diablo Canyon Nuclear Power Plant, Unit 2, Pacific
Ga
05000323
AUTH.NAME
AUTHOR AFFILIATION
POWERS,D.A.
Region
4 (Post
820201)
RECIP . NAME
RECXPIENT AFFILIATION
RUEGER,G.M.
Pacific Gas
6 Electric Co.
SUBJECT:
Forwards insp repts
50-275/98-17
E 50-323/98-17
on 981102-05
& 1207-11.No violations identified.
DISTRIBUTION CODE:
IE01F
COPIES
RECEIVED:LTR
ENCL
SIZE:
TITLE: General
(50 Dkt)-Insp Rept/Notice of Violation Response
NOTES:
RECXPXENT
ID CODE/NAME
PD4-2
INTERNAL: ACRS
AEOD/
CENTE
NUDOCS-ABSTRACT
OGC/HDS3
TERNAL: LITCO BRYCE,J H
NRC PDR
COPIES
,,LTTR ENCL
1
1
2
2
1
1
1
1
1
1
1
1
1
1
1
1
1
1
RECIPIENT
ID CODE/NAME
BLOOM,S
AEOD/SPD/RAB
DEDRO
NRR/DRCH/HOHB
NRR/DRPM/PERB
OE DIR
RGN4
FILE
01
NOAC
NUDOCS FULLTEXT
COPIES
LTTR ENCL
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
<o~mom
<<<~owe p~
i
NOTE TO ALL >RIDS" RECIPIENTS:
PLEASE HELP US TO REDUCE WASTE.
TO HAVE YOUR NAME OR ORGANIZATION REMOVED FROM DISTRIBUTION LIST
OR REDUCE THE NUMBER OF COPIES RECEIVED BY YOU OR YOUR ORGANIZATION, CONTACT THE DOCUMENT CONTRO
DESK
(DCD)
ON EXTENSION 415-.2083
TOTAL NUMBER OF COPIES
REQUIRED:
LTTR
19
ENCL
19
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION IV
611 RYAN PLAZAORIVE, SUITE 400
ARLINGTON,TEXAS 76011 8064
JAN -6 199
Gregory M. Rueger, Senior Vice President
and General Manager
Nuclear Power Generation Bus. Unit
Pacific Gas and Electric Company
Nuclear Power Generation, B32
77 Beale Street, 32nd Floor
P.O. Box 770000
San Francisco, California 94177
SUBJECT:
NRC INSPECTION REPORT 50-275/98-17; 50-323/98-17
Dear Mr. Rueger:
During November 2-5 and December 7-11, 1998, an NRC inspection was conducted at your
Diablo Canyon Nuclear Power Plant, Units 1 and 2, reactor facilities. The enclosed report
presents the scope and results of that inspection.
ln accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," a copy of this letter and its
enclosure willbe placed in the NRC Public Document Room (PDR).
Should you have any questions concerning this inspection, we willbe pleased to discuss them
with you.
Sincerely,
Dr. Dale A. Powers, Chief
Engineering and Maintenance Branch
Division of Reactor Safety
Docket Nos.:
50-275; 50-323
Enclosure:
NRC Inspection Report
50-275/98-17; 50-323/98-17
990ii30038 990i06
ADQCK 05000275
8
Pacific Gas and Electric Company
-2-
cc w/enclosure:
Dr. Richard Ferguson
Energy Chair
1100 lith Street, Suite 311
Sacramento, California 95814
Ms. Nancy Culver
San Luis Obispo Mothers for Peace
P.O. Box 164
Pismo Beach, California 93448
Chairman
San Luis Obispo County Board of
Supervisors
Room 370
County Government Center
San Luis Obispo, California 93408
Mr. Truman BurnshMr. Robert Kinosian
California Public Utilities Commission
505 Van Ness, Rm. 4102
San Francisco, California 94102
Robert R. Wellington, Esq.
Legal Counsel
Diablo Canyon Independent Safety Committee
857 Cass Street, Suite D
Monterey, California 93940
Mr. Steve Hsu
Radiologic Health Branch
State Department of Health Services
P.O. Box 942732
Sacramento,
California 94234
Christopher J. Warner, Esq.
Pacific Gas and Electric Company
P.O. Box 7442
San Francisco, California 94120
David H. Oatley, Vice President
Diablo Canyon Operations and Plant Manager
Diablo Canyon Nuclear Power Plant
P.O. Box 3
Avila Beach, California 93424
P
Pacific Gas and Electric Company
Managing Editor
Telegram-Tribune
1321 Johnson Avenue
P.O. Box 112
San Luis Obispo, California 93406
0
Pacific Gas and Electric Company
-4-
E-Mail report to T. Frye (TJF)
E-Mail report to D. Lange (DJL)
E-Mail report to NRR Event Tracking System (IPAS)
E-Mail report to Document Control Desk (DOCDESK)
E-Mail report to R. Correia (RPC)
bcc to DCD,(IE01) >,"'~
bcc distrib. by RIV:
Regional Administrator
Resident Inspector
DRS Director
DRS Deputy Director
DRP Director
DRS-PSB
MIS System
Senior Project Inspector (DRP/E)
RIV File
Branch Chief (DRP/TSS)
DOCUMENT NAME.'R:5 DC>DC817RP.LEE
To receive co
of document, indicate In box:
C" ~ Co
without enclosures
"E" ~ Co
with enclosures "N ~ Noco
RIV:SRI:EMB
LEEllershaw/Imb'2/28/98
Rl:EMB
CAClark
12/28/98
C:EMB
DAPowers
018'/99
AC:PB
LJSmit
01
/99
C:EMB
DAPowers
01/5/99
previously concurred
OFFICIALRECORD COPY
y3ogj j
Pacific Gas and Electric Company
-4-
E-Mail report to T. Frye (TJF)
E-Mail report to D. Lange (DJL)
E-Mail report to NRR Event Tracking System (IPAS)
E-Mail report to Document Control Desk (DOCDESK)
E-Mail report to R. Correia (RPC)
bcc to DCD (IE01)
bcc distrib. by RIV:
Regional Administrator
Resident Inspector
DRS Director
DRS Deputy, Director
DRP Director
DRS-PSB
MIS System
Senior Project Inspector (DRP/E)
RIV File
Branch Chief (DRP/TSS)
DOCUMENT NAME: R:+DC>DC817RP.LEE
To receive co
of document, Indicate lnbox: "C'~Co
vnthoutenclosures '6 ~
wfthencfosures
N ~No
RIV:SRI:EMB
Rl:EMB
CEMB
~
ACPB
C:EMB
LEEIlershaw/Imb*
CAClark*
DAPowers
LJSmit
DAPowers
018'/99
12/28/98
12/28/98
01
/99
previously concurred
OFFICIALRECORD COPY
01/S/99