ML16342A331

From kanterella
Jump to navigation Jump to search
Insp Repts 50-275/93-23 & 50-323/93-23 on 931018-22.No Violations Noted.Major Areas inspected:follow-up on Open Items Identified During Previous Emergency Preparedness Inspections
ML16342A331
Person / Time
Site: Diablo Canyon  
Issue date: 11/19/1993
From: Mcqueen A, Pate R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML16342A330 List:
References
50-275-93-23, 50-323-93-23, NUDOCS 9312130303
Download: ML16342A331 (24)


See also: IR 05000275/1993023

Text

Report Nos.

U. S.

NUCLEAR REGULATORY COMMISSION

REGION V

50-275/93-23

and 50-323/93-23

Licensee:

License

Nos.

DPR-80

DPR-82

Pacific Gas

and Electric Company

(PGEE)

77 Beale Street

San Francisco,

California 94106

Facility Name:

Diablo Canyon Nuclear

Power Plant

{DCPP), Units I and

2

Inspection. at:

Qiablo Canyon Site,

San Luis Obispo County, California

Inspection

Conducted:

October

18 - 23,

1993

Inspectors:

c ueen,

mergency

repare

ness

na yst

ate

cygne

~

~

Team Leader

P.

M. gualls,

Reactor Inspector

K. M. Prendergast,

Radiation Specialist

D. B. Pereira,

Licensing Examiner

A. S. Mohseni,

Emergency

Preparedness

Specialist,

NRR/PEPB

Approved by:

o ert

.

ate,

ie

,

a eguar s,

mergency

Preparedness,

and Non-Power Reactor

Branch

~Summar:

r&P

ate

gne

Areas

Ins ected:

Announced inspection to examine the following portions of

the licensee's

emergency

preparedness

program:

follow-up on Open Items

identified during previous

emergency

preparedness

inspections

and observe

the

1993 annual

emergency

preparedness

exercise

and associated

critiques;

and

Inspector Identified Items.

Dur ing this inspection,

Inspection

Procedures

82301

and

92701

were used.

Results:

The licensee

was found to be in compliance with

NRC requirements

within the areas

examined during this inspection.

One item was identified as

an exercise

weakness for review in future inspections

{Section 11).

Several

areas

were indicated to the licensee for potential

improvement (Sections

7

thru l2).

Two open

items from the

1992 emergency

preparedness

exercise

were

reviewed

and closed

{Section 2).

9312i30303 93iii9

PDR

ADOCK 05000275

9

PDR

INSPECTION DETAILS

Ke

Persons

Contacted

J.

S.

Bard, Director, Mechanical

Maintenance

R.

M. Bliss, Planner,

Technical

Support Center

  • M.

Burgess,

Director, Technical

Services

  • W. G. Crockett,

Manager,

Technical

and Support Services

S. J.

Foat,

Access Control Supervisor

  • S.

R. Fridley, Director, Operations

  • W. H. Fujimoto, Vice President,

Nuclear Technical

Services

.

J.

E. Gardner,

Senior Engineer,

Radiological,

Environmental

Chemical

Engineering

(RECE)

  • C. R. Groff, Director, Plant Engineering.
  • L. A. Hagen, Director, Safety,

Health

8 Emergency Services

J. A.-Hayes,

Supervising

Engineer

R. L. Honaker,

Outage Coordinator

'*K. A. Hubbard,'Regulatory

Compliance

  • M. T. Hug, Supervisor,

Emergency

Planning

'. T. Moretti, Radiation Protection Supervisor

R.

M. Morris,

EP Coordinator

.

  • J. B. Neale,

De'sign Engineer

  • R. P.

Powers,

Manager,

Nuclear equality Services

C.

B. Prince,

EP Coordinator

G.

M. Rueger,

Senior Vice President

P. A. Steiner,

Supervisor,

Emergency

Planning

D.

R. Steamer,

System Engineer

  • D. A. Taggart, Director, Site guality Assurance

(gA)

  • R. G. Todaro, Director, Security
  • J. D. Toresdahl,

EP Consultant

  • J. D. Townsend,

Vice President

and Plant Manager

E. -V. Waage,

Senior Engineer

S.

Wood,

EP Consultant

D.

Yows,

EP Consultant

and

The above individuals denoted with an asterisk

were present during the

October

22,

1993, exit meeting.

The inspectors

also contacted

other

members of the licensee's

emergency

preparedness,

administrative,

and

technical staff during the course of the 'inspection.

NRC Per'sonnel

at Exit Interview

A. D.

A. S.

K. M.

P.

M.

Mcgueen,

Emergency

Preparedness

Analyst,

RV,

Mohseni,

Emergency

Preparedness

Specialist,

NRR/PEPB

Prendergast,

Radiation Specialist,

RV

gualls,

Reactor Inspector,

RV

2

Action on Previous

Ins ection Findin

s

HC 92701

Follow-up Item (92-15-01).

Failure to Verif

Reactor

Shutdown in the

1992 Annual

Emer

enc

Exercise.

It was observed

by an

MRC inspector during the

1992 annual

emergency

exercise that Control

Room operators

did not properly verify that the

reactor

was shutdown after

a reactor trip.

Despite the clearly

indicated failure of the

Power

Range

(PR), Intermediate

Range (IR), and

Source

Range Nuclear Instruments

(SRNIs)

and of Digital Rod Position

Indicator (DRPI), step

1 of E-O, "Reactor Trip or Safety Injection," was

verified completed satisfactorily

by the crew.

Subsequent

questioning

revealed

the operators

responsible

for this verification believed the

NIs and

DRPI were operab']e during the performance of step

1.

Step

1

involves verifying power is decreasing

by using these

NIs and all rods

are bottomed

by using DRPI.

DRPI was flashing'indicating failure and

all NIs were pegged

low indicating failure.

Seventeen

minutes after the

trip, the .SRNI,was reported failed to the Senior control Operator

(SCO);

and nineteen

minutes after the trip, the

DRPI was reported failed to the

SCO.

In this instance the operators

did not properly verify the reactor

was shutdown.

The inspectors

concluded that the operators effectively

implemented the emergency

plan based

on the limited observation that the

simulator mode -of operation

provided.

However, the inspectors

also

concluded that the failure of the. crew to properly verify the reactor

was shutdown

was of major concern.

The licensee

followed up on this

item with an Action Request

(Number A0273101).

This item was reviewed

by the Control

Room inspector during this exercise

and the operating

crew positively determined that the reactor

was shutdown;

and observed

indications

by both the Source

Range Nuclear Instrumentation

and

by

panels

in the back.

This item is closed.

Follow-up Item (92-15-02).

Simulator or Ta

e Procedures

in 0 erator

Pla

in the

1992 Annual

Emer enc

Exercise.

A problem regarding the use of a taped scenario for control

room actions

was identified by the

NRC inspection

team during the

1992 annual

emergency exercise

as

an apparent

weakness

in scenario

implementation

and development.

NRC inspection

procedure

.82301

(Evaluation of

Exercises for Power Reactors)

indicates that inspectors will assess

the

performance of the control

room staff as it conducts

the task of

"analysis of plant conditions

and corrective actions."

This could not.

be appropriately

observed

during the most critical times of the exercise

(after the explosion leading to

a General

Emergency)

since reactor

control activity was taped

and fed to the staff rather than their

responding to the event in their normal manner.

This could result in an

inability for the licensee

and the

NRC to evaluate

the exercise

due to

lack of observation opportunity.

The licensee

followed up on this item

with Action Request

Number A0273101.

In order to assess

the performance

of the control

room staff as it conducted

the task of analysis of plant

conditions

and corrective actions; this item was reviewed during the

1993 annual

emergency exercise.

The operating

crew performed

satisfactorily during the critical tim'es of this exercise.

The scenario

0

-

3

events

and transients

were live during the degrading plant

conditions,'nd

were appropriate to effectively ensure that the crew could implement

the site emergency

plan

and respond to plant conditions.

Their

mitigation of the event in progress

appeared

appropriate.

This item is

closed.

Exercise Plannin

res onsibilit

scenario ob'ectives

develo

ment

control of scenario

The licensee's

Emergency

Preparedness

(EP) staff has the overall

responsibility for developing,

conducting

and evaluating the annual

emergency

preparedness

exercise.

The

EP staff developed

the scenario

with the assistance

of licensee staff from other organizations

possessing

appropriate .expertise

(e.g. reactor operations,

heal.th.

physics, security,

maintenance,

etc.). 'n an effort to maintain strict

security over the scenario,

individuals who had

been

involved in the

exercise 'scenario

development

were not participants

in the exercise.

The objectives

were developed

in concert with the offsite agencies.

NRC

Region

V -and Federal

Emergency

Management

Agency

(FEMA) Region

IX were

provided

an opportunity .to comment

on the proposed

scenario

and

objectives.

The complete exercise

document

included objectives

and

guidelines,

exercise

scenario

and necessary

messages

and data (plant

parameters

and radiological information);

The exercise

document

was

tightly controlled before the exercise.

Advance copies of the exercise

document were provided to the

NRC evaluators

and,other

persons

having

a

specific need.

The players did not have

access

to the exercise

document

or information on scenario

events.

This exercise

was conducted

to meet

the requirements

of IV.F 2 of Appendix.

E to

10 CFR Part 50.

Exercise Scenario

The exercise

objectives

and scenario

were evaluated

by the

NRC and were

considered

appropriate

as

a method to demonstrate

Pacific Gas

and

Electric Company's

(PGLE) capabilities to respond to an emergency in

accordance

with their Emergency

Plan

and implementing procedures.

The

exercise

scenario started with an event classified

as

an Unusual

Event

(UE)

and ultimately escalated

to a. General

Emergency

(GE)

classification.

The opening event in the exercise

involved

a

lubricating oil fire in a diesel

generator

room.

The room and hallway

filled with thick smoke that significantly impaired visibility and

respiration.

The California Department of Forestry

(CDF) was called to

help fight the fire, necessitating

the declaration of a UE.

Fire

fighters were unable to bring the fire under control within ten minutes,

meeting the criteria for declaration of an ALERT.

After 9:45 a.m.,

the

site experienced

a loss of all onsite

and offsite power.

A loss of

onsite

and offsite power lasting greater

than

15 minutes met the

criteria for declaration of a Site-Area

Emergency

(SAE).

After about

10:20 a.m.,

due to indications of a degraded

core with possible loss of

eoolable

geometry

as indicated

by core exit thermocouples

reading in

excess of 1200 degrees

Fahrenheit;

the criteria was met for declaration

of a

GE.

A subsequent

series of events

led to releases

of radioactive

gases offsite.

The plume initially traveled in

a southeasterly

4

direction.

Later in the scenario,

a wind shift carried the plume

through-southern

San Luis Obispo County and northern

Santa

Barbara

County depositing significant amounts of iodines

an'd particulates

over

portions of these counties.

The onsite

phase of the exercise

was

conducted

on October 20, followed by an ingestion

pathway drill on

October

21

and

22.

Federal

Observers

Five

NRC inspectors

evaluated

the licensee's

response

to the

scenario.'nspectors

were stationed

in the (simulator)

CR,

TSC, Operational

Support Center

(OSC),

~ and in the

EOF.

An inspector

in the

OSC also

accompanied

repair/monitoring -teams.

Offsite portions of this annual

exercise

were evaluated

by

FIRMA, Region IX, which will result in a

separate

inspection report by that agency.

Exercise Observations

82301

~

The following observations,

as appropriat'e,

are intended to be

suggestions

for improving the emergency

preparedness

program.

An

exercise

weakness

is

a finding identified as needing corrective action

in accordance

with 10 CFR 50, Appendix E, Paragraph

IV.F.5.

All

exercise

times

and other times .indicated in this report are Pacific

Daylight Time (PDT).

Control

Room Simulator

CR

The following aspects

of CR operations

were observed

during the

exercise:

detection

and classification of emergency

events,

notification, frequent

use of emergency

procedures,

and innovative,

attempts to mitigate the accident.

At 9:47 a.m. in the scenario,

Unit

1 lost all

AC bus

power due .to

scenario

events.

As directed

by the Control

Room Supervisor

(CRS), the

two shift foremen determined

a method to backfeed via the Unit

1 Startup

transformer across to the Unit 2 vital and non-vital buses.

This

determination

was completed at about

10:30 a.m.,

whereby the

CRS

requested

the Technical

Support Center

(TSC) to verify if the method

was

correct

and that breaker voltage

and current loadings would not be

exceeded.

At 10:50 a.m., directions

by the

TSC were given to the

CRS to use

EOP

ECA-0.3, Appendix H, instead;

which crossties vital buses

between units

using

an operable

Diesel Generator

at Unit 2.

Since the

TSC directed

the implementation of Appendix H, the crew proceeded

to perform Appendix

H.

Due to Scenario constraints,

at about ll:20 a.m.,

the

500

KV offsite

power was established

via backfeed

from the Unit 2 to Unit

1 by the

scenario controllers'irection to the simulator operators..

5

The issue or concern

by the

NRC inspector

was the extent of time (over

one hour) to determine the corrective actions to backfeed to Unit

1

AC

buses.

The

AC Power was restored

at 11:20 a.m. via the simul.ator

operators

in order for the scenario

to progress

along directed

events.

.Credit should

be given to the two shift foremen for their determination

of a method of energizing Unit 1's vital buses via Unit 2's non-vital

buses.

Even though,

due to scenario faults, that method would not'ave

been

able to be completed,

the quick thinking and simplicity of their

method

was considered excellent.

Evaluation of their method

was

eventually conducted

and approval

was granted,

but this appeared

at the

same time as the Appendix

H solution,

which was determined

by the

TSC to

be the method to restore the

AC buses

to Unit 1.

The

NRC observer

considered that

a long tiine was used to determine

a method for restoring

AC Power,

when there should

have 3ieen

a readily available

method to

restore

AC power. to either unit by cross connecting

the

AC buses.

At a debriefing conducted

on Oct 21, 1993,-the licensee controllers

discussed

the length of, time to 'restore

AC bus power.

They considered

that the length of -time was appropriate for the scenario

and the

difficulties associated

with the Hotor Operator Disconnect

(NOD)- being

welded shut;

Using the word "weld'ed" in the scenario

discouraged

further attempts

at freeing the NODs, which was the true success

path

for restoring the units'C @uses.

Technical

Su

ort Center

TSC

The following aspects

of TSC operations

were observed:

activation,

accident assessment/classification,

notification,

and interactions

'between

the various emergency

response facilities.

The following

represent

the

NRC inspector's

observations

in the

TSC.

a.

The

HP Supervisor provided good anticipatory advice

as to the

effects of possible

changes

in the event; for example:

(1)

At 10:14 a.m.,

he recommended

to the Site Emergency

Coordinator

(SEC) that additional Protective Action

..Recommendations

(PARs)

be

made to the county based

on the

large inventory of material in containment

and the

possibility of containment

leakage.

(2)

At 1:30 p.m.,

he provided to the

SEC

a projected

plume

map

and

an explanation of a possible

change

in wind direction

and the effects of the change.

b.

The following TSC engineering

support staff issues

appeared

to

contribute to the licensee

not identifying the point of release

or

to properly characterize

the extent of core

damage.

(1)

The core damage

assessment

performed

by the staff showed

core melt vice the actual

60X.

It appeared

to the inspector

that after the initial assessment

at the time water

was

restored,

no

new assessments

were made.

6

(2)

The

TSC staff was not effective in locating the source of

leakage

from the containment.

Instead

they concentrated

their efforts

on purge line penetration

leakage.-

(3)

The

TSC staff appeared

to not be aware that the

HP staff.had

information provided by inplant radiation monitors which

would have helped

them to localize the source of the leak.

{4)

The technical staff incorrectly told the

NRC Senior Resident

Inspector that Flow Element

700 had only local indication.

Later the Site

Emergency Coordinator

(SEC) directed the

staff to look on,the

Emergency

Assessment

and Response

System

(EARS) where there.was

remote indication.

. (5)

The technical -staff appeared

to focus

on proving that their

first solution to a problem was correct

and did not appear

to adequately

widen the search for other possible solutions.

0 erational

Su

ort Center

OSC

Two

NRC inspectors

observed activitie's conducted

by the

OSC;

one located

part time at the

OSC location

on the turbine deck

and

one who

accompanied field teams

dispatched

from the

OSC and part time observed

activities in the

OSC.

The following represent

the

NRC inspector

observations

in the

OSC.

a 0

b.

The

OSC was activated

promptly within twelve minutes of the Alert

declaration

in accordance

with Emergency

Plan Implementing

Procedure

(EPIP)

EP EF-2, "Activation and Operation of the

Operational

Support Center."

Briefings were performed for all teams prior to dispatch to ensure

personnel

were infor'med and capable of performing their mission in

a safe manner.

c.

-

Surveys to determine

the habitability of the

OSC were performed

throughout'the

exe} cise

and records

were maintained.

d.

The

OSC staff and persons

who performed the briefings of teams

prior to dispatch

were not kept fully informed of release

conditions.

Consequently,

at I:25 p.m.,

a team was dispatched

outside the plant in

a path directly under the release.

The team

was not provided instructions to wear Protective Clothing

(PC) or

a suitable respirator for this mission.

The respirator

was not

worn because

of the limitations of the standard

30-minute tank.

The team concluded that the walk around the plant would have

used

up most of the supply of oxygen

and left them unable to complete

their mission.

There appears

room for improvement in the method

of disseminating

release

information to the

OSC.

Also,

alternative solutions to cope with the restrictions of the 30-

minute air tanks should

be considered.

)l

7

e.

9,

h.

The

OSC was not observed

recording

and tracking the doses received

by persons

returning to the

OSC from missions

in the plant.

The

ability to quickly determine

doses

accumulatdd

during plant

response

missions

would be beneficial in long term recovery

operations

or high dose rate entry or activity. It was indicated

by the licensee that most persons

would be processed

through

access

control

and

use the automated

access

(ACAD) system.

However, in an emergency

there

may be occasions

where individuals

are,not

processed

by access

control or there

may be problems with

the

ACAD system.

There was

a shortage

of iodine cartridges for team use at the 85

foot level access

control point.

The problem resulted in a number

of delays

in teams

accomplishing their mission.

The

OSC staff did not issue

personal

dosimeters

to the personnel

staged

in the elevation trailer awaiting

OSC needs.

The operations

of. the

OSC were hampered

by the'ack of appropriate

plant drawings in the

OSC.

Briefings were held

up on several

occasions

whil'e trying to locate

a drawing for a certain

area to

be visited (e.g., ventilation ducting for survey, etc.)

and to

determine

the best path to follow and the location of certain

equipment.

The results of onsite monitoring may have

been

delayed

due to the

instructions for "turn back" at

25 millirem for high'iodine

release.

This standard

appeared

to inhibit actions

by plant

personnel

in the course of missions to identify, quantify, or

mitigate

a release

If the results of monitoring would be

beneficial in the veri'fication of dose-projection .or damage

assessment,

then the dose to provide release

data should

be

considered

when discussing

the conditions at which the team would

be turned

back due to dose limitations.

J

~

As. discussed

Py

monitoring team

performing soil

soil or vegetati

verification of

the onsite

team

appropriate.

the licensee

in their player meeting,

the onsite

does

not have procedures

or equipment for

or vegetation

sampling.

Again, if the results of

on sampling are necessary

to aid in comparison

or

dose

assessment

or damage

assessment;

providing

procedures

and equipment for such sampling

appears

10.

Emer enc

0 erations Facilit

EOF

The following EOF operations

were observed:

activation; functional

capabilities;

interface with offsite officials; dose

assessment;

discussion of recovery

and reentry;

and the formulation of protective

action recommendations

(PARs).

The following are

NRC observations

of

EOF activities.

0

8

An Alert was declared

at 8:35 a.m.,

and the

EOF was declared

operational

wi-th .the interim minimum staff at 9:27 a.m. in

accordance

with EPIP

EP EF-3A.

The

EOF interim staff performed

its functions in accordance

with its procedures

and at 9:51 a.m.,

. the Interim Advisor to the County

(AC) signed the first PAR for

the

SEC.

At 10:25 a.m.,

the Recovery

Hanager

(RH) and his team arrived.

The turnover activities were performed efficiently and in

accordance

with procedures.

At ll:00 a.m.,

when the

EOF staff

were. adequately

briefed

and ready to assume

command

and control,

the

RH declared

the facility activated.

and in charge of the.

functions established

in his procedures.

~

In facility management

and control, the status

boards

were kept

up

to date.

The

RH and the Assistant

RH performed their functions

efficiently despite several

changes

in command during the

exercise.

Periodic briefings were held.

The emergency classifications

were

made at the Control

Room

(Simulator)

and the

TSC, prior to Long-term

EOF activation.

Reactor conditions were continuously assessed

by the

EOF

engineering

personnel.

The engineering staff at the

EOF and the

TSC did not accurately

assess

core

damage

and the release

pathway.

Containment

high range radiation readings

and results

from a Post

Accident Sampling

System

(PASS)

sample,

core uncovery, time,

and

other indicators in the plant were not used to adequately

assess

core damage.

The engineering staff did not accurately

determine

the release

pathway using the area radiation monitors

and

therefore

reduced the chances

of successful

mitigation.

The

engineering staff considered

the release

to have potentially

occurred through

two pathways

and attempted to terminate the

release

through those.

Considerations

were not given to radiation

monitors which would have assisted

them in identifying the real

pathway.

Offsite dose .assessment

and quantification of the release

rate

were timely and accurate.

It appeared,

however, that air sample

results

from the field to confirm iodine levels were slow and few.

This was important because

it"was the iodine levels that were

driving the

PARs beyond the

10 mile EPZ.

The development of Protective Action Oecisions

were timely and

appropriate.

Notifications and communications

were generally performed

effectively and periodically.

It was noted,

however, that the

status of the release

of radioactive material into the environment

communicated

to offsite officials was not entirely accurate.

This

inaccurate

information appeared

in the I:15 p.m..press

release.

9

h.

Despite .the instructions

given to the players in the area of

drillmanship prior to and during the exercise

by the Plant

Hanager,

the

RH,

and his assistant

RH, it was noted that

some

players

were too quick to blame the scenario for events that were

not readily explainable.

ll.

Exercise

Meakness

One area of activity was identified by the

NRC inspectors

as

an exercise

weakness.

Based

on observations

by the inspectors

in the

TSC and

EOF;

there

was

a concern that technical

support provided by the engineering

staff at the -TSC, and the

EOF did not appear to provide emergency

management

with appropriate

assessments

regarding the areas of core

damage

and probable release

path.

Accurate information in this area is

.

needed to mitigate the event

and to estimate the magnitude of offsite

releases

and environmental

consequences.

Specifics

on which this

weakness

categorization is based

are indicated .in sections

S.b

and lO.d

above.'he-applicable

sections of the approved

Emergency

Plan are

listed below:

Section 6.2,

ASSESSHENT ACTIONS, indicates in part:

....This section contains

a more- detailed discussion of the

four most important assessment

functions;

namely,

the proper

functioning of emergency cooling systems for emergencies

involving possible degradation of the core heat sink, the

assessment

of core condition in such

a circumstance,

the

estimation of the magnitude of a release,

and the

determination of the environmental

consequences

of a

release.

Section 6.2.3,

Assessin

Core

Oama e, states

in part:

Preliminary core

damage

assessment

uses

parameters

such

as

reactor vessel

water level

and core temperatures

to confirm

that conditions exist which can lead to clad and/or core

failure.

This is quantified through the use of containment

hydrogen

and area radiation monitor readings.

Long-term core

damage

assessment.

methodology

uses reactor

coolant

and containment air sample analysis to determine

the

extent of clad and/or core failure more accurately.

Section 5.2.2.2.b.l),

En ineerin

and Technical

Anal sis

under

(Engineering Advisor) states

in part:

Perform systems

analysis,

resolve core/thermal

hydraulics...and

diagnose

plant conditions.

Ft

10

Table 5.2-1),

Section A.Z.e), Onsite

Emer enc

0 eratin

Or anization

Res onsibilities

Authorit

and Duties, states,

in part,

regarding

TSC

Operations:

This includes collecting

and analyzing technical

information

to assess

plant operations,

providing technical

counsel

in

support of the Control

Room (CR), assessing

radiological

release

potential,

determining actual

or potential release

rates,

on-site exposure monitoring and contamination

contro1,

repairing plant components

or systems

as required

by the emergency

and or consequences.....

A preliminary core

damage

assessment

at about 10:45 a.m. estimated

core

damage

as between

about

2X and

20X, with 100X gap release.

At about

12:44 p.m., the figure was refined to.about .7X and reported to the

EOF

where it was

so posted for virtually the remainder of the plume phase

portion of the exercise;

The

7X figure was questioned%y

several

individuals during the exercise

as being unrealistically low.

Statements

by individuals in the

TSC and

EOF indicated their belief that

core

damage

was

much higher.

This core

damage

assessment

was not

updated until after 4:00 p.m.

when

PASS sample results

were received

by

the Corporate

Incident Response

Center verifying much higher core

damage.

Since the request

For

a

PASS sample

was initiated b> controller

prompting at about 12:30 p.m., the results of the

PASS analysis

would

not have

been available until later had the controller not intervened.

Concentration of the

TSC and

EOF engineering staffs

on the "purge line

release

path concept"

precluded their searching

for and identifying the

true release

path for virtually the entire plume phase of the exercise.

This. occurred despite the availability of area radiation alarms in the

vicinity of the containment leak area to the HP-oriented staff. at the

TSC.

Amount of core

damage

and release

pathways

are significant because

they

have

a direct impact

on offsite consequences.

Accurate

assessment

of

radioactive inventory -available for release,

which is

a function of core

damage,

and .identificati,on of potential

release

pathways,

including

filtration and other in-containment

removal

processes,

are critical for

assessment

of ongoing

and potential offsite consequences.

This area will be reviewed in future inspections of licensee

emergency

drills and exercises.

(Exercise

Meakness

Item 93-23-01)

Licensee Criti ues

A series of exercise critiques

were conducted

by the licensee

upon

completion of the exercise.

First,

a facility critique was conducted

at

each

emergency

response facility with players

and controllers

immediately following the exercise.

The following day,

a critique was

conducted with players

and controllers

from all emergency facilities.

A

formal corporate cr'itique. was conducted

at the site to cover significant .

problems,

strengths,

and observations.

NRC inspectors

observed

the

I

11

facility critiques immediately following the exercise

and the formal

corporate critique.

These critiques were evaluated

by the

NRC

inspectors.

~

Facility critiques immediately following the exercise termination

appeared

satisfactory

and appropriate

to exercise activities.

Some of the shortcomings

noticed

by the

NRC inspectors

were also

noted

by the licensee

and were discussed

in critiques.

~

The corporate exercise critique on October

21 also appeared

satisfactory

and appropriate

to exercise activities.

Exit Interview

An exit interview was held

on October

22,

1993, to discuss

the

preliminary

NRC findings.

The licensee

was- informed of the exercise

weakness

identified during the inspection'and

discussed

in -Section

11

above.

Items discussed

are

summarized

in Sections

2 and

7 through

12 of

this report.

r

0