ML16341G003

From kanterella
Jump to navigation Jump to search
Insp Repts 50-275/91-04 & 50-323/91-04 on 910211-14. Violation Noted & Being Considered for Escalated Enforcement Action.Major Areas Inspected:Mechanical Maint Measuring & Test Equipment Issues at Facility
ML16341G003
Person / Time
Site: Diablo Canyon  
Issue date: 03/04/1991
From: Kirsch D, Miller L
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML16341G002 List:
References
50-275-91-04, 50-275-91-4, 50-323-91-04, 50-323-91-4, NUDOCS 9103200125
Download: ML16341G003 (22)


See also: IR 05000275/1991004

Text

U.S.

NUCLEAR REGULATORY COMHISSIOtt

REGION

V .

Report Nos.

Docket Nos.

License

Nos.

Licensee:

50-275/91-04

and 50-323/91-04

50-275

and 50-323

'I

DPR-80 and DPR-82

Pacific

Gas

and Electric Company

77 Beale Street

San Francisco, California 94106

Facility Name:

Diablo Canyon Units

1 and

2

Inspection Conducted:

February 11-14,

1991

Inspector:

er,

le ,

peratsons

ect>on

a e

cygne

Approved by:

~Summar:

D.

. Kirsch,

C

e

Reactor Safety Br

ch

ate Signe

Inspection

on February 11-14,

1991 (Report Nos. 50-275/91-04

and 50-523/91-04)

Areas Ins ected:

This was

an announced,

special

inspection to follow-up on the inspection

documented in Inspection Report Nos. 50-275/90-29

and 50-323/90-29

concerning

mechanical

maintenance

measuring

and test equipment

(MH M&TE) issues

at

Diablo Canyon.

Inspection

procedures

30703 and 92700 were used.

Results:

The inspection

made the following general

conclusions:

1.

The licensee's

management

at the site

and corporate offices had not

ensured that the guality Assurance

(gA) and guality Control

(gC)

Departments'ignificant

audit findings relating to the

M&TE program were

substantively followed up and corrected

by the Ma'intenance

Department.

2.

The

gC Department,

and to a lesser degree,

the

gA Department,

were not

.aggressive

in seeking corrective

action for the findings of their audits

of HM M&TE.

q 1 Q3'1QQ l ~>5 9 fQ3Q5

pop

pz)DC/

Q~7QQQ275

f'PR

.

2

3.

The methods

and equipment

used

by the Mechanical

Maintenance

Department

to control

M&TE were still inadequate,

despite

the previous licensee

audits

and

NRC inspection,

(50-275/90-29),

based

on a limited sample of

activities.

These findings appear to represent

a significant safety matter because

they

indicate

a chronic programmatic

weakness

in the control of MM MINUTE, which may

have, or at least

had the potential to adversely

impact installed safety

related equipment.

Further, although .these deficiencies in the control of

NN

NIENTE were identified by the gA and

gC organizations,

these oversight groups,

Mechanical

Maintenance

and

PGIIE management

were ineffective in achieving the

necessary

corrective action.

I'ne

apparent violation (50-275/91-04-02)

was identified:

failure to identify

a breakdown in the program for control of measuring

and test equipment

as

a

nonconformance,

and failure to promptly correct this breakdown.

Unresolved item 50-275/90-29-01

was resolved

by this inspection into violation

50-275/91-04-02,

and is therefore closed.

Three

open items were identified.

i

DETAILS

Persons

Contacted

  • J. Townsend,

Vice President,

NPG, Plant Manager

<<M. Barkhuff, guality Control Manager

'T. Bennett, Mechanical

Maintenance

Department

Manager

C. Seward,

Senior

Power Production Engineer

H. O'onnell, Regulatory Compliance Engineer

D. Taggart, Director, Site guality Assurance

J. Strahl, Mechanical

Maintenance

Foreman

<<B. Giffin, Asst. Plant Manager, Maintenance

Services

A. Young, Sr.

gA Supervisor

<<T. Grebel, Regulatory Compliance Supervisor

<<Attended exit.meeting.

The inspectors

also held discussions

with other licensee

and contractor

personnel

during the inspection.

Back round

This inspection

was

a followup inspection to Inspection

Nos. 50-275/90-29

and 50-323/90-29.

The purposes of the latest inspection were threefold:

to review further the existing program for control of measuring

and test

equipment

(HSTE), to review the corrective=actions

which had been taken

for deficiencies identified in earlier versions of that program by the

licensee's

audits

and the previous

NRC inspection,

and to determine whether

enforcement action was appropriate for the unresolved

item identified by

that inspection.

This unresolved

item concerned

what appeared

to be

ineffective corrective action for the

HSTE program weaknesses

previously

identified by the licensee's

audits

and surveillances.

Review of Existin

Pro

ram for Control of MSTE

The inspector

conducted surveillances of work by personnel

in the

Mechanical

Maintenance

(HH) and Instrumentation

and Controls

(ISC)

calibration and tool issuing facilities.

Selected

tool issue logs,

calibration records,

MSTE modules from -the Plant Information Management

System

(PIMS), and personnel

qualification records

were reviewed.

In

addition, tool issuance,

return,

and calibration were observed.

a.

The inspector

observed that calibrated tools were issued

and

calibrated

by the

ISC departnent in a careful

and methodical

~

manner.

Licensee representatives

stated at the beginning of the

inspection that all work performed in the radiologically

controlled area

(RCA) during the refueling outage in progress

would be done using only MSTE issued

by the

ISC department.. This

policy was announced in a memorandum

dated

November 21, 1990,

and

became effective January

14, 1991, shortly after the end of the

previous

NRC inspection.

The inspector determined that because

of this change in policy,

approximately

75K of the calibrated

torque wrenches

were under the

control of the .ISC department,

a higher percentage

than was found

"'

during the previous =inspection.

C

The only potential discrepancy

observed

in the .ISC department control

=-.

program was that calibration personnel

stated that they did not have

an effective method to ensure that issued 'tools were promptly returned

when the job to which the tools had been assigned

had

been completed.

A

b.

The inspector

observed that calibrated tools were issued

and

calibrated

by the

MM department in -a manner which was generally

consistent with the less detailed procedural

guidance

required

by

the licensee for this department.

However, the following

significant discrepancies

were identified:

(1)

On February 12, 1991, the inspector

observed that Tension

Dynamometer

8157

had

been

issued for Mork Order C0078894-01

on January

23,

1991,

a work order which was completed

on

January

29, 1991.

This was not

a safety related job, but was

associated

with safely moving a cask

used for transportation

of radioactive material.

At the inspector's

request,

the

tool was located.

The personnel

using it stated that it had

been in use to check chainfalls for some days,

a different

job than the one for which it,had been

issued.

The licensee

personnel

were not aware of this earlier job.

The inspector

noted that this was

a current

example of a finding

identified in gC Surveillance

Report

PCS 90-0030,

dated April 12,

1990,

and

a similar one re-identified in guality Assurance Audit

90812T, dated

September

6, 1990.

The surveillance report

had

stated= that

28% of the

MSTE usage

sampled

was not recorded

as

required

by guality Assurance

Procedure

(gAP) 12.A, Control

and

Calibration of Measuring

and Test Equipment,

Sections

4.25 and

4.26, Revision 19.

The

gA audit stated that 35K of work orders

reviewed did not contain adequate

MSTE'escriptions,

as required

by AP C-40S3,

Revision 12, Attachment 6.3, Instructions for

Completing

and handling W/0's with PIMS on Line.

Finally,

MM M&TE personnel

stated that personnel

frequently did

not return

MSTE once the job for'hich it had been issued

was

completed,

and that testing personnel

did not have

an effective

.

method to ensure that the equipmei t was returned.

Based

on this

limited sample of one job which was checked,

and the comments

from both

MM M&TE and

I&C M&TE personnel,

the inspector concluded that

the licensee's

controls to ensure that

MSTE was traceable

to the

jobs where it w'as

used

were still ineffective.

This is an open

i tem (50-275/91-04) .

On February

12 and 14,

1991', the inspector requested

that eight

torque wrenches available for issue in the

HH calibrated tool

issue

room be checked at one point of their useable

range for

calibration.

Licensee

personnel

performed

a check on each of.

these

wrenches.

Two of the eight (25%),8 393 and 8381, were

found out of calibration.

Torque'wrench

8393 indicated

240

in-lbs at an actual

value of 218 in-lbs', while torque wrench

1381 indicated

125 in-lbs at an actual

value of 145 in-lbs.

Both wrenches

were indicated by their calibration records to

be in calibration.

The tolerance for torque wrenches

to be

considered. in calibration was four percent of their setpoint

per Step 7.2.7 of Procedure

HP M-53.1.

Licensee

personnel

could not explain this finding.

They

indicated that typically one out of 100 times they would

find a similar discrepancy.

The discrepant

torque wrenches

were

removed from service fot calibration.

The inspector noted that Maintenance

Procedure

H-53.1,

Revision 5, Section 7.4 required. that torque wrenches

be

verified before

and after their use at the setting, or over

the range, at which they were to be used.

The inspector noted

that it was possible that

a torque wrench could be in calibration

at

some points

and out of calibration at others.

In this case,.

a simple one point calibration check such

as that performed at

the inspector's

request

would not necessarily

indicate

a

previous verification error had been

made.

However, this.

relatively high percentage

of discrepancies

suggested

a significant percentage

of verification errors.

The inspector concluded that the verification program for HM

torque wrenches

was potentially failing to ensure that only

calibrated tools were in use.

This is an open item

(50-275/91-04-03).

The inspector

observed

the

MM MSTE personnel

perform

several verification checks of audible indicating (snap-

type) type torque wrenches,

also

known as "click type"

torque wrenches.

These verifications were performed

on

different models of the Milliams Torque Mrench Tester.

Steps

7.2.2

and 7.3. 1 of procedure

h)P M-53.1, referenced

in the

previous paragrapli,

required

ihe calibration of torque

wrenches

in accordance

with the applicable Technical Bulletin.

These

personnel

were not aware of the prominent Note in

Technical Bul'letin No. TB-129, the applicable j'echnical

Bulletin for this activity, which described

the proper

use of this equipment:

"Extreme care must be exercised

when checking audible

indicating (snap-type)

wrenches

so the operator

does

- not pull beyond the "break

away torque."

The inspector

observed

that

MM MSTE personnel

were

una

of this precaution,

and routinely did not use extreme care,

unaware

,'onsequently,

for smaller torque wrenches,

measuring

in

in-lbs, these

personnel

routinely pulled the wrench

significantly beyond the break

away torque.

For example,

for a wrench set to.break

away at 100 in-lbs, the Milliams

Tester typically indicated

a peak torque value of 130-140

in-lbs had been attained during the test.

For larger torque

wrenches,

the

same effect was not noted.

For example, for

a wrench set to break

away at 100 ft-lbs, a peak torque value

of 102 ft-lbs was typically attained.

The person performing

the test attempted

to estimate

the value of the release tor u

t the process

was inherently imprecise given the relative

e

orque,

rapidity with which the wrench passed

through the break

away

torque

.val ue.

The inspector noted that field personnel

could reasonably

be

expected

to be even less meticulous

than the testing

personnel

who routinely exceeded

the setpoint torque values

unintentionally.

The inspector concluded that this testing

had demonstrated

that use of snap-type

torque wrenches

in

the in-lb ranges

could result in significant overtorquing of

fasteners

in those

ranges.

A related,

but broader

conclusion

was independently

reached

by the licensee's

Technical

and Ecological Services

(TES) Division Report

420DC9176,

(January

14,

1991) issued in response

to Action

Request

A0183483

(March 17, 1990).

That report made

one

observation

which was relevant to this discussion:

"Click" type wrenches

may have

a second

Ltorque3 peak

that can significantly over torque

a bolt."

The inspector

determined that the IhC NTE program

had

'ecently

greatly reduced

the number of snap-type

torque

wrenches available for use,

whereas

the

NN MATE program

had

not addressed

the concern.

To the contrary,

on February

14,

1991, the inspector

was advised

by licensee testing personnel

that workman were requesting

snap-type

torque wrenches for

use inside the

RCA from the

MM NTE calibrated tool issue

room, despite

the licensee's

decision discussed

in Section 3.A

above to use only I&C calibrate'd tools in the

RCA beginnin

January

14,

1991.

eginning

'I

The inspector

concluded that, for small torque wrenches,

the

licensee's

program to control torquing of fasteners

had not

been nearly as precise

as required

by HP M-53.1.

The

inspector

noted that the effect of the unknown errors

produced

should

be considered

by the licensee for systematic

evaluation.

(Open Item 50-275/91-04-01)

~

~

4.

Review of Previous Oualit

Assurance

Audits and gualit

Control

urve)

ances,e

ate

to

1

ro ram

ea

nesses

nreso

ve

Item

-

1

The inspector

reviewe'd the status of corrective action for the

surveillances,

audits

and the inspection which preceded this inspection

and which were related to Of MSTE.

Inspection

Report

Nos. 50-275/90-29

and 50-323/90-29 previously detailed

much of this chronology.

It is

summarized

here,

combined with additional information determined during

this inspection.

Four licensee

reports

from December 5, 1989 through September

6, 1990

identified repeatedly that the

NH METE program had significant weaknesses.

These reports

w'ere.:

a.

ualit

Control Surveillance

89-175 dated

December 5,

1989

This report concluded that "a significant problem exists with

fMN] MSTE traceability to specific work activities."

An

expanded surveillance

was recommended,

but no definitive

corrective action which addressed

correcting this problem

was indicated

by the surveillance.

b.

gualit

Control Surveillance

90-030 dated

A ril 12,

1990

This surveillance identified a variety of programmatic

problems.

These included:

"chronic omission of data,

data errors,

missing signatures,

.

.

. logs not maintained;

incomplete

and

no history searches/evaluation

for out-of-

tolerance

MSTE, history searches

ARs exceeding

procedural

time limits;

equipment

usage

not being consistently recorded,

jeopardizing

the accuracy of the calibration data baseline;

"as found" data not recorded

and in some instances

photocopied

and uses (sic) for multiple tools."

inadequate

training and qualification of caIibrators;

extrapolation of calibration data which is not permitted;

use of standards

with less

than the Lprocedurally] required

accuracy;"

0

6

This expanded

surveillance of MM M8TE concluded that:

"Unsatisfactory performance of tool calibration and issue

activities

was primarily due to unclear or incomplete

procedures

and poor practices

by maintenance

personnel.

Many of the program administrator's

corrective actions

during the last year only corrected

the symptoms of the

problems

and not their causes

thus allowing problems to recur..

. . The overall effectiveness

of the Mechanical

Maintenance

calibration program is unsatisfactory."

A follow-up surveillance

was

recommended

by gC to determine whether

the corrective actions identified and scheduled

by the

HM department

were effective.

In discussions

with the inspector,

the

gC Manager stated that

he

had recomnended

to the Mechanical

Maintenance

Department

Manager

that

a nonconformance

report

(NCR) be issued,

but that manager

considered

that an

NCR was inappropriate

because

the surveillance

findings were not significant enough,

and because

that manager

thought that

some of the surveillance findings were invalid.

At the time of the previous inspection,

which began

on November 27,

1990,

some of the Action Requests

initiated by RC for specific findings

of this surveillance

had still not been addressed

by the Mechanical

Maintenance

department

(e.g.

AR A0184108, dealing with rusted standards,

and

AR A0183542, dealing with widespread

r ecordkeeping errors).

1/here

the findings had been addressed,

they were addressed

in piecemeal

fashion

by lower level per'sonnel,

using

comment fields on Action Requests,

rather

than in a coordinated

way which clearly demonstrated

management

oversight

and approval of the response.

Most significantly, licensee

personnel

could not provide any documentation

which addressed

the five

overall conclusions

and seven

recommendations

of this surveillance.

During this inspection, this documentation

was still not available.

The inspector concluded that these

conclusions

and recommendations

had

not been formally addressed.

ualit

Performance

and Assessment

Branch Surveillance

90-126,

dated

a

j

The Site guality Assurance

Manager stated that this surveillance

was

initiated by guality Assurance

because

of concerns .regarding the

validity of gC Surveillance

90-30.

This surveillance

was

a review of

previous surveillances,

audits, corrective action requests

(ARs), and

guality Evaluations

(gEs) related to the program for HM NTE.

This

surveillance clearly identified that

some of the findings identified

by gC were repetitive,

and

recommended

a gA audit of the area.

This surveillance mentioned that

MM MSTE deficiencies

had been

identified as early as

1985.

The inspector confirmed that guality

Assurance Audit 85230P,, dated October 17, 1985,

had identified

failures to properly document

HATE usage.

These

problems

were

documented

to have

been corrected

by procedural

revision and

personnel

training.

The inspector

observed that surveillance

90-126 did not recommend

-'n

NCR for the recurrence'f

MSTE program weaknesses.

d.

ualit

Assurance

Audit 90812T, dated

Se tember 6, 1990

This audit independently

reassessed

the

MSTE programs.

including

MM MSTE, five months after the

MN program deficiencies

were identified

by gC.

Ho comment

was

made regarding the existence of programs with

different procedural

requirements for use of HSTE.

The audit did

reconfirm several of the deficiencies identified in the

gC

Surveillance

90-30.

Generally,. it was less clearly written, and

made

no general

conclusions or recormendations

regarding the

HM MSTE

program.

The audit also identified recurrent deficiencies related to those

identified in 1987 by ACR OCO-8?-gA-NOOl.

That 1987

NCR referred to

the discovery that the calibration accuracy ratios

between calibration

standards

and

MSTE had not, in all cases,

been determined

and documented.

This 1990 audit found recurrent failures to control this ratio,

as

had

gC Surveillance 90-30.

Most of the problems identified by Audit 90812T were limited to

technical

issues.,

The most significant findings of this audit

appear to have

been:

Usage information for HSTE was not recorded

as required

on 35K

of 20 work orders

reviewed.

This was

a repeat finding from gC

Survei'llance

90-30.

The procedurally required accuracy ratios

between calibration

standard

and

HSTE of 4:1 were not attained for several different

types of equipment.

This was

a repeat finding from gC

Surveillance

90-30.

HN did not maintain vendor manuals

for. most of the equipment

they were responsible for calibrating; therefore,

tool

room personnel

could not describe

or refer to recognized

practices

and methods of calibration.

This particular

discrepancy,

as noted in paragraph

3.b.3 above,

was still

evident during this inspection in that tool room personnel

were not familiar with the precaution in the vendor manual for

the use of click type torque wrenches.

This audit did not state clearly any conclusions

regarding the

adequacy of the

NN MSTE program,

nor did it make any clear

recommendations

to management,

unlike gC surveillance

90-30.

However, unlike the

gC surveillance,

which only documented

the

specific findings as Action Requests

to the

HN department,

this

audit did issue

several

Audit Finding Reports

(AFRs), which required

the

NM department

to respond with a root cause

determination for the

problems.

0

Action Requests

were the licensee's

working level request for

information by the requestor of the affected party, in this case,

the

MN department.

At the request of the

MM department,

the due

date fop these detailed corrective actions

was extended..

At the

time of the previous

NRC inspe'ction,

no action

had been taken

on

these findings.

This audit did not clearly identify any nonconformance

or programmatic

breakdown,

nor did it refute

gC Surveillance

90-30.

Ho corrective

action for its findings had

been taken prior to the

NRC inspection

which commenced

on November 27,

1990.

5.

Conclusions

Re ardin

Licensee Corrective Action for MM M&TE Pro ram

e ic>encses

Prior to Ins ection 50-2

9 - 9

The previous

NRC inspection

(50-275/90-29) identified that

a

nonconformance

report had not been initiated to address

the recurrent

failures to follow the established

MM M&TE program.

That inspection

focused

on the statements

in Audit 90812T that

MM had not fully

implemented the corrective actions required

by NCR DCO-G7-gA-HOOl.

As discussed

in paragraph

4d above, that NCR's findings were narrowly

focused

on calibration ratio discrepancies.

The failure to initiate

a

nonconformance

was identified in the previous report as unresolved

item

90-275/90-29-01.

The previous inspection also identified several

examples,

in addition to those discussed

in this report, of specific quality problems

in the

MM M&TE program.,

After review of the material

discussed

above, discussion with licensee

personnel

and managers,

and the observations

discussed

in Paragraph

3,

the inspector concluded that the licensee's

corrective action in response

to the many formal reports of a deficient

MN M&TE program

had been inadequate.

guality Control Surveillance

90-30, in particular, clearly reported

a

significant condition adverse

to quality, namely numerous

examples of

failures to implement the

MM M&TE program procedural

requirements.

The

licensee's

own surveillance

repor t characterized

the

MM M&TE program

as

"unsatisfactory"

and "not acceptable."

Senior licensee

management

was provided with the report of surveillance

90-30,

as

was guality Assurance.

Yet, at. the time of the previous

inspection,

over seven

months later,

a nonconformance

report

had not been

issued for these

programmatic discrepancies.

As

a direct result, the

cause for the weaknesses

had not been determineo,

and corrective actions

to restore

program quality were not defined.

Rather,

an additional audit

and

an additional surveillance

were performed which added additional

examples of specific problems,

but did not integrate

the findings further.

These

subsequent

efforts reduced

the clarity of the

gC surveillance's

conclusions

and recommendations,

and postponed

and diluted effective

corrective action to correct the overall problem.

The inspector,

therefore,

concluded that the scope

and breadth of thes

failures

was substanti'al

enough to indicate

a breakdown in the guality

ese

Assurance

program for the calibration and control of measuring

and test

equipment.

This is an apparent violation of the requirements

of

10 CFR Part 50, Appendix B, Criterion XVI, "Corrective Action," and guality

Assurance

Procedure

15.B, "Nonconformances,"

Paragraph

2.1.1

and 3.1, in

  • that

a nonconformance

report for this breakdown

was not initiated until

after the previous

NRC inspection

again brought this problem to senior

management's

attention

(Enforcement

Item 50-275/91-04-02).

Unresolved

Item 50-275/90-29-01,

which directly referenced

the calibration

ratio discrepancies

NCR, is correspondingly

incorporated

as part of this

apparent violation, and is closed.

As noted abbve, related

issues of potential overtorquing of small

fasteners

due to use of click-type torque wrenches

(Open Item

50-275/91-04-01),

use of uncalibrated

torque wrenches

(Open Item

50-275/91-04-03),

and undocumented

use of calibrated tools

(Open Item 50-275/91-04-04)

were identified.

These

items are

considered

integral parts of the

MM HSTE program breakdown.

They

will be followed up during followup on the .Enforcement

Item.

Review of Licensee Corrective Action Since the Previous

Ins ection

As imnediate corrective action for the findings of Inspection 90-

29/90-29,

the licensee

issued

nonconformance

report

NCR DCO-90-

MN-N089 on December

21, 1990.

The nonconformance

was described

as:

"Previous

gC and

gA audit findings indicated

a significant

number of program implementation deficiencies.

These deficiencies,

and the time involved responding to the deficiencies warrant

further evaluation."

At the conclusion of the latest inspection, this

NCR was still under

revision to determine

the appropriate corrective actions.

Most of the

proposed corrective actions from the most recent

gA audit, 90812T,

had

been delayed

pending the development of a unified corrective action plan

from this

NCR.

Unresolved

Item

An unresolved

item is

a matter about which more information is reauired

to ascertain

whether it is an acceptable

item,

a deviation, or a violation.

Exit Interview

The inspector

met with licensee

management

denoted in Paragraph

1 on

'February 14,

1991.

The scope

and detailed findings of the inspection

were discussed.

Licensee representatives

acknowledged

the findings of the

inspection.

Subsequently,

on February 25,

1991, licensee

representatives

were informed that

an Enforcement

Conference

on the results of this

inspection

would be conducted

on March 8, 1991.

n

r

4k