ML16341E181
| ML16341E181 | |
| Person / Time | |
|---|---|
| Site: | Diablo Canyon |
| Issue date: | 04/14/1987 |
| From: | Burdoin J, Mendonca M NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V) |
| To: | |
| Shared Package | |
| ML16341E182 | List: |
| References | |
| 50-275-87-11, 50-323-87-10, GL-83-28, IEB-85-003, IEB-85-3, NUDOCS 8704290396 | |
| Download: ML16341E181 (12) | |
See also: IR 05000275/1987011
Text
U.
S.
NUCLEAR REGULATORY COMMISSION
REGION V
Report Nos. 50-275/87-11,
50-323/87-10
Docket Nos. 50-275,
50-323
Li.cense
Nos.
Licensee:
Pacific Gas
and Electric Company
77 Bea1e Street,
Room 1451
San Francisco,
Cali fornia
94106
Facility Name:
Diablo Canyon Units 1 and
2
Inspection at:
Diablo Canyon Site,
'San Luis Obispo County, California
Inspection
condu
e
March 23-2
, 1987
Inspectors:
Approved by:
F.
ur own,
eacto
Inspector
~a
M.
M nd
ca,
C .ief
eactor
Project .Section
1
0 te Ss,gned
ate Signed
~Summa':
Ins ection Durin
Period of March 23-27
1987
Re ort Nos. 50-275/87-11
and,
50"323 87"10
non-1>censed staff training; followup of IE Temporary Instruction(s).,
Part
21(s),
and previous identified inspection item(s),
and an independent
inspection of various vital areas
and equipment in the plant.
Inspection
procedu'res
nos.
30703,
41400,
71707,
and 92703 were used
as guidance for the.
i.rjspection.
Results:
No items .of noncompliance or deviations were identified.
8704290396
870414
ADOCK 05000275
8
'I
DETAILS.
Individuals Contacted
Pacific Gas
and Electric
Com an
(PG8E)
- R.
C. Thornberry, Plant Manager
"J.
A. Sexton,
Plant Super'intendent
"L. F.
Momack, Operations
Manager
- T. L. Grebel,
Regulatory Compliance Supervisor
R.
M. Luckett, Regulatory Compliance
T. J. Martin, Training. Manager
J.
E.
Mol.den, Operations Training, Supervisor
D.
R. Clifton, Technical
and Maintenance Training Supervisor
N.
M. Bennett, Instructor Training Coordinator
G.
H. Gund, Mechanical.-Maintenance
Training Instructor
T.
N. Gray,
I8C Senior. Training Instructor
D.
R.
Geske, Verification Planning Group Supervisor
C.
L. Meyers,
Docume'nt Control Analyst
M.
L. Smith,
Power Production
Engineer
I
Various other engineering
and
gC personnel.
- Denotes attendees at exit meeting
on March 27, 1987.
In addition,
NRC Resident Inspector(s)
attended
the exit management
meeting.
Area Ins ection
An independent
inspection
was conducted in Units 1 and
2 Turbine and
Auxiliary Buildings.
The equipment
and areas
inspected
included
A.
Five Emergency Diesel Generator
Rooms
B.
Six 4160 Volt Switchgear
Rooms
C.
Combined Two-Unit Control
Room
D
Two Containment
Spray
Pumps, Unit 1
E.
Three Charging
Pumps,
Units 1
F.
Four Safety Injection Pump Areas.
G
Four
RHR Pump Areas
H.
Six .Component Cooling Pumps
I.
Pumps
J.
Six 480 Volt. Vital Bus Rooms
K.
Two Cable Spreading
Rooms
L.
Two Hot Shutdown Panels
M.
Two 480 Volt Center Areas
N.
Turbine Building .at Elevations 140'nd
85'on-I
incensed Staff Trainin
The inspector
examined the licensee's
program for training of
non-licensed staff to determine that it sati.sfies
regulatory requirements
and meets the licensee's
commitments for training.
The
.does
not.
specifically identify any nuclear or'industrial
standards
-to which the
licensee is committed.
In conversation
.with the training'manager, it was
determined that the licensee's
training program conforms to ANSI standard
"
N18. 1-1971 "Selection
and Training of Nuclear
Power Plant Personnel."
The
FSAR describes
training for non-licensed staff as follows:
Replacement training for operation
personnel
hired at Diablo Canyon prior
to April 27,
1984 followed established
company procedures
and programs
which required
new nonlicensed auxiliary operators
to undergo
a- formal 30
month training program.
This program consists of lesson
assignments,
review tests,
and qualification examinations.
Replacement training,for operation
personnel
hired. after April 27,
1984
is conducted in accordance
with .a plant manual
procedure.
Each
new
auxiliary operator
undergoes
a formal structured training program
consisting of two parts;
seventeen
weeks of classroom training,
and
approximately
24 months on-the-job watchstation qualifications'he
17
weeks of classroom training is in fundamentals
which includes
mathematics,
nuclear/m'echanical/electrical
sciences,
etc.
and systems
which includes. electrical/primary/secondary
systems,
and primary and
, secondary
support systems.
Matchstation gualifications,
an on-the-job
phase of traini.ng, prepares
the candidate to operate
components
outside
the control
room and to gain operating experience prior to taking over
the..sole responsibilities of standing .a watch.
This phase 'is divided by
watchstation ta give the. operator
a logical approach to qualification.
Replacement
training. for. nonopqrating personnel,
such
as technicians
and
craft journeymen, is conducted
as required by procedures.
Although these
positions are generally filled with experienced, personnel,
training is
provided to qualify individuals to perform the many specialized
duties of
these positions.
In general,. the training is accomplished
in two phases:
academic
and hands-on (on-the-job) training.
This training is, in
additi.on to the training provided under. the General
Employee Training
Program.
The inspector
examined
the, licensee's
prognam for training of nonlicensed
staff by reviewing. the followi.ng administrative procedures:
AP-B-150,- Rev. 1, dated June 25, 1986,
"Non-Licensed Operator Training
Program"
AP-B-450,
Rev. 1, dated August 21, 1985, "Instrumentation
and Control
Technician Training".
AP-B-750, Rev.,',
dated August 12, 1985,
"Maintenance
Personnel
Training"
The inspector
examined the following training records to determine if the
. above procedures
were properly implemented.
Auxiliary operators;
records for ten people of approximately sixty
nine operators-were
reviewed
0
IBC technicians;
records for seven people of approximately sixty
five technicians
were reviewed
.
Maintenance electricians;
records
for. eight people of approximately
sixty two electricians
were reviewed
It is concluded
from review of the administrative procedures
above
and
examination of the aforementioned training records that the training
program for non-licensed
operators,
I8C technicians
and maintenance
electricians
appears
to satisfy the training requirements
for these
disciplines
as described in the
FSAR.
The inspection in this area
was not completed during this inspection
period and-will be continued during a future inspection.
This item will be followed as open item 50-275/87-11-01.
No violations or deviations
were identified.
Foll.owu
of IE Tem orar
Instruction .s) (TI)
TI 2515/73 (IE Bulletin 85-03) "Motor-0 crated Valve
Common
Mode Failures
Durin
Plant Transients
Oue to
Im ro er Switch Settin s"
Thi.s TI outlines inspection requirements
for IE Bulletin 85-03, which
requested
licensees, to develop
and implement a program to ensure that
switch .settings
on certain .safety-related
motor-operated
valves are
selected,
set and maintained correctly to accommodate
the maximum
differential pressures
expected
on these
valves during both normal
and
abnormal
events within. the design basis.
The inspector
as
a followup to inspection report 50-275/86-31 selected
as
a sample
the following five motor operated
valves;
8107,
8801B,
8974B,
FCV-95 and
LCV-109 from the
27 valves of Unit 1 for which torque/limit
switch adjustments
had been
made during the Unit 1 refueling outage in
fall of 1986.
The work orders
under which the torque/limit switch adjustments
for the.
selected
valves are listed below:
Valve No,'.s..
Mork Order No's.
Valve -No.'s.
Word Order No'.s.
8107
8801B
8974B
G-0001355
C-0002025
C"0002049
FCV-95
LCV-109
C"0003045
C-0002059
The inspector
examined the work orders for task (work},description,
safety/plant
impact, initial review/signoff,
gC inspection
holdpoints/signoff;
summary
comments, operability test/signoff, test data
results,
completion verification, etc.
The records
appeared
to be in
order and adequate.
The requirements of TI 2515-73/IE Bulletin 85.-03 not addressed
in this
repbrt or inspection report 50-275/86-31 will be inspected .during a
subsequent
inspection(s)
and reported
under
Open Item TI 2515/73.
No violations or deviations
were identified.
Followu
of 0 en Items List (OIL
Part 2ls
The following part 21 reports applicable to some nuclear
power plants
were reviewed with the licensee:
OIL 86-20-P, Susceptibility of BH line of instrument manufactured
by
Foxboro, to deterioration resulting in equipment failure.
OIL 86-22-P, Failure of Milmar electronics
underpower relays to meet
gA
standards
required for nuclear
power plant
OIL 86-23-P, Stationary sleeve
on thrust bearing of Atwood 8 Morrill MSIV
must be machined to prevent galling.
The licensee
concluded following his study of the above part 21 reports
that the equipment described
in these
reports is not installed at the
Diablo Canyon Plant.
Consequently,
no action is required of the
licensee.
These
items. are closed.
No=-violations or deviations. were identified.
Followu
of Previous Identified Ins ection Item s
Closed
Item 50-275/85-37-01
Generic Letter 83-28. Item 3.2 Post
Maintenance
Teston
Item 3.2. 1
NRC Requirements
The licensee
shall review maintenance
procedures
and technical
specification to assure
post maintenance
operability testing of all
safety-related
equipment is performed.
Licensee Action
Administrative Procedures
NPAP-CG. "Clearances,"
and AP-C-6S3,
"Post-Maintenance
Testing," are in place,
which ensure that the
appropriate tests
are conducted to verify that equipment which has
been
removed from service for maintenance
(either corrective or preventive)
be
tested prior to its return to service to determine that it is operable
and.is
capable of performing its intended'safety
function.
Following
completion of maintenance. work, the appropriate
postmaintenance
test is
run after. the equipment is return to service,
but before declaring it
"operable".
E
~
Item 3.2.2
NRC Requir ement:
The licensee
shall review vendor
and engineering
recommendations
to
ensure that appropriate test guidance is included in test
and maintenance
procedures
and technical specifications
where required.
Licensee Action
The licensee
has reviewed the applicable
vendor
and engineering
recommendations to ensure that appropriate test guidance is included in
maintenance
procedures
or technical specifications
as required.
No
technical specifications
changes
were made.
Of the postmaintenance
testing recommendations
generated
from the review,
few recommendations
need further review to determine if they should
be
incorporated into future procedure
revisions.
If they are determined to
be applicable,
the procedures will be revised
by mid-November
1986.
The licensee.'.s
actions described
above were submitted to the .staff in
DCL-86-074 dated
March 20, 1986.
This material
was reviewed by the staff
along with additional material
on the subject submitted earlier.
The
staff's safety evaluation
forwarded to the licensee
October
21,
1986
concluded that the licensee's
actions
taken in response
to. Items 3.2.1
and 3.2.2 were acceptable.
The inspector
examined administrative procedures
NPAP-C6 "Clearances,"
and AP-C-6S3,
"Post-Maintenance
Testing,"
and concluded that they
appeared
to be in order and satisfy the requirements'of
Items 3.2.1.
This item is closed.
No violations or deviations
were identified.
The inspector
conducted
an exit meeting
on March 27, 1987, with the Plant
Manager
and other members of the plant staff.
During this meeting,
the
inspector
summarized the scope of the inspection activities and reviewed
the inspection findings as described
in this report.
The licensee
acknowledged
the concerns identified in the report.
~
b
0
ir