ML16341D856

From kanterella
Jump to navigation Jump to search
Insp Repts 50-275/86-21 & 50-323/86-21 on 860721-25.No Noncompliance or Deviation Noted.Major Areas Inspected: Generic Ltrs,Followup of Allegation,Followup on Notice of Violation & Independent Insp,Using Listed IE Procedures
ML16341D856
Person / Time
Site: Diablo Canyon  
Issue date: 08/11/1986
From: Burdoin J, Mendonca M, Sub G, Suh G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML16341D857 List:
References
50-275-86-21, 50-323-86-21, GL-83-28, GL-83-286-21, GL-85-09, GL-85-22, GL-85-226-21, GL-85-9, GL-85-96-21, NUDOCS 8608270108
Download: ML16341D856 (18)


See also: IR 05000275/1986021

Text

Report Nos.

Docket Nos.

License Nos.

Licensee:

U. S.

NUCLEAR REGULATORY COMMISSION

REGION V

50-275/86-21,

50-323/86-21

50-275,

50-323

DPR-807

DPR-82

Pacific Gas

and Electric Company

77 Beale Street,

Room 1451

San Francisco,

California

94106

Facility Name:

Diablo Canyon Units

3. and

2

" Diablo Canyon Site,, San Luis

Inspection Conducted:

July 21-25,

1986

Inspectors:

J. Z. Burdoin, Reactor Inspector

Inspection at:

G. Y. Suh, Reactor Inspector

Approved by:

M. M. Mendonca,

Chief, Reactor Project

~Summer:

Obispo County,

CA

p/ii/g~

Datq Signed

3zt l>~

Date Signed

pg. lap

Section I

Date Signed

Ins ection durin

eriod of Jul

21-25

1986

(Re ort Nos. 50-275/86-21

and

50-323/86-21

  • '""'"'"

generic letters, of followup of an. allegation, of followup on Notice of

Violation, and independent

inspection of the plant.

Inspection procedure

numbers

30703,

71707,

35744,

92702,and

92703 were used

as guidance for the

inspection.

Results:

No items of noncompliance

or deviations

were identified.

8608270108

860811

PDR

  • 000K 05000275

PDR

1

f

t

'

@

h

DETAILS

Individuals Contacted

Pacific

Gas

and Electric

Com an

(PG&E)

J.

D. Shiffer, Vice President

-R.

C. Thornberry, Plant Manager

D. R. Bell,

QC Supervisor

T. A. Roselli,

QC Engineer

W. J. Kelly, Iicensing 'Representative

-T. L. Grebel, Regulatory Compliance Supervisor

C. Coffer, Nuclear Regulatory Affairs

R.

Oman, Assistant Project Engineer for Systems,

NECS

E. Connell, Supervisor,

Mechanical

Group,

NECS

T. Lee, Nuclear Group Ieader,

NECS

R. Luckett, Regulatory Compliance

Various other engineering

and

QC personnel

="Denotes attendees

at exit management

meeting

on July 25,

1986.

In addition,

a

NRC Resident Inspector attended

the exit management

meeting.

An independent

inspection

was conducted in the Turbine and Auxiliary

Buildings.

The equipment

spaces

inspected

included:

a.

Three Emergency Diesel Generator

Rooms, Unit l.

b.

Three

4160 Volt Switchgear

Rooms, Unit l.

c.

Sj.x Battery Rooms, Units

1 and 2.

d.

Two RHR Pump Rooms, Unit l.

e.

Two Cable Spreading

Rooms, Units

1 and 2.

f.

,Three Charging

Pump Areas, Unit l.

g.

Turbine Building, Elevations 85'nd 140', Unit 1.

h.

Three

CCW Pump Areas, Unit 1.

i.

Two Safety Injection Pump Areas, Unit l.

j.

Two Containment

Spray

Pump Areas, Unit 1.

k.

Combined Two-Unit Control Room, Units

1 'and

2

'1.

Boron Injection Tank Area, Unit 1.

m.

Containment Penetration

Area, 85'levation, Unit l.

Housekeeping

and equipment status

appeared

to be acceptable.

No violations of NRC requirements

were identified.

Notice of Violation Follow-u

The inspector

reviewed the licensee's letter of response

to the Notice of

Violation included in NRC Inspection Report 50-275/86-14

and

50-323/86-15.

PGSE letter DCL-86-164, dated June ll, 1986, describes

the

FW

1

h

4

~

W

y

I

W

t

I

'F

h

4

~ 4 I

4

4

I

II

~

I

h

h

n

p

4

I

4

I

Fl 4

4

I

~

4

'7

hl

~

4

4

4

I

I

I

corrective measures

taken and/or planned to be taken to remedy the

findings of this violation.

The Notice of Violation identified eight Licensee Event Reports

(LERs)

for Units

1 and

2 which were examples of Technical Specification

(TS)

required surveillances

that had not been performed within the

TS allowed

time limits.

These

examples

demonstrated

an inherent weakness

in the

licensee's

control of the

TS Surveillance Test Program

(STP) which

resul.ted in required

TS surveillances

being passed

over.

The licensee

pointed out that they had become

aware of the weakness

in

the area of control of TS surveillance

schedules

as early as last year.

Following the issuance

of the

SALP Report,

October

18,

1985, which

identified what appeared

to be

a negative surveillance testing program

trend,

the licensee

reviewed past surveillance

records

and initiated

a

Surveillance Test Improvement Action Program

(SAP) during the last

quarter of calendar year 1985.

From these

reviews,

the licensee

identified and reported additional missed surveillances.

These

reviews

are continuing and PGSE will promptly report any additional mis'sed

surveiilances.

The Surveillance Test Improvement Action Plan consisted

of:

Reexamining the surveillance control procedures

and initiating

necessary

improvements;

Providing additional staffing, including a dedicated Surveillance

Test Supervisor to manage

the

SAP;

Providing additional training; and

Improving the Preventive Maintenance

and Test Scheduler

(PMTS)

computer program software

and diagnostics.

From the review of past surveillance

records,

additional missed

surveillances

were identified and reported in the foll,owing IERs:

Unit 1

84-36-

84-37-

84-38-

84-39-

85-40-

86-02-

Missed Surveillance

on BIT Recirculation

Check Valve 8912

Surveillance

on Containment Fan Cooler Unit 1-2 not

Performed within Technical Specificatipn Required Interval

Procedural Deficiency Results in Missed Surveillance

Procedural

Inadequacy

and Personnel Error Results in

Inadequate

Surveillance Test on 125V Battery 1-3

Incomplete Performance of a Surveillance Test

Surveillance Required by Technical Specifications

Not

Performed

Unit 2

85-27 - Missed Surveillance

on Valve FCV-678 Due to the Preventive

Maintenance

and Test Scheduler

System File Being Updated in

Error

h

4

I

V

1i

i

f

U

k'"

'I

The inspector

reviewed these

IERs and the corrective actions taken by the

licensee

which appear to be acceptable.

The inspector

reviewed the licensee's

additional corrective actions,

listed below,

and examined the identified document(s)

to verify these

actions

and the

SAP Program described

above:

a

~

Co'rrective Action(s):

A supplemental

review of regulatory requirement

changes,

and an

independent

review of TS and

STPs is being performed by the

licensee's

Regulatory Compliance

Group to ensure all TS requirements

are appropriately incorporated into STPs.

Document(s)

(1)

Procedure,

AP A-55, "Administrative Procedure

Technical

Specification

Change Process."

(2)

Second quarter Status,

Surveillance

Improvement Action Plan,

dated

June 30,

1986.

b.

Corrective Action(s}:

A training program has been partially developed

which includes

procedure

revisions to AP C-3Sl and

AP E-4,

and lessons

learned

from

the

STP file and LER reviews.

The lessons

learned, will be

periodically reevaluated

and incorporated into an on'going retraining

program.

Plant management is involved in the development,

implementation,

and monitoring oj 'this training program..

The

initial training session

was conducted

on May 9,

1986, for all DCPP

surveillance test program department

heads

and test coordinators.

Document(s):

Training Session Record,

Topic:

Surveillance Training, dated

May 9,

1986.

C.

Corrective Action(s):

A special Plant Staff Review Committee

(PSRC) meeting will be held

once per quarter to assure

DCPP is taking adequate

overall

corrective actions in response

to identified problems.

This special

PSRC will overview the following to ensure application of lessons

learned

and that any trends

are identified:

Effectiveness

of Technical Review Groups;

Trending of Nonconformance

Reports

(NCRs) and LERs, including

summary of root causes

and appropriateness

of corrective

actions;

and

Human Performance

Evaluation System findings.

e

4

If

if

~

el

>>4

eel

I

F I

I

e

4

I

I

4

J

he

e

m

4

m

e

4

Document(s):

(1)

Onsite Safety Review Group

(OSRG)

NCR Trend Analysis and

Training Critique Summary, First quarter

1986.

(2)

PSRC's

Minutes of a Special Meeting, June 3,

1986.

d.

Corrective Action(s):

gC is conducting

a 100$ ongoing review of completed

STP data

sheets

to verify compliance with procedural

requirements.

This will

continue at least through the completion of the Surveillance Test

Program Action Plan at which time plant managers will determine

the

extent of future reviews.

Document(s):

Procedure,

AP C-800S1,

"Administrative Procedure,

DCPP

gC Department

Activities'

"

e.

Corrective Action(s):

The licensee is in the process

of performing gA reviews of Chemistry

and Radiation Protection, Electrical and Mechanical Maintenance,

and

the Fire Marshal completed

STP files.

Document(s):

One intra-company

memorandum,

dated July 23,

1986, from equality

Support to Engineering Department, File No. 420.7, Subject:

Data

Sheets

Versus Files

08 and 58.

The examination of the corrective actions

taken by the licensee in

response

to this violation also entailed

a detailed review by the

inspector of Procedure

AP C-3Sl, "Administrative Procedure

Surveillance

Testing and Inspection," dated April 21, 1986.

This procedure

which

describes

the Surveillance Testing and Inspection Program to be used at

Diablo Canyon has been revised since the inspection conducted during

April 7-11,

1986 (Inspection Report Nos. 50-275/86-12

and 50-323/86-13).

This latest Revision

7 along with Procedure

AP C-800Sl (identified above)

has incorporated

the essence

of the inspector's

findings reported in the

April 7-11 inspection with regard to the subject of Procedure

AP C-3Sl.

Followup items 50-275/86-12-02

and 50-323/86-13-02

are closed.

It is concluded by the inspector that the corrective actions

taken

by the licensee in response

to this violation are acceptable.

This violation (50-275/86-12-01

and 50-323/86-13-01) is closed.

4

I

1

~

~

~l

~

~

4.

Followu

of Generic Letters

a.

(Closed) 50-275/50-323

Generic Letter 85-22

Potential for Loss of

Post-LOCA Recirculation

Ca abilit

Due to Insulation .Debris Blocka

e

This generic letter informed licensees

of a generic safety concern

regarding IOCA-generated insulation debris that could block

containment

emergency

sump screens.

This blockage

could result in a

reduction of net positive suction head margin below that required

for recirculation pumps to maintain long-term cooling.

In the

letter,

the staff recommended

Regulatory

Guide

(RG) 1.82, Revision

1, 'be used

as guidance for the conduct of 10 CFR 50.59 reviews

dealing with the changeout

and/or modification of thermal insulation

installed

on primary coolant system piping and components.

RG 1.82,

Revision 1, provides

guidance for estimating potential debris

blockage effects.

Although no written response

or specific action

was required by .this letter, licensees

were directed to distribute

copies of the generic letter and its enclosures

to the appropriate

groups within their organizations

responsible for conducting

10 CFR 50.59 reviews.

b.

In telecons with representatives

of the licensee's

Nuclear Power

Generation Department,

the inspector

determined that the generic

letter and its enclosures

were distributed to the groups responsible

for conducting

10 CFR 50.59 reviews

(Nuclear Operations

Support,

Nuclear Engineering

and Construction Services

(NECS)) in the

corporate offices. It was also verified that the Nuclear Group

within NECS which has design responsibility for containment

sumps

had received

and reviewed the generic letter;

and determined that

no corrective actions

were needed.'he

on'site

10 CFR 50.59 review

responsibility,

as outlined in Administrative Procedure

C-1 Sl,

"Onsite Plant Modification Administration," is held by the

PSRC with

working review responsibility delegated 'to the Regulatory Compliance

Group.

The inspector

determined that these organizations

had

received

copies of this generic letter and its enclosures.

Based

on the above,

we conclude that the licensee's

response

to

Generic Letter 85-22 was acceptable'.

This, generic letter is closed

for Units

1 and 2.

I

(0 en) 50-275/50-323

Generic Letter 85-09

Technical

S ecifications

for Generic Ietter 83-Z8

Item 4.3

I

Item 4.3 of Generic Letter Ietter 83-28,

"Required Actions Based

on

Generic Implications of Salem

ATWS Events," established

the

requirement for the automatic actuation of the shunt trip attachment.

for Westinghouse plants.

In Generic Letter 85-09,

the staff

requested

licensees

and applicants of Westinghouse

PWRs to submit

proposed

TS changes

to include enhanced limiting condtions of

operation

and surveillance/testing

requirements

for the reactor trip

breaker

components

and the, reactor trip bypass

breakers.

In response,

the licensee

stated that it is

a member of the

Westinghouse

Owners

Group

(WOG) and subscriber

to the

WOG program to

develop

a reactor trip breaker reliability model.

Based

on the

A

~

~

r I-

I

I

f

I

I K

11

V

I

I'

'

KI

i"

I

e

K

I

I,

I

K

O'f

I

1

f

I'

.I

N

Kt

II

I

r

r

I

I

,, hl

I

I

K

It

p

I

K'

V

Il

I

ll,

'l l 'l

p

VK

KN'

~

%

1

rrr

1

I

III

Ir

c ..It

I

K

I, I

I

C

K tt

j

I

tf

tt

Ih

I

N

1

11

I

'I

I

lt

Ik,

'I

1*

rr

I

I

a

I

1

6

WOG's current calculations, of the reactor trip system

unavailability, the 3.icensee

concluded that there is an

insignificant reliability improvement from including periodic

surveillance tests of the bypass breakers in the TSs.

PGSE proposed

to administratively control bypass

breaker testing.

The licensee

also proposed to'dopt the remaining surveillance test requirements

and allowable outage

times proposed in Generic Letter 85-09

as

administratively controlled interim requirements,

without TS

changes, until the requirements

can be optimally determined

once the

HOG trip breaker reliability model is developed.

NRR is currently reviewing the licensee's

submittal with a scheduled

review completion date of December,

1986.

This item will remain

open

and will be followed as

open item GL-85-09.

5.

Alle ation

ATS No. RV-86-A-0049

a

~

Characterization

Three H. P. Foley Company nonconformance

reports

(NCRs 8802-865,

8802-939,

and 8802-943)

were not processed

in, accordance

with

established

procedures.

b.

Im lied Si nificance to Desi n

Construction'or

0 eration

Improper processing

of NCRs and failure to correct nonconforming

conditions

may result in known plant deficiencies

which could have

an adverse effect on the safe operation of the plant.

C.

Assessment

of Safet

Si nificance

This allegation involves two concerns:

(1)

The first concern is that NCR 8802-865

was dispositioned

"accept as-built" and that corrective action was accomplished

later,

on a minor variation report,

The alleger's logical

question

was

"why it was accepted-as-built

on his

NCR and being

corrected later."

NCR 8802-865 filed on June 21,

1983, identified welding

concerns in a Unit 2 containment

hydrogen monitoring

(RCHMC)

panel which developed

from Resign

Change Notice

(DCN)

DCO-EE-594, Revisions

15 and -16.

Revision

15 of the

DCN called

for the mounting of two modules in the

RCQ1C panel which

involved the installation of'ome angle iron pieces inside the

panel for mounting the two modules

and terminal blocks,

and

enlarging the openings in the panels to facilitate mounting

modules

82 and 83.

Revision

15 also allowed for the removal of

up to 30% of weld material in welds adjacent to the openings

during the'opening

enlarging'process.

"Revision 16 to DCN 594

modified the design of Revision 15 by changing,th'e'"sizes

of the

angle iron pieces.

'

tj fl

DCN DC2-SE-12835,

Revision "0" (issued 6/13/83), called for the

installation of twelve welds (six per module) to replace

those

)

1

!

t

~

~

h

I

~

P

k,k(,

E

h ~

5 I'

71

hh

'

I

1

P

ll

J

'Ilh

h

r

P,

k

7

'.

P

I

( h

P

P

~

~

~

F

welds

removed during the installation of modules

82 and

83

under

DCN 594;

Revision

1 (issued

June

28,

1983) to DCN 12835

changed

the design of Revision

0 to add twenty bolts to the

RCHMC panel, in lieu of the twelve welds.

The inspector

examined

the above identified DCNs,

and the

associated

gC inspector reports

contained in these

packages.

The

DCN packages

and documentation

apyear to be in order.

The

inspector also examined in the field the installation of

modules

82 and

83 in the

RCHMC panel.

The field examination

verified that twenty bolts and washers

required by DCN 12835,

Revision 2, to replace

welds

removed under

DCN 594, Revision

16,

had been installed.

The inspector

examined in detail

NCR 8802-865 which dealt with

various aspects

of welds under

DCN 594.

However, the welds to

be installed under

DCN 12385, Revision 0, evidently were never

installed because

Revision

1 for the

same

DCN substituted bolts

and washers in lieu of welds.

However, it appears

that

some

grinding of welds took place in the

RCHMC panel to remove weld

material, probably from DCN 594 Revision 15, which allowed for

the removal of 30% of existing weld material. It appears

that

the "As Built" expression

used in the NCR referred to the

grinding of any remaining weld material in preparation for the

use of bolts and washers

as

a substitute for the twelve welds.

The completion of the installation of modules

82 and 83 in RCHMC

panel

was accomplished

under

DCN 12835, Revision 1.

No records

of completing the work under

a minor variation report can be

found in the package.

It appeared

from the examination of

records

and files that the work was accomplished

and

(}C

inspected in accordance

with established

procedures

to assure

the quality of work required for Class I systems.

It is concluded that the dispositioning of NCR 8802-865

appeared

to conform to Foley procedure

gCP-3 for processing

and

control of deviations

and nonconformances.

(2)

The second

concern entails the initiation of NRC 8802-939

dated

October 4,

1983, for Class I Support Rework.

The

NCR was

voided on October 5,

1983,

and

NCR 8802-943 which addresses

the

dispositioning/voiding of, NCR '8803-939

was initiated the

same

day.

The alleger's

concern is that NCR 8802-939 filed October 4,

1983,

was improperly dispositioned.

The

NCR identified conduit

change

order 4119 which required relocating the support for

electrical cable'ray

JJEA because it interfered with a new

beam joint connection.

The

NCR cia'imed the conduit change

order should have been processed

under raceway'upport

rework

Appendix

D of Procedure

QCP-17 rather

than. Appendix

C

(electrical modification work).

I

J

The inspector

examined Appendix

C of procedure

gCP-17

and

identified that Exhibit C-l, "Conduit Change Order," allows for

~

~

~

d

H4'l

H

P

I

I

e

H

"~

t

,d

H

H 'I

I

V

K

~

I

I

'

Ht

td

~,

t'H'1

I'If. H

d

H

k

rd

A

K,H

Hl

H

k

relocating Class I raceway supports.

Conversations

with the

licensee's

gC people

has determined that it was the

company'olicy

to accomplish inter-departmental

interferences

(IDI),

raceways conflicting with structural steel or piping under

Appendix

C of gCP-17.

The inspector

examined conduit change

order No.

4119 package

and the enclosed

QC records.

The records

and files appear to

be in order indicating the work of relocating the electrical

tray support was accomplished in accordance

with established

procedures.

d.

e.

The two NCRs,

8802-939

and 8802-943,

were reviewed;

and it is

concluded that the dispositioning of these

MCRs appears

to be

adequate

and to have been processed

in accordance

with

established

procedures.

Lt

Conclusions

and Staff 'Position

It is concluded that the" subject

NCRs have been dispositioned in

accordance

with established

procedures.

l$

Mone.

~

~

6.

The ins ector conducted

an exit meetin

o

1

p

g

n July 25,

1986, with the Plant

Manager

and Compliance Supervisor.

During this meeting,

the inspector

summarized

the scope of the inspection'activities

and reviewed the

inspection findings as described in this report.

The licensee

acknowledged

the concerns identified in the report.

~

~

~

II

H

W

1

I