ML16341C888

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-275/79-01 & 50-323/79-01 on 790122-0201.No Noncompliance Noted.Major Areas Inspected:License Action on Previous Findings,Electrical & Instrumentation Work Observation & Record Review of Seismic Trip Sys
ML16341C888
Person / Time
Site: Diablo Canyon  
Issue date: 02/08/1979
From: Haynes R, Hutson T, Kirsch D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML16341C889 List:
References
50-275-79-01, 50-275-79-1, NUDOCS 7903190071
Download: ML16341C888 (24)


See also: IR 05000275/1979001

Text

U.

S.

NUCLEAR REGULATORY COP)MISSION

OFFICE

OF

INSPECTION AND ENFORCEMENT

REGION V

50-275/79-01

,Report

No.

50-323/79-01

50-275

Docket

No.

50-323

CPPR-39

License

No.

CPPR-69

Safeguards

Group

Licensee:

Pacific

Gas

and Electric Company

77 Beale Street

San Francisco,

California

94106

Facility Name.

Diablo Canyon Units

1 and

2

Inspection at

Diablo Canyon Site,

San Luis Obispo County, California

Inspection

Conducted

January

22 - February 1,

1979

Inspectors:

D. F. irs,

eactor Inspector

9

T. W. Hutson,

Reactor

Inspector

ate Signed

Approved By:

R. C.. Haynes~

f, Project Section,

Reactor

Construction

and Engineering

Support

Branch

Summary:

Ins ection'.during period of Januar

22,

1979 throu

h Februar

1,

1979

Re ort Nos.

50-27

-6l an

Areas

Ins ected:

Routine,

unannounced

inspection

by regional

based

inspectors

of

icensee

action

on previous inspection findings; licensee

action

on reported

50.55(e)

items; electrical

and instrumentation

work observation

and record

review related to the seismic trip system

and dedicated

shutdown panel; arc

strike repair program;

VSL tendon

and rock anchor

work observation

and record

review; pipe support

and restraint work observation

and record review; as-built

drawing completion

and engineers

equipment releases;

and

gA audits.

The

inspection involved 77 inspector-hours

onsite

by two

NRC inspectors.

Results:

Of the eight areas

inspected,

no items of noncompliance

or deviations

vre~e Vuentified in seven

areas

and

one

unr esoived

item was identified in .the

area of pipe support

and restraints-(Paragraph

10).

0~~80oq (,

IE:V Form 219 (2)

ll

DETAILS

Individual s Contacted

a ~

Pacific

Gas

and Electric

Com an

(PGSE

b.

+R.

  • M
  • M.
  • D
  • J
  • V
  • J
    • D

D.

H.

C.

J.

R.

R.

S.

J.

J.

J.

R.I.

J.

B.

Gu

D. Etzler, Project Superintendent

N. Norem, Startup

Engineer

E. Leppke,

QA Supervisor

A. Rockwell, Resident Electrical

Engineer

N. Cochran,

Resident Civil Engineer

L . Killpack, Resident

Mechanical

Engineer

Arnold, Coordinating

QC Engineer

L. Polley, Assistant

To Project Engineer

Nielsen,

Senior Electrical

Engineer

J. Gormley, Supervising

Mechanical

Engineer

Braff, Pipe Support Supervisor

A. Holley, Piping Inspection

Group Supervisor

A. Young, Electrical

Engineer

Bell,

QA Inspector

J. Foat, Electrical Field Engineer

Nystrom, Electrical

Inspector

Cole, Electrical Field Engineer

Hanna,

NSSS Group Supervisor

Mendoza, Field Engineer

Macdonald,

Engineering

Services-Scheduler

R. Sumner,

Startup

Engineer

Gragg,

Welding Inspector

F. Atkinson

Com an

GFA

c ~

M.

T.

p.

M.

H.

M. Walsh,

QA Manager

Loomis,

QA Auditor

Bernasconi,

QC Inspector

Anderson,

Lead Inspector

P. Foie

Com an

Foie

V. Tenneyson,

QA Manager

d.

Pullman-Kelloq

(Kello

D.

V.

D.

Geske,

Assistant

QA Manager

J . Casey,

Level II Examiner

K. Truran,

QA Engineering

Supervisor

+Contacted

via telecon

on February 2, 1979.

  • Attended January

25, 1979, exit interview at site.

    • Attended February 1, 1979, exit interview at Corporate Office.

Project Status

The licensee

plans to be prepared

to load fuel in Unit

1 about

May 1,

1979,

pending completion of the operating license

hearings

and

issuance

of an operating license,

and plans to complete all seismic

modification work on Unit

1 prior to fuel load, except:

a.

Seismic

upgrade of the fire protection

hose reel

system.

b.

Installation of flange extensions

to the Turbine Building

structural

steel

columns.

The Unit

1

punch list was reviewed

and noted to contain about

265 items, not all of which are required for fuel loading or

startup.

The licensee

stated that the punch list would Become

much smaller following the performance of system verification

testing, currently to be performed in February

1979.

Gener al

Effective February 1, 1979, Mr.

W. A. Raymond

assumed

the duties

of gA Director, replacing Mr. R.

P.

Wischow.

Mr. Raymond

was

previously Plant Superintendent

at Humboldt Bay Nuclear

Power

Plant.

In response

to inspector questions,

the licensee

reported that

no

Kulka terminal blocks

(No. 604D-2402-06)

are

used in safety re-

lated applications at Diablo Canyon.

Licensee Action on 0 en Items of Enforcement

(0 en) Infraction - Failure to Se grate Mutuall

Redundant Circuits

n Contr'o

Room

Pane s'in

a Manner

Re uvre

b t e

PS

R

5 -275 an

2

8-

In response

to the item of noncompliance,

the licensee

reported the

discrepancy in accordance

with 10 CFR 50,

Paragraph

50.55(e).

The

licensee

submitted letters to the

NRC on November 2, 1978,

and Jan-

uary 18, 1978, addressing

the corrective actions required

by the

Notice of Yiolation and

10 CFR 50, Paragraph

50.55(e).

Representatives

of the licensee's

Engineering

Department

had

inspected

the Unit

1

and

2 Auxiliary Safeguards

Cabinets

A and

B,

Solid State Protection

System Trains

A and

B and the Main Control

-3-

Boards.

These

inspections

did not disclose

any additional defi-

ciencies in separation

of mutually redundant circuits.

The li-

censee

had written Nonconformance

Report

(NCR) No. DCO-78-EG-009

documenting

the item of noncompliance.

This

NCR was in the pro-

cess of resolution.

An instruction (NPI-2.3,

"NRC Licensing" )

was issued

on November 15, 1978, to assure that verification

actions are taken

by engineering

in response

to

NRC licensing

comnitments

not covered

by normal design or construction verifi-

cation.

The inspector observed that the licensee

had begun separation of

mutually redundant circuits in the control

room panels

and noted

that inspection

and acceptance

had not yet been performed.

This

area will be examined during

a future inspection.

5.

Licensee Action on Ins ector Identified Followu

Items

a.

(Closed)

Pi

e

Su

ort Ins ection

50-323/78-15-04

The licensee

stated that

a final walk'down inspection

was being

performed

on Unit

1 pipe supports

and

was also scheduled

for

Unit 2.

The licensee

reaffirmed the commitment that all Unit

1

mechanical

snubbers

would be inspected

and stroked within 30

days prior to fuel loading to assure

proper operation.

The

Unit

1 final pipe support inspection -program

has

shown that

only a small percentage

of Unit

1 hangers

have discrepancies

(mainly loose nuts).

Although the Unit 2 final walkdown had not begun,

the licensee

had corrected

the discrepant

conditions

noted

on Unit 2 sup-

ports

Nos.

564-90

and 564-95.

(Ref.

IE Inspection Report

No.

50-323/78-1 5. )

The inspectors verified that the licensee's

walkdown program

adequately

addressed

final inspection criteria

and appeared

effective in determining discrepant

conditions requiring repair.

No items of noncompliance

or deviations

were identified.

I

b.

(Closed) Unresolved

Item - Unit 2 Pi

e

Su

ort Meld Surface

re arat

on

5 -323 78-

-05

The inspector

examined the licensee's

actions to resolve what

appeared

to be rough surface conditions

on

a weld of support

No.89-25R.

The licensee

ground the weld area in question

to a smooth surface

and performed

a liquid penetrant

examina-

tion of the area

on December

20, 1978.

The liquid penetrant

(LP) examination

record

was

examined

and

no rejectable indica-

tions were found.

LP examinations

were witnessed

by PG&E gC

personnel.

This was the fourth satisfactory

LP examination

performed

on that shop weld.

No items of noncompliance

or

deviations

were identified.

(Closed) Protection of Safet

Related

Com onents

50-323/78-15-06

The inspector

examined

the licensee's

program for maintaining

and verifying cleanliness

of primary system

components.

Proce-

dure MFI-3-2 and Specification

8752 require that component

openings

remain closed

except

as necessary for installation or

fitup.

Licensee

representatives

stated that only the Resident

Mechanical

Engineer

may authorize entry to the primary system

for specific activities; moreover; after flushing, strict con-

trol is employed wherein

permanent

covers

are installed

and

entry is allowed only with proper clothing and material

account-

ability.

The licensee

pointed out that an inspection

and cleanup

of primary piping is per formed prior to and after flushing.

The Unit 2 primary system

had not been flushed yet.

The pro-

gram for maintaining

and verifying cleanliness

of primary system

components

appears

to adequately

implement the

NSSS suppliers

requirements.

No items of noncompliance

or deviations

were

identified.

(Closed) Safet

Related

Outside

Tank Foundations

50-

32

8-

The inspector

examined

the licensee's

actions to preclude voids

in the concrete

foundations of outside safety related

tanks

and

found that the actions

appeared

adequate.

Documentation

examined

'ncluded

the batch plant inspector's daily reports, daily strength

reports

and concrete

placement

cards for lifts F317-B,

C and

D

of the Unit

1 condensate

storage

tank and lifts F327-A, B, and

C of the Unit

1 refueling water storage tank.

The

GFA procedure for stud welding

(gCP-16)

was examined for

compliance with AWS-D1.1.

The completed installations of about

500 studs

were examined for compliance with procedural

require-

ments.

The

GFA stud welding inspection reports

and bend test

inspection reports were sampled

and

examined for compliance

with procedural

requirements.

The following activities related to the installation of seismic

modifications

on the outside safety related

storage

tanks were

sampled

and

examined for compliance with procedural

requirements.

(1)

Completed welding and fitup of tank stiffener plates.

(2)

Reinforcing steel installation on Unit

1 condensate

storage

tank and refueling water storage tank.

(3)

Goner ete curing conditions.

(4)

Rebar storage conditions.

No items of noncompliance

or deviations

were identified.

e.

Closed

Seismic Stron

t3otion Indication and Reactor Tri

'

stem

50-275

323 78- 5-08

The licensee classified the seismic strong motion indication

system as."not safety related"

and the reactor trip system

as

safety related.

(1)

Review of

A Im lementin

Procedures

The following Foley procedures

were examined for compliance

with FSAR commitments

and licensee

drawing requirements:

(a)

gCP-9:

"Installation of Raceways,

Junction

Boxes

and

Terminal

Boxes for Wire Pull"

(b)

gCP-10:

"gC Procedure f'r Power, Control

and Signal

Wires"

(c)

gCP-ll:

"Cable and Wire Terminations"

No items of noncom'pliance

or deviations

were identified.

(2)

Observation of Work and

Work Activities

The following completed

work associated

with the seismic

trip system

was

examined for compliance with procedural

and

FSAR requirements.

(a)

Nine conduit installations.

(b)

Thirty-five cable installations,

including

terminations.

(c)

Nine conduit supports.

(d)

Cabinet mounting

and circuit installations in

Seismic Trip Cabinets for Trains

A and

B.

No items of noncompliance

or deviations

were identified.

(3)

Review of

ual it

Records

The following quality related

records associated

with the

above observations

were examined for compliance with pro-

cedural

requir ements:

(a)

Conduit installation sheets

(b)

Raceway inspection reports

(c)

Circuit installation records

(d)

Circuit installation resistance

data

(e)

Cirucit termination records

(f)

Class

IE support inspection reports

(g)

Support installation work sheets

No items of noncompliance

or deviations

were identified.

f.

(Closed) Fire Protection

and

Su

ression

S stem

The licensee

had performed

a walkdown inspection of Unit

1

piping systems

to determine

the number of anchors installed into

concrete

blocks of concrete

block walls.

Licensee representa-

tives noted that the center

of concrete

blocks was not an area

of concern

because

the centers

are filled with steel-reinforced

concrete.

A similar walkdown inspection

was scheduled for

Unit 2.

An evaluation of the effectiveness

of a small

number

of hangers

installed in the concrete

blocks was being performed.

The inspector

had

no further questions

on this item.

Licensee

representatives

noted that fire protection

hose reel

lines would be supported

by seismically qualified hangers

and

that about 405 of this work had

been

completed in Unit 1.

Fire

protection sprinklers

were being

added

over Class

1 equipment

and all

new sprinkler

system lines are to be supported

by

seismically qualified hangers.

This work was currently 305

complete in Unit l.

It had

been identified by an

NRC inspector that one Cardox

system pipe support

had loose locknuts

and

was missing

one

U-bolt nut.

(IE Inspection

Report

No. 50-275/78-15.)

The

9

licensee

noted that the Cardox system

was

a Class

2 system

and that the repair of the identified discrepancies

was

completed

on January

23,

1979.

No items of noncompliance

or deviations

were identified.

(0 en

Ru ture Restraint Bolt Tension Settin

s

50-323/76-03,

05,

8-

an

Discussions

with licensee

and contractor

personnel

disclosed that

all A490 bolts installed in rupture restraints,

that

had been

torqued more than once, will be replaced.

The most recent revision

of the

AISC Specification for Structural

Joints

Using

ASTl1 A325

or A490 Bolts requires that A490 bolts not be reused after final

torqueing.

Numerous rupture restraints

have

been disassembled

and reassembled

due to modifications or rework and therefore con-

tain reused

A490 bolts.

This practice

was allowed by the pre-

vious edition of the structural

steel bolting standard.

Due

to the difficulty in determining accurately

which bolts

had

been

torqued

more than once,

the licensee

decided to replace all A490

bolts used in the rupture restraints.

This item will be examined

during

a future inspection.

Licensee Action on 50.55 e) Items

a ~

(Closed)

Ade uac

of tlotor Driven Auxiliar

Feedwater

Pum

s

e

.

IE Ins ect on

Re ort

o.

5 -2

an

3

The licensee

had submitted

a final report addressing

this matter

on October

24, 1978.

The report

was reviewed

and appeared

to

provide adequate

resolution of the identified condition.

This

item is closed.

b.

(Closed

De th-to-Thickness

Ratio of Turbine Buildin

Column

e s'Excee

owa

es of

IS

Manua

The licensee

submitted

a 50.55(e) report

on December ll, 1978,

describing the actions

taken to correct the identified Turbine

Building column "depth-to-thickness ratio" deficiencies.

The inspector reviewed drawings

2277-S-V-E101

and

E102 and the

welding procedure

(WS-10) being used to weld the stiffeners to

the columns.

Twenty-six completed

welds were examined for com-

pliance with visual

acceptance

criteria of AWS D1.1-1975.

All

welds

examined

appeared

satisfactory.

The contractor

had noticed earlier what appeared

to be

a crack

in the weld termination areas

of the partial penetration

welds.

A nonconformance

report

(NCR No. 243)

was written documenting

the deficient weld areas.

The contractor

stated that this matter

would be resolved.

The welding and inspection records for

columns 10.6, 12.2,

14,

20 and 23.8 on the

A line were reviewed.

This review included Field Erection Inspection Sheets,

Welding

Electrode

Issuance

Records

and Welder gualifications.

No items

of noncompliance or deviations

were noted

and the inspector

had

no further questions

on this matter.

c. '"(Closed

Material Documentation Deficiencies in Small Structural

tee

S

a es

On December

13, 1978, the licensee

submitted written notification

of a discrepancy

reportable

under the provisions of 10 CFR 50.55(e).

This report identified that material certifications

and test re-

ports, associated

with small structural

steel

shapes

supplied

by

a local supplier,

were improper.

The licensee

had undertaken

an

extensive investigation to determine the adequacy of safety re-

lated materials

purchased

from that local supplier

by all site

contractors

and presented

the results of that investigation.

A

final 50.55(e) report was submitted

on January

31,

1979.

The

results of the investigation were examined

by the inspector.

The licensee's

investigations

appeared

to be comprehensive

and

adequate.

The licensee

had examined manufacturer's

certifications at the

original mill and conducted

physical

and chemical tests,

per-

formed by an independent

laboratory

and the licensee's

Department

of Engineering

Research,

on

31

samples of material for which

certifications were either questionable

or not available.

Of

the certifications

examined or obtained

by testing, only one

heat

number

was rejectable

(failed only the bend test).

The

material with that heat

number

was rejected

and replaced with

" conforming material.

This item is closed.

7.

Dedicated

Shutdown

Panel

a ~

Observation of Work and

Work Activities

The following completed

work was examined for compliance with

procedural

requirements.

(1)

Five installed circuits.

(2)

Three conduit supports

and

one conduit installation.

e

-9-

(3)

Dedicated

shutdown

panel

mounting.

No items of noncompliance

or deviations

were identified.

b.

Review of

ualit

Records

The following quality related

records

associated

with the above

work observations

were examined for compliance with procedural

requirements.

(1)

Conduit installation sheet

and raceway inspection report.

(2)

Circuit installation, termination

and insulation resistance

records.

(3)

Class

IE support inspection reports

and support installation

work sheets.

No items of noncompliance

or deviations

were identified.

8.

Arc Strike

Re air Pro ram

The )nspector

reviewed the arc strike repair program established

by Kellogg.

Engineering Specification

D-271,

Procedure for Removal

of Arc Strikes

and

Weld Splatter

on Piping and Components,

was re-

viewed for compliance with ASME Code Section XI, thru Summer

1978

Addenda.

At the time of the inspection,

the program was newly

implemented;

however, four Deficient Condition Notices

(DCN) had

been issued,

of which two were closed out.

DCNs 332-006

and 332-013,

and the related Field Process

Sheets,

Liquid Penetrant

Reports

and

Ultrasonic Test Reports

were reviewed for compliance with the repair

program requirements.

No items of noncompliance

or deviations

were noted.

9.

VSL Tendon

Rock Anchor

uglification

The inspector

reviewed the

VSL Report

on Turbine Pedestal

Test Anchors,

dated

December

15, 1978.

Documentation

reviewed included the material

certifications for tendon wire and the cement

used in grout; receiving

inspection reports; certificate of calibration for the hydraulic ram;

calculation of tendon elongations;

correlation of calculated

and meas-

ured extensions

in the test anchors

and calculation of the required

bond lengths

based

on the test anchor results.

PGSE

had documented

their review and approval of the test results for the turbine pedestal.

The

same testing

program would be used for the

VSL tendons to be

installed

on the outside vital tank enclosures.

No items of noncompliance

or deviations

were identified.

-10-

10.

Pi

e

Su

orts and Restraints

The inspector

reviewed the final walkdown inspection

program for

Unit

1 rupture restraints.

At present,

the program is approximately

50% complete for Unit 1.

The inspector selected

two rupture re-

straints,

5-6RR and 3-11RR, for examination to verify the effective-

ness of the final walkdown inspection.

The final walkdown and

documentation

review for rupture restraints identified several

unacceptable

items w'hich were documented

on the review record

and

on Deficient Condition Notice

(DCN) 43-58.

The

DCN stated that

weld

D of restraint 3-llRR was undersized.

The inspector visually

examined the weld, after repairs effected

by the

DCN were complete,

and noted that

some

base metal

had

been

removed.

The dimensions

of this area

were approximately

6 inches long, 3/8 inch wide and

extended

into the base

metal

approximately 1/16 inch.

A review

of the field process

sheet for weld

D repair .identified that the

weld had

been

accepted

by the Kellogg gC inspector

on December 7,

1978.

Discussions with licensee

personnel

indicated that the area

of base

metal

removal

was acceptable.

This item<is considered

unresolved

pending further review by the inspector.

(50-275/79-01-01)

The installation, settings

and quality records of the following

nine spring

hangers

in the Unit

1 containment

were examined.

S rin

Han er

1044-7V

52-12V

46-9V

52-23V

46-8Y

52-22V

51-24V

57N-90V

176-145Y

Size

(Load Ratin

14

7

3

12

6

12ll

4

13

A visual inspection of spring

hanger

46-9V indicated that

no lock

nuts were present

on either

end of the turnbuckle installed in the

hanger rod.

A review of the Support Final Inspection

Record veri-

fied that the missing lock nuts were identified by the

gC inspector

during the final inspection,

and recorded

as not being tight (as

required

by procedure

ESD-223, "Installation and Inspection of

Class

I Pipe Supports" ) in the locknut checkoff column.

The

gC

inspector failed to record the discrepancy

in the remarks

column

as required

by ESD-266,

"Final hlalkdown Inspection of Class

I Pipe

Supports,"

and signed off the support

as being acceptable.

Discus-

sions with licensee

and contractor

personnel

indicated that the

same

gC inspector

had questionable

inspection practices

in the past

and

that corrective action was in progress

to reinspect all work pre-

viously accepted

by that

gC Inspector.

The inspector

had

no

further questions

on this matter at that time.

As-Built Drawin

s and

En ineer

E ui ment Releases

12.'3.

'he

licensee's

design drafting department

had incorporated into drawings

62Ã of the Priority 1 as-built conditions received

from the field.

A

summary report was being issued

monthly to track completion of the

as-built documentation.

The licensee

was performing this activity as

required

by EDP-3.7, "As-Built Documents,"

and requires that all

Priority

1 as-built conditions

be completed prior to fuel lo'ading.

It appears

that actions to implement this commitment are adequate.

The licensee

stated that engineering

release

of components

and.

equipment would be completed prior to fuel loading.

Thirty-six

Unit

1 Engineering

Releases

remain to be completed

and adequate

controls appear to be implemented

to assure their completion.

No items of noncompliance or deviations

were identified.

gA Audits

The licensee's

internal audit system

was inspected

by examining

ten

gA audits

performed

since

November 9, 1978.

In the conduct of

these audits,

the licensee identified ten findings which required

corr'ective action.

The corrective actions

had

been initiated

and/or completed

in accordance

with the licensee's

nonconformance

reporting

system or open item resolution

system.

No items of non-

compliance or deviations

were identified.

Unresol ved

Items

Unresolved

items are matters

about which more information is required

in order to ascertain

whether they are acceptable

items,

items of non-

compliance,

or deviations.

One unresolved

item was identified during

this inspection

and is discussed

in Paragraph

10.

14.Exit'Interview

The inspectors

met with licensee

representatives

(denoted

in

Paragraph

1) at the conclusion of the inspections, on January

25,

1979,

and February 1, 1979,

and

summarized

the inspection

purpose,

scope

and findings.

The licensee

was informed of the unresolved

item and noted that the circumstances

would be evaluated.