ML16341A502

From kanterella
Jump to navigation Jump to search
Submits Guidance to Implement Review of Outstanding Allegations & Discusses Development of Work Plan on High Priority Basis
ML16341A502
Person / Time
Site: Diablo Canyon Pacific Gas & Electric icon.png
Issue date: 11/17/1983
From: Dircks W
NRC OFFICE OF THE EXECUTIVE DIRECTOR FOR OPERATIONS (EDO)
To: Harold Denton, Deyoung R, Martin J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V), NRC OFFICE OF INSPECTION & ENFORCEMENT (IE), Office of Nuclear Reactor Regulation
Shared Package
ML16341A501 List:
References
NUDOCS 8503200200
Download: ML16341A502 (4)


Text

1

'E November 17, 1983 MEMORANDUM fOR:

FROM:

SUBJECT:

John B. Martin, Regional Administrator, Region V

Harold R. Denton, Director, NRR Richard C. DeYoung, Director, IE William J. Dircks Executive Director for.Operations REVIEW OF"ALLEGATIONS OUTSTANDING ON DIABLO CANYON NUCLEAR POWER PLANT At the Commission.meeting of October 28, 1983, the staff was directed to pursue all outstanding allegations to resolution.

In addition, the

'ommission directed the staff to provide a sta'tus report "...addressing these matters,.;" prior to the authorization of-criticality and low power testing; I have designated Jack Martin, Region V, as having line responsibility for this activity.

T. Bishop has been further designated by Jack Martin to direct this effort.

He is charged with the responsibility to:

identify in 'coordination with NRR, IE and OI all outstanding allegations; 1

develop a work plan and schedule in concert with NRR and IE which will direct the effort of offices involved to pursue all allegations to conclusion;

. provide a coordinated status report to EDO approximately 10 days prior

'o Commission consideration of criticality and low power testing by

'Diablo Canyon; and produce a final report which will provide final conclusions on all outstanding allegations.

In the way of general

guidance, I would point out that it is necessary to begin development of a work plan on a high priority basis.

This plan should reflect a scoping and prioritization of allegations so that the required

. status report will be able to provide to the maximum extent feasi.ble, reasonable information to the Coenission on which they can make a

determination on Diablo Canyon in regard to criticality and low power licensing.

Completion of t'ne evaluation of all allegations must be acct.plished, but it is more important that they be reviewed correctly than that a particular completion time be met.

00 gg%12~2~5

-@0g2002

< 0g000 pg0 PD

~

~,

~

~

~

I expect all Offices involved to give full support to Hr. Bishop in this effort.

The OEDO should be contacted if problems develop or assitance is needed.

($igne5) Fiiham l. Oi,el%

CC:

B. Hayes G.