Forwards Guidance on Allegations & Staff Work Plan Developed to Implement Guidance
ML16341A500
Person / Time
Site: Diablo Canyon Pacific Gas & Electric icon.png
Issue date: 11/29/1983
From: Dircks W
NRC OFFICE OF THE EXECUTIVE DIRECTOR FOR OPERATIONS (EDO)
To: Gilinsky, Palladino, Roberts
NRC COMMISSION (OCM)
Shared Package
ML16341A501 List:
References
NUDOCS 8503200192
Download: ML16341A500 (2)


Text

November 29, 1983 tlEtlORANDUN FOR:

Chairman Palladino Commissioner Gilinsky.

Commissioner Roberts Commissioner Asselstine Commissioner Bernthal SROYi'.

SUBJECT:

William J. Dircks Executive Director for Operations PLANS FOR DEALING WITH ALLEGATIONS RELATING TO DIABLO CANYON

.Enclosed for your information is my guidance for dealing with the approximately 72 Diablo Canyon allegations and the staff work plan developed to implement that gui dance.

Action plans which assign staff and outline the approach to resolution have been developed for each allegation.

These detailed ~orksheets are available should any Commissioner desire to review them.

The initial on-site work will be conducted this week with approximately 17 staff assigned; Other related work has begun or wil.l begin.promptly..

The interim report will be provided to me by December 19 -

a date selected so as to.be approximately 10 days prior to the current estimate of the licensees criticality readiness.

I will provide it to you promptly after receipt.

Enclosure:

As stated (Sip,cl Villi-.7,.I..'.r".."s 0

William J. Dircks Executive Director for Operations cc:

OPE OGC Q~gQqi Qv tx om g/(> /es

~POD 8503200i92 83ii29 PDR ADOCK 05000275I P