ML16341A179

From kanterella
Jump to navigation Jump to search
Informs of Completion of Staff Evaluation of Const Status & Readiness for Power Ascension Testing & Full Power Operation.Summaries of Reviews & Assessments Which Contributed to Conclusion of Readiness Encl
ML16341A179
Person / Time
Site: Diablo Canyon Pacific Gas & Electric icon.png
Issue date: 07/20/1984
From: Bishop T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To: Eisenhut D
Office of Nuclear Reactor Regulation
Shared Package
ML16341A180 List:
References
MC-94300, NUDOCS 8408070531
Download: ML16341A179 (4)


Text

~Iea RE 0If, (4

P

~O 0

es o

jg**g4 MEMORANDUM FOR:

FROM:

UNITED STATES R

RIUCLEAR REGULATORY COMMISSlON REGION V 1450 MARIALANE,SUITE 210 WALNUtCREEK, CALIFORNIA94595

>~@>>

M

~ r

~ r

,heRI D eeee12 G. Ef sech nc

.Dfeecfcs, Disfsfon of Licensfng, NRR Thomas W. Bishop, Director Division of Reactor Safety and Pro)ects, RV

SUBJECT:

DIABLO CANYON UNIT NO.l (DN 50-275)

CONSTRUCTION STATUS AND OPERATIONAL READINESS REPORT (MC 94300)

The Region V staff's evaluation of Diablo Canyon Unit 1 readiness for power ascention testing and full'ower operation is complete.

Except as noted in Attachment 6 it is our conclusion that the plant systems have been properly accepted by the licensee, that requesite low power, testing has been satisfactorily performed, that the Regional inspection program is current, and that outstanding items are not of such significance to preclude full power operation.

Enclosed, for your information, are summaries of reviews and assessments which contributed to our conclusion of readiness:

a.

Overall Assessment (1)

Diablo Canyon Unit 1, Full Power License Review Panel Conciderations, dated June 19, 1984.

/E' Fi)EIp b.

Assurance of Construction ualit (1)

Summary of Installation Quality Verifications.

(2)

Summary of Licensee Quality Assurance Audits and Stop Work Orders since September 1981.

C ~

S ecial Reviews of 0 erational Readiness (1)

Special Team Inspection (50-275/84-07) of operating crews and management involvement during initial startup and low power testing, dated June 20, 1984.

(2)

Special Examination (50-275/84-07) of the training program for shift

advisors, dated Hay 25, 1984.

~.~>> ~gsa+

840807053i 840720 PDR ADOCK 05000275 P

'OR

As you are aware the staff's position on allegations and design quality are being addressed in separate Supplemental Safety Evaluation Reports.

Should you have comments or questions regarding the above please contact this office.

Coiprha( PypzJ $y 7:w 8<4fiop)

T. Q. Bishop, Director Division of Reactor Safety and Pro)ects, RV

Enclosures:

(1)

Diablo Canyon Unit 1, Full Power License Review Panel Considerations, June 19, 1984 (2)

Summary of Installation Quality Verifications (3)

Summary of Licensee Quality Assurance Audits and Stop Work Orders Since September 1981 (4)

Special Team Inspection Report 50-275/84-07, June 20, 1984 (5)

Special Examination Report 50-275/OL-84-02, May 25, 1984 (6)

Items Requiring Licensee Action Prior to Exceeding 5X Power cc w/enclosure:

J. B. Martin, RV R. DeYoung, IE:HQ G. Knighton, NRR D. Kirsch, RV P. Johnson, RV M. Mendonca, RV