Ack Receipt of Re Lack of Public Confidence in Emergency Planning & Impediments to Evacuation of Public Elements in Event of Nuclear Emergency.Statements Re Concerns Will Serve as Basis for Inquiry
ML16340E042
Person / Time
Site: Diablo Canyon  
Issue date: 12/02/1983
From: Martin J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To: Kranzdorf R
AFFILIATION NOT ASSIGNED
Shared Package
ML16340E043 List:
References
NUDOCS 8312200429
Download: ML16340E042 (6)


Text

December 2, 1983 Dr. Richard Kranzdorf, Spokesperson Concerned Cal Poly Faculty and Staff 160 Graves Avenue San Luis Obispo, California 93401

Dear Dr. Kranzdorf:

This is to acknowledge receipt of your letter of Novenber 4, 1983 to the Chairnan of the U. S. Nuclear Regulatory Commission and attachments

thereto, expressing concerns regarding a lack of public confidence in etn rgency planning for the Diablo Canyon Nuclear Power Plant and iaqediments to evacuation of elements of the public in the event of a nuclear etn rgency.

Thank you for the reasoned and documented statenant regarding your concerns.

They wi11 serve as a basis for inquiry, hopefully leading to a sound evaluation and resolution of these concerns.

Please be advised that we have provided copies of your correspond nce to the U. S. Federal Emergency ttanagetn nt Aoency (FEI1A), which has a specific assignment by Executive Order of the President to take the lead in'offsite radiological +urgency planning and response.

Me will work closely with FEHA, the State of California Office of Etn rg ncy Services, and cognizant local emergency services elements in evaluating and resolving your expressed concerns.

Please feel free to contact us if you wish to provid further data reflecting on your concerns or if we may answer any questions regarding our handling of the evaluation of your concerns.

Sincerely,

+~hn B. FFnrt1n Regional Administrator

/

gP~F PFFFT.

OFFICES

, 'URNAME/

DATE IF RYe ~

~ ~ ~ e ~ e

~ e ~ eeeee HcGueen eeoc

~ ~ e

~

~ ~ ~ ~ e ~ e l e

~

~ ~

~ ~ eee eee L. Norderha

~\\

~

~ ~ e

~

e

~ ~

J.

Ma tin

~ ee

~ ee ~ e

~

~ e

.12/...).....28.3.

...........ff'....

q Scarano ee ~ ee ~ ~

oooo'3.2/........1.83

'WC FOAM 318 O040) NACM 0340 OFFICIAL RECORD COPY USGFoo FBBF~QBO

l

~I

Allegation ATS.

No.

RV-83-A-0060 Characterization:

Lack of public confidence in feasibility of local emergency plans and impediments to public evacuation during an emergency.

Initial Assessment of Si nificance:

Substantiation of allega-tions could indicate that evacuation of the EPZ may not have been adequately evaluated, thus resulting in an inadequate emergen-cy plan finding by FEMA with potential adverse impact on the licensing of the DCNPP.

Source:

Letter from Dr. Richard Kranzdorf, as spokesperson for Concerned Cal Poly Faculty and Staff to NRC Chairman and Region V Administrator, 11/83 f

Approach to Resolution:

1.

Copy of correspondence provided to Region ZX, U.S.

Federal Emergency management Agency (FEMA).

2 ~

FEMA will provide copies of Kransdorf'orrespondence to State of California Office of Emergency Services and San Luis Obispo County Emergency Services Office.

3 0 Dr. Kranzdorf initially notified by letter that his correspondence was

received, is being evaluated, and that he will be notified of subsequent determinations pertain-ing thereto.

FEMA is arranging a conference for the week of December 5,

1983, for discussion and resolution of Kranzdorf allegations.

Participants to be NRC-RV, FEMA-IX, State of California Office of Emergency Ser-

vices, and local County officials.

i 5 ~

Coordinate closely 'ith FEMA to resolve the specific allegations

t 1

I

and alleged substantiation therefor.

6.

Formulate with FEMA a response to Dr.

Kranzdorf regarding resolution of his allegations, and if appropriate, continuing actions.

Status:

FEMA is coordinating meeting/conference for week of Dece=ber 5,

1983.

Review Lead:

Region V

~Su ort:

Region V - none presently envisioned.

FEMA-IX - not yet determined.

Estimated Resources:

Region V:

6 mandays (estimated)

FEMA-IX:

to be provided f'r and managed separately.

Estimated Com letion:

Interim:

12/12/83 Final:

Cannot yet be determined