ML16340A351
| ML16340A351 | |
| Person / Time | |
|---|---|
| Site: | Diablo Canyon |
| Issue date: | 12/13/1978 |
| From: | Sternberg D, Thomas Young NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V) |
| To: | |
| Shared Package | |
| ML16340A352 | List: |
| References | |
| 50-275-78-19, NUDOCS 7901250350 | |
| Download: ML16340A351 (8) | |
See also: IR 05000275/1978019
Text
U ~ S.
NUCLEAR REGULATORY CO>MISSION
OFFICE
OF INSPECTION AND ENFORCEMEVcf
.Report
No. 50"275/78"19
Docket No. 50-275
REGION V
License
No,
Safeguards
Group
Licens'ee:
Pacific
Gas
and Electric Company
77 Beale Street
San Francisco,
94106
Faci'Ii;ty Name.
Diablo Canyon Unit
1
Inspection at:
Diablo Canyon Site,
San Luis Obispo County, California
Inspection
conduc
d:
Nov mber 1-30,
1978
Inspectors:
T.
oung, Jr.,
Re
dent
R
cto
Inspector
Da
Signed
Date Signed
,Approved
By:
Summary:
D.
t1. Sternberg,
Chi
, Reactor
rojects
ection
Reactor Operations
and Nuclear Support
Branch
Date S'gned
3 7f
Date Signed
Ins ection on November
1-30,
1978
Re ort No. 50-275 78-19
P""P'"'"i"9
instrument calibration, preoperational
test program controls
and
QA/QC,
plant staff review committee activities, plant toui
and witnessing of
testing in progress.
This inspection
involved 152 inspector-hours
onsite
by one
NRC resident inspector.
Results:
No items of noncompliance
or deviations
were identified.
7eonso8s ~
RV Form 919 (9)
iC'> F'~
DETAILS
1.
Persons
Contacted
- R. D. Ramsay,
Plant Superintendent
R.
D. Etzler, Project Superintendent
R.
P.
klischow, Director, guality Assurance
- M. N. Norem,
Resident. Star tup Engineer
M.
E. Leppke,
gA Supervisor
- J. S.
Diamonon,
gC Supervisor
M.
W. Stephens,
ISC Foreman
- R. Patterson,
Supervisor of Operations
D. A. Backons,
Supervisor of Maintenance
- J. N. Gisclon,
Power Plant Engineer
The inspector also talked with and interviewed
a number of other
licensee
employees,
including members of general
construction,
the
operations staff and
gA organization
personnel.
- Denotes those attending
the exit interview.
~
~
2.
Preo erational Testin
Portions of the following tests
were witnessed
by the inspector:
5.4 - Flf Heater Drips and Level Control
23.3 - Preoperational
Testing of Auxiliary and
Fuel Handling
Buildings Ventilation
25.6 - Containment
Class
I Instrument Air Performance
Demon-
stration
28.6 - Energizing
480 Volt Switchgear
31.1.1 - Energizing
and Preoperational
Testing of Security
System Battery Charger
and Paralleling with Batteries
31.2 - Energizing
and Preoperational
Testing of Security
System
Power Inverter
1<hile witnessing
the above testing (in some tests
only parts of the
tests
were being performed or redone),
the inspector verified that
the procedures
were technically adequate;
the latest revisions
were
available
and approved;
the overall crew performance
was adequate
and, in the case of completed tests,
the acceptance criteria were
met.
Administrative controls for design
change
and documentation
were followed.
Ho items of noncompliance
or deviations
were identified.
Test Instrument Calibration
The test instrument calibration program
was
examined
by the in-
spector.
The inspector
found that the master calibration schedule
was being maintained
and that an instrument
usage
log was being
maintained.
A computerized
instrument calibration program has
been
developed
and implemented for planning
and scheduling
these activi-
ties.
Each month the
I8C department
receives
a computer listing of
all instruments
which come due during the month.
The listing also
identifies instruments
which are past due.
In addition, the supervisor receives
an
IBM card for each task on
the list.
This card is prepunched
to identify the'articular task
to which it applies.
llhen the task is actually performed,
the com-
pletion date is written on the card,
and the card is then fed back
into the computer
so that the machine
can update its lists.
No items of noncompliance
or deviations
were identified.
Prep erational
Test Pro
ram Controls
The inspector verified by record review and/or observation that (a)
~ jurisdictional controls were being observed for system turnover,
(b) tagging
was being accomplished
consistent with jurisdictional
controls of the administrative
procedures
and (c) controls were
being observed prior to and subsequent
to testing.
A schedule for
preoperational
testing is being maintained
and is as current
as
possible with the seismic
and security modification work in progress.
Ho items of noncompliance
or deviations
were identified.
Prep erational
Testin
A
The inspector
examined
one
QA and
one
QC audit report of an audit
conducted within the last three months.
The audits were conducted
in accordance
with approved
procedures
and corrective actions for
all discrepancies
had
been taken.
System turnover
from construc-
tion to the startup test group and to operations division was being
conducted
in accordance
with established
procedures
and administrative
controls.
Ho items of'oncompliance
or deviations
were identified.
Plant Staff Review Committee
PSRC
Records of the
PSRC were examined
and discussions
were held with
committee
members.
The
PSRC was found to be functional
and carrying
out its assigned responsibilities
per its charter.
The inspector
noted
some minor discrepancies
in functions
and
activities of the committee
as set forth in the charter
and the
proposed
technical specifications
(TS), e.g.,
the charter calls for
a quorum of the chairman
or his alternate
and'two
members
as stated
in the
FSAR.
The proposed
TS calls for a quorum of the chairman
or
his alternate
and four members.
These differences
were discussed
at the exit interview and
a licensee representative
stated that
these differences
were
known to the committee
and they were hopeful
that the proposed
TS would be changed
before licensing of the
plant.
iso items of noncompliance
or deviations
were identified.
7.
Plant. Tour
The inspector walked through various areas
of the plant on a weekly
basis to observe activities in progress;
to inspect the general
state of cleanliness,
housekeeping
and adherence
to fire protection
rules; to check the proper approval of "Man on the Line, Caution,
Information and Clearance"
tags
on equipment
and to review with
operators
the status of various
systems
in the plant.
The seismic modifications are approximately 75/ complete
and work
continues
in all areas.
The new security building is almost
com-
plete
and the security force is expected
to move in within the next
two weeks.
Housekeeping
in all areas is commensurate
with modifi-
cation work being done in that area.
No items of noncompliance
or deviations
were identified.
.8.
Exit Interview
The inspector
met with a senior
licensee
representative
on a weekly
basis
and with the representatives
(denoted in Paragraph
1) at the
conclusion of the inspection
on Oecember
1, 1978.'he
scope
and
findings of the inspection
were summarized
by the inspector.