GE-Hitachi Nuclear Energy - Supplement 1 to Proposed Resolution of Items #18b, 19 and 20 of NRC Suggested U.S. Advanced Boiling Water Reactor Design Changes
ML16299A147
Person / Time
Site: 05200045
Issue date: 10/25/2016
From: Head J
GE-Hitachi Nuclear Energy Americas
To:
Document Control Desk, Office of New Reactors
Shared Package
ML16299A146 List:
References
MFN 15-065, Suppl 1
Download: ML16299A147 (2)


Text

GE Hitachi Nuclear Energy Jerald G. Head Senior Vice President, Regulatory Affairs 3901 Castle Hayne Road PO Box 780 M/C A-18 Wilmington, NC 28402-0780 USA T 910 819 5692 F 910 362 5692 jerald.head@ge.com MFN 15-065, Supplement 1 Docket number: 52-045 October 25, 2016 US Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001

Subject:

Supplement 1 to GEH Proposed Resolution of Items # 18b, 19 and 20 of NRC Suggested U.S. Advanced Boiling Water Reactor Design Changes

References:

1. Letter from R.E. Kingston, GEH to USNRC,

Subject:

ABWR Standard Plant Design Certification Renewal Application Design Control Document, Revision 5, Tier 1 and Tier 2, December 7, 2010.

2. Letter from USNRC to Jerald G. Head, GEH,

Subject:

GE-Hitachi Nuclear Energy -

United States Advanced Boiling-Water Reactor Design Certification Renewal Application, July 20, 2012.

3. Letter from Jerald G. Head, GEH, to USNRC,

Subject:

Response to NRC Letter: GE Hitachi Nuclear Energy - United States Advanced Boiling-Water Reactor Design Certification Renewal Application (July 20, 2012), September 17, 2012.

4. Letter from Jerald G. Head, GEH to USNRC:

Subject:

GEH Proposed Resolution of Items # 18b, 19 and 20 of NRC Suggested U.S. Advanced Boiling Water Reactor Design Changes, August 11, 2015 GEH submitted a Design Certification Renewal application for the U.S. Advanced Boiling Water Reactor (ABWR) in Reference 1 pursuant to the requirements of Subpart B, Standard Design Certifications, of Title 10 of the Code of Federal Regulations (10 CFR) Part 52, Licenses, Certifications, and Approvals for Nuclear Power Plants.

In Reference 2, the NRC suggested design changes to address issues that the agency considered to be regulatory improvements or changes that could meet the 10 CFR 52.59(b) criteria. In addition, the NRC requested that GEH implement the Fukushima Near-Term Task

MFN 15-065, Supplement 1 Page 2 of 2 Force recommendations contained in SECY-12-0025, Proposed Orders and Requests for Information in Response to Lessons Learned from Japans March 11, 2011, Great Tohoku Earthquake and Tsunami, dated February 17, 2012. Collectively, these items are termed the 28-item backfit list.

In Reference 3, GEH responded to Reference 2 and committed to address the 28-item backfit list.

In public and private meetings the NRC held with GEH on May 7th, 2015, GEH reviewed the closure plan for the 28-item backfit list for those items that GEH would not receive any additional Requests for Additional Information. During that meeting, the following items of the 28-item backfit list were discussed and GEHs approach was found to be acceptable by the staff: Item #18b - Structural, dynamic and impact analysis of new and spent fuel racks, Item #19

- Thermal hydraulic analysis of the spent fuel racks and Item #20 - Criticality analyses of new and spent fuel storage racks.

In Reference 4, GEHs proposed resolution to Items #18b, 19 and 20 of the 28-item backfit list transmitted in Reference 2 was submitted to the NRC. In Reference 4, GEH committed to deletion of the new fuel storage vault. During recent review the ABWR DCD Chapter 16 -

Technical Specifications, it was determined that deletion of the new fuel storage vault Design Features from Technical Specifications (TS) and from the Secondary Containment Control Guideline were not included in the previous markups in Reference 4. contains a summary of the ABWR DCD changes as a result of this supplement as well as the impact on the ABWR DCD. Enclosure 2 contains the ABWR DCD Draft Rev 7 markups.

If you have any questions concerning this letter, please contact Hugh Upton at 408-314-8499.

Sincerely, Jerald G. Head Senior Vice President, Regulatory Affairs Commitments: No additional commitments are made in this response.

Enclosures:

1. MFN 15-065, Supplement 1 - GEH Summary of Changes
2. GEH ABWR DCD Draft Revision 7 Markups cc: Adrian Muniz, NRC DBR - 0012230