Text

v0, REG,,et 0

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D. C. 20555 November 5, 1979 MEMORANDUM FOR: D. Ross, Director Bulletins and Orders Task Force FROM:

Darrell G. Eisenhut, Acting Director Division of Operating Reactors

SUBJECT:

LICENSING ACTIONS RELATED TO BULLETINS AND ORDERS A number of licensing actions and plant modification approvals have resulted from the activities of the Bulletins and Orders Group. A significant number of these have not yet been acted on pending completion of the review and pre paration of the necessary safety evaluations by the Bulletins and Orders (B&O)

Group. In view of the priority of other work within the B&O Group and in con sideration of the expected limited life of the B&O Group, it appears appropriate to consider whether the B&O Group will be able to complete all of these items, or whether DOR will fall heir to completing some of these items. If this appears to be the case; we should attempt to define, as early as possible, which items DOR will need to complete so that it can be factored into our overall workload planning.

A listing of the outstanding action items for Oconee is attached for use. This list is typical of all licensees of B&W vended plants. The list does not include completion of the response to Bulletins 79-05, 79-06, and 79-08. It also does not include the resolution of the question of whether the small break studies, which have been conducted by B&O, affect the determination of compliance with 50.46 or whether any changes in currently approved ECCS models should be made.

It is assumed that this question will be resolved by B&O before it goes out of business.

As soon as you have reviewed the current backlog of the B&O Group, we are prepared to meet with you to discuss cha ges in assignments.

Darrell G. Elsenhut, ting Director Division of Operating Reactors

Attachment:

Licensing Action Status for Oconee cc: w/attachment R. Vollmer W. Gammill W. Russell R. Ingram B. Grimes J. R. Miller R. Reid L. Shao T. J. Carter M. Fairtile 7911280 2 q )

Attachment OCONEE STATION LICENSING ACTION STATUS BULLETINS & ORDERS ITEMS ITEM STATUS T.S. changes related to revised relief valve Submitted 5/21/79. Need settings and reactor coolant high pressure trip.

Questions & subsequent S.E.

T.S. changes for Emergency F.W. system required Submitted 5/21/79. Preparing by May 7,.1979 Order and review.of EFW plant S.E. & Concurrently reviewing modifications.

T.S. Submittal.

Review of Safety Grade Anticipatory Trips Duke responded on 10/5/79 to Note:

Duke will not start procurement until NRC 9/7/79 request for design approval issued by NRC.

additional information. Need S.E.

Long Term Generic Issues related to Duke responded on 10/5/79 to May 7, 1979 Order.

all but one question of NRC's 9/21/79 requests. Needs review.

Review of Responses to IE Bulletin 79-05C.

Submitted by Duke 9/14/79 Needs review.

Review of ECCS modeling techniques used in Submitted by Duke 9/13/79.

small break analysis.

Needs review.