ONS-2016-062, Transmittal of Oconee Nuclear Station, Units 1, 2, and 3 - Independent Spent Fuel Storage Installation - Updated Final Safety Analysis Report, Revision 25
ML16195A383 | |
Person / Time | |
---|---|
Site: | Oconee |
Issue date: | 06/30/2016 |
From: | Batson S L Duke Energy Carolinas |
To: | Document Control Desk, Office of Nuclear Material Safety and Safeguards |
References | |
ONS-2016-062 | |
Download: ML16195A383 (12) | |
Text
ENERGY ONS-2016-062 June 30, 2016 ATTN: Document Control Desk Director, Division of Spent Fuel Storage Office of Nuclear Material Safety and Safeguards U.S. Nuclear Regulatory Commission
' Washington, DD 20555-0001
Subject:
Duke Energy Carolinas, (LLC) (Duke Energy) Oconee Nuclear Station, Units 1, 2, and 3 Docket Nos. 72-4, 50-269, 50-270, 50-287 Independent Spent Fuel Storage Installation Updated Final Safety Analysis Report, Revision 25 Scott L. Batson Vice President Oconee Nuclear Station Duke Energy ON01VP I 7800 Rochester Hwy Seneca, SC 29672 o: 864.873.3274
- f. 864.873.4208 Scott.Batson@duke-energy.com 10 CFR 72.4 10 CFR 72.48 10 CFR 72.70 Pursuant to 10 CFR 72.48 ( d)(2), and in accordance with 10 CFR 72. 70 and 10 CFR 72.4, Duke Energy hereby submits the Oconee Nuclear Station (ONS) Independent Spent Fuel Storage Installation (ISFSI) Updated Final Safety Analysis Report (UFSAR), Revision 25. The effective date of the revision is December 31, 2015, as indicated at the bottom of each page. There were no changes made to the Oconee ISFSI UFSAR in Revision 25. The ONS ISFSI UFSAR, Revision 25, is enclosed on one compact disk (CD). The contents are in Adobe Acrobat Portable Document Format (pdf). As required by NRC guidance for electronic submissions, Attachment 1 provides a listing of the document components that comprise the enclosed CD. Attachment 2 provides the List of Effective Pages (LOEP) for Tables and Figures. Attachment 3 provides insertion instructions for those receiving hardcopy distribution.
Attachment 4 provides the report of changes, tests, and experiments performed pursuant to 10 CFR 72.48. This submittal document contains no new or revised regulatory commitments.
If you have any questions regarding this submittal, please contact Kay Brocklesby at (864) 873-6661.
I declare under penalty of perjury that the foregoing is true and correct. Executed on June 30, 2016. Sincerely, Scott L. Batson Vice President Oconee Nuclear Station www.duke-energy.com ONS-2016-062 Document Control Desk June 30, 2016 Page 2 Attachments:
- 1. Document Components on CD 2. List of Effective Pages (LOEP) for Tables and Figures 3. Insertion Instructions (for hardcopy distribution only) 4. 10 CFR 72.48 Report
Enclosure:
CD: Oconee Nuclear Station Independent Spent Fuel Storage Installation, 2015 Update -Rev 25 xc: Ms. Catherine Haney, NRC Region II Administrator (CD) U.S. Nuclear Regulatory Commission Marquis One Tower 245 Peachtree Center Ave., NE, Suite 1200 Atlanta, GA 30303-1257 Mr. James R. Hall, Project Manager (CD) U.S. Nuclear Regulatory Commission 11555 Rockville Pike Mail Stop 0-8G9A Rockville, MD 20852 Mr. Eddy Crowe (hardcopy)
Senior Resident Inspector Oconee Nuclear Station ONS-2016-062 Document Control Desk June 30, 2016 Attachment 1 Attachment 1 Document Components on CD (1 page attached)
ONS-2016-062 Document Control Desk June 30, 2016 Attachment 1 Filename 001 ONS ISFSI Rev 25 Title Page 001 ONS ISFSI Rev 25 Text 002 ONS ISFSI Rev 25 Tables 003 ONS ISFSI Rev 25 Figures File Size 57 KB 1,632 KB 1,256 KB 25,284 KB ONS-2016-062 Document Control Desk June 30, 2016 Attachment 2 Attachment 2 List of Effective Pages (LOEP) for Tables and Figures (3 pages attached)
ONS-2016-062 Document Control Desk June 30, 2016 Attachment 2 OCONEE ISFSI UFSAR-2014 UPDATE List of Effective Pages (LOEP) for Table and Figures The purpose of this list is to assure that the pages in the Tables and Figures section of your manual match the most recent issue, as well as to show a full accounting of all tables and figures, including those that have been deleted. The earliest effective date, 12/31/07, was used when all tables and figures were re-issued.
Effective Table Table Title Date No. 12/31/07 A-1 Design Parameters for the Oconee ISFSI 12/31/07 A-2 Summary of ISFSI Fuel Handling Operations 12/31/07 A-3 Primary Design Parameters for the ISFSI Transport Systems 12/31/07 A-4 Major Systems, Subsystems, and Components of the Oconee ISFSI 12/31/07 A-5 Population Growth in Oconee, Pickens, and Anderson Counties, South Carolina (1980-2005) 12/31/07 A-6 Population Projections for Oconee, Pickens, and Anderson Counties, South Carolina (2010-2050) 12/31/07 A-7 Joint Frequencies of Wind Direction and Speed by Stability Class 12/31/07 A-8 Soil Permeability Test Results 12/31/07 A-9 Significant Earthquakes in the Southeast United States (Intensity V or Greater) 12/31/07 A-10 Physical Characteristics of PWR Fuel Assemblies Based on Nominal Design 12/31/07 A-11 Transfer Cask Stress Analysis for Tornado Effects 12/31/07 A-12 Oconee ISFSI Major Components and Functions 12/31/07 A-13 Oconee ISFSI Radioactive Material Confinement Barriers 12/31/07 A-14 Oconee ISFSI Major Components and Design Requirements 12/31/07 A-15 ONS ISFSI Project Transfer Trailer Design Parameters 12/31/07 A-16 Oconee ISFSI Major Components and Classification 12/31/07 A-17 Gamma Energy Spectrum 12/31/07 A-18 Shielding Analysis Results 12/31/07 A-19 Summary of Estimated On-site Doses Resulting from ISFSI Operations (Per DSC Transfer to HSM) 12/31/07 A-20 Dose Estimate for Construction of Additional Horizontal Storage Modules Based on Labor Estimates for 2 X 10 Array 12/31/07 A-21 Neutron and Gamma Energy Spectrum 12/31/07 A-22 Comparison of Total Dose Rates for HSM With and Without Air Outlet Shielding Blocks 12/31/07 A-23 Cask Drop Target Parameters ONS-2016-062 Document Control Desk June 30, 2016 Attachment 2 Effective Figure Date No. 12/31/07 B-1 12/31/07 B-2 12/31/07 B-3 12/31/07 B-4 12/31/07 B-5 12/31/07 B-6 12/31/07 B-7 12/31/07 B-8 12/31/07 B-9 12/31/07 B-10 12/31/07 B-11 12/31/07 B-12 12/31/07 B-13 12/31/07 B-14 12/31/07 B-15 12/31/07 B-16 12/31/07 B-17 12/31/07 B-18 12/31/07 B-19 12/31/07 B-20 12/31/07 B-21 12/31/07 B-22 12/31/07 B-23 12/31/07 B-24 12/31/07 B-25 12/31/07 B-26 12/31/07 B-27 12/31/07 B-28 12/31/07 B-29 12/31/07 B-30 Figure Title Location of ISFSI General Location Site Plan ISFSI Layout Topography Within 5 Miles Relative Positions of Meteorological Instruments Relative Elevations of Meteorological Instruments Areal Groundwater Survey Groundwater Survey at Station Site Well Permeameter Test Apparatus Formulae for Determining Permeability General Site Area Site Boring Plan Core Boring Record Core Boring Record Core Boring Record Core Boring Record Core Boring Record Core Boring Record Core Boring Record Core Boring Record Core Boring Record Core Boring Record Core Boring Record Core Boring Record Core Boring Record Core Boring Record ISFSI Foundation Profile Site Layout and Route Site Plan ONS-2016-062
- Document Control Desk June 30, 2016 Attachment 2 Effective Figure Date No. 12/31/07 B-31 12/31/07 B-32 12/31/07 B-33 12/31/07 B-34 12/31/07 B-35 12/31/07 B-36 12/31/07 B-37 12/31/07 B-38 12/31/07 B-39 12/31/07 B-40 12/31/07 B-41 12/31/07 B-42 12/31/07 B-43 12/31/07 B-44 12/31/07 B-45 12/31/07 B-46 12/31/07 B-47 12/31/07 B-48 Figure Title Transfer Cask Lifting Yoke Transfer Cask Lift Extension Spent Fuel Pool Area Spent Fuel Pool Area Spent Fuel Pool Area NUHOMS System Loading Operations Flowchart NUHOMS System Loading Operations Flowchart NUHOMS System Loading Operations Flowchart NUHOMS System Loading Operations Flowchart NUHOMS System Loading Operations Flowchart NUHOMS System Loading Operations Flowchart Location of Dose Rates Dose Rate Versus Distance From Surface of HSM Dose From Filled HSM Array Dose From Filled HSM Array Radiation Zone Map of Modules Surface Dose Rates Deleted Per 1991 Update Fuel Assembly Burnup Requirements ONS-2016-062 Document Control Desk June 30, 2016 Attachment 3 Attachment 3 Insertion Instructions (for hardcopy distribution only) (1 page attached)
ONS-2016-062 Document Control Desk June 30, 2016 Attachment 3 Insertion Instructions (for hardcopy distribution only) 1. Replace List of Effective Pages (LOEP) for Tables and Figures with the 2015 LOEP Update. 2. Replace entire text portions with the updated text portion (including the List of Abbreviations, Table of Contents, List of Tables, and List of Figures.)
- 3. Update Tables and Figures according to the following instructions.
NOTE: There were no Tables or Figures updated during this revision.
ONS-2016-062 Document Control Desk June 30, 2016 Attachment 4 Attachment 4 10 CFR 72.48 Report (1 page attached)
ONS-2016-062 Document Control Desk June 30, 2016 Attachment 4 Oconee Nuclear Station hereby informs the Nuclear Regulatory Commission that no changes, tests or experiments were made under the provisions of 10 CFR 72.48 between January 1, 2015 and December 31, 2015.