200 Exelon Way Exelon Generation Kennett Square. PA 19348 www.exeloncorp.com 10 CFR 50.55a July 12, 2016 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001 Limerick Generating Station, Units 1 and 2 Renewed Facility Operating License Nos. DPR-39 and DPR-85 NRC Docket Nos. 50-352 and 50-353
Subject:
Response to Request for Additional Information Regarding Proposed Relief Request 14R-10 for Limerick Generating Station, Units 1 and 2
References:
- 1) Letter from D. P. Helker (Exelon Generation Company, LLC) to the U.S.
Nuclear Regulatory Commission, "Submittal of Relief Requests associated with the Fourth 10-Year Interval lnservice Inspection (ISi)
Program," dated April 13, 2016(ML16104A122).
- 2) E-mail correspondence from R. Ennis (U.S. Nuclear Regulatory Commission) to S. J. Hanson (Exelon Generation Company, LLC),
"Draft Request for Additional Information Regarding Proposed Relief Request 14R-10 for Limerick Generating Station, Units 1 and 2 (ML16174A298)," dated June 22, 2016.
By letter dated April 13, 2016, Exelon Generation Company, LLC (Exelon) submitted relief requests associated with the Fourth 10-Year lnservice Inspection Interval for Limerick Generating Station (LGS), Units 1 and 2. Specifically, Exelon submitted requests 14R-01, 14R-02, 14R-05, 14R-06, 14R-07, 14R-08, 14R-09, 14R-10, 14R-11, 14R-12, and 14R-13.
In the Reference 2 e-mail correspondence, the U.S. Nuclear Regulatory Commission (NRC) requested additional information relating to Relief Request 14R-10. The attached contains Exelon's response to the NRC request for additional information.
Response to Request for Additional Information Proposed Relief Request 14R-1 O July 12, 2016 Page 2 There are no regulatory commitments in this response.
If you have any questions concerning this response, please contact Stephanie J. Hanson at 610-765-5143.
Respectfully, James Barstow Director, Licensing and Regulatory Affairs Exelon Generation Company, LLC
Attachment:
Response to Draft Request for Additional Information Regarding Proposed Relief Request 14R-1 O for Limerick Generating Station, Units 1 and 2 cc:
USNRC Region I, Regional Administrator USNRC Senior Resident Inspector, LGS USNRC Project Manager, LGS R. R. Janati, Pennsylvania Bureau of Radiation Protection
ATTACHMENT Limerick Generating Station, Units 1 and 2 Renewed Facility Operating License Nos. DPR-39 and DPR-85 Docket Nos. 50-352 and 50-353 Response to Draft Request for Additional Information Regarding Proposed Relief Request Concerning 14R-10
Response to Draft Request for Additional Information Attachment Proposed Relief Request I4R-10 Page 1 of 3 Docket Nos. 50-352 and 50-353 By letter dated April 13, 2016, Exelon Generation Company, LLC (Exelon) submitted relief requests associated with the Fourth 10-Year Inservice Inspection Interval for Limerick Generating Station (LGS), Units 1 and 2. Specifically, Exelon submitted requests I4R-01, I4R-02, I4R-05, I4R-06, I4R-07, I4R-08, I4R-09, I4R-10, I4R-11, I4R-12, and I4R-13.
The NRC staff has determined that additional information is needed to complete its review. On June 22, 2016, the NRC issued a draft request for additional information (RAI). This RAI supersedes a previous draft RAI sent to Exelon on June 14, 2016 (ML16166A086), regarding Relief Requests I4R-02 and I4R-10. Specifically, question EVIB-RAI-1 involving I4R-02 has been deleted since Exelon has identified that the requested information was previously docketed in a number of inservice inspection summary reports.
The RAI is restated below along with Exelon's response.
EVIB-RAI-2:
Relief request I4R-10 proposes an alternative to the requirements of the ASME Code,Section XI, Table IWB-2500-1, concerning nozzle-to-vessel weld and nozzle inner radii examination requirements.
- a. Please provide information related to the inspections that have already been performed on the components for which this alternative is requested. In addition, include all indications that were found and how these indications were dispositioned. If no indications were found during any inspections, please state so.
- b. Please provide information regarding the extent of inspection coverage that was obtained to date for nozzle-to-vessel welds and nozzle inner radii at LGS, Units 1 and 2.
Response
The tables below provide information related to the inspections performed, inspection results, and extent of inspection coverage obtained during the third inspection interval for the nozzle-to-vessel welds and nozzle inside radius section exams covered by Relief Request I4R-10 at Limerick Generating Station, Units 1 and 2.
Response to Draft Request for Additional Information Attachment Proposed Relief Request I4R-10 Page 2 of 3 Docket Nos. 50-352 and 50-353 Summary# ComponentID Description LastInspected CoverageObtained Indications Comments 600700 N2A NozzletoVessel 1R12(2008) 76%
NRI noindicationsfound 600710 N2AIR NozzleInnerRadius 1R12(2008) 100%
NRI noindicationsfound 600730 N2B NozzletoVessel
no3rdintervalinspection 600740 N2BIR NozzleInnerRadius
no3rdintervalinspection 600760 N2C NozzletoVessel 1R15(2014) essentially100%
NRI noindicationsfound 600770 N2CIR NozzleInnerRadius 1R15(2014) 100%
NRI noindicationsfound 600790 N2D NozzletoVessel
no3rdintervalinspection 600800 N2DIR NozzleInnerRadius
no3rdintervalinspection 600820 N2E NozzletoVessel
no3rdintervalinspection 600830 N2EIR NozzleInnerRadius
no3rdintervalinspection 600850 N2F NozzletoVessel 1R12(2008) 76%
NRI noindicationsfound 600860 N2FIR NozzleInnerRadius 1R12(2008) 100%
NRI noindicationsfound 600800 N2G NozzletoVessel
no3rdintervalinspection 600890 N2GIR NozzleInnerRadius
no3rdintervalinspection 600910 N2H NozzletoVessel
no3rdintervalinspection 600920 N2HIR NozzleInnerRadius
no3rdintervalinspection 600940 N2J NozzletoVessel
no3rdintervalinspection 600950 N2JIR NozzleInnerRadius
no3rdintervalinspection 600970 N2K NozzletoVessel
no3rdintervalinspection 600990 N2KIR NozzleInnerRadius
no3rdintervalinspection 601000 N3A NozzletoVessel
no3rdintervalinspection 601010 N3AIR NozzleInnerRadius
no3rdintervalinspection 601030 N3B NozzletoVessel
no3rdintervalinspection 601040 N3BIR NozzleInnerRadius
no3rdintervalinspection 601060 N3C NozzletoVessel
no3rdintervalinspection 601070 N3CIR NozzleInnerRadius
no3rdintervalinspection 601090 N3D NozzletoVessel 1R12(2008) 75.1%
NRI noindicationsfound 601100 N3DIR NozzleInnerRadius 1R12(2008) 100%
NRI noindicationsfound 601300 N5A NozzletoVessel 1R12(2008) 77.6%
NRI noindicationsfound 601310 N5AIR NozzleInnerRadius 1R12(2008) 100%
NRI noindicationsfound 601330 N5B NozzletoVessel 1R12(2008) 77.6%
NRI noindicationsfound 601340 N5BIR NozzleInnerRadius 1R12(2008) 100%
NRI noindicationsfound 601360 N6A NozzletoVessel
no3rdintervalinspection 601370 N6AIR NozzleInnerRadius
no3rdintervalinspection 601380 N6B NozzletoVessel
no3rdintervalinspection 601390 N6BIR NozzleInnerRadius
no3rdintervalinspection 601400 N7 NozzletoVessel 1R16(2016) essentially100%
NRI noindicationsfound 601410 N7IR NozzleInnerRadius 1R16(2016) 100%
NRI noindicationsfound 601420 N8A NozzletoVessel
no3rdintervalinspection 601420 N8AIR NozzleInnerRadius
no3rdintervalinspection 601440 N8B NozzletoVessel 1R15(2014) essentially100%
NRI noindicationsfound 601450 N8BIR NozzleInnerRadius 1R15(2014) 100%
NRI noindicationsfound 601490 N17A NozzletoVessel
no3rdintervalinspection 601500 N17AIR NozzleInnerRadius
no3rdintervalinspection 601520 N17B NozzletoVessel 1R12(2008) 77.6%
NRI noindicationsfound 601530 N17BIR NozzleInnerRadius 1R12(2008) 100%
NRI noindicationsfound 601550 N17C NozzletoVessel
no3rdintervalinspection 501560 N17CIR NozzleInnerRadius
no3rdintervalinspection 601580 N17D NozzletoVessel
no3rdintervalinspection 601590 N17DIR NozzleInnerRadius
no3rdintervalinspection LimerickGeneratingStationUnit1
- NRInorecordableindications
Response to Draft Request for Additional Information Attachment Proposed Relief Request I4R-10 Page 3 of 3 Docket Nos. 50-352 and 50-353 Summary# ComponentID Description LastInspected CoverageObtained Indications Comments N2A NozzletoVessel 2R10(2009) 83.7%
NRI noindicationsfound N2AIR NozzleInnerRadius 2R10(2009) 100%
NRI noindicationsfound N2B NozzletoVessel 2R12(2013) essentially100%
NRI noindicationsfound N2BIR NozzleInnerRadius 2R12(2013) 100%
NRI noindicationsfound N2C NozzletoVessel
no3rdintervalinspection N2CIR NozzleInnerRadius
no3rdintervalinspection N2D NozzletoVessel 2R10(2009) 79.9%
NRI noindicationsfound N2DIR NozzleInnerRadius 2R10(2009) 100%
NRI noindicationsfound N2E NozzletoVessel
no3rdintervalinspection N2EIR NozzleInnerRadius
no3rdintervalinspection N2F NozzletoVessel 2R12(2013) essentially100%
NRI noindicationsfound N2FIR NozzleInnerRadius 2R12(2013) 100%
NRI noindicationsfound N2G NozzletoVessel
no3rdintervalinspection N2GIR NozzleInnerRadius
no3rdintervalinspection N2H NozzletoVessel 2R09(2007) 80%
NRI noindicationsfound N2HIR NozzleInnerRadius 2R09(2007) 100%
NRI noindicationsfound N2J NozzletoVessel 2R09(2007) 80%
NRI noindicationsfound N2JIR NozzleInnerRadius 2R09(2007) 100%
NRI noindicationsfound N2K NozzletoVessel 2R10(2009) 80.3%
NRI noindicationsfound N2KIR NozzleInnerRadius 2R10(2009) 100%
NRI noindicationsfound N3A NozzletoVessel
no3rdintervalinspection N3AIR NozzleInnerRadius
no3rdintervalinspection N3B NozzletoVessel 2R11(2011) essentially100%
NRI noindicationsfound N3BIR NozzleInnerRadius 2R11(2011) 100%
NRI noindicationsfound N3C NozzletoVessel 2R09(2007) 82%
NRI noindicationsfound N3CIR NozzleInnerRadius 2R09(2007) 100%
NRI noindicationsfound N3D NozzletoVessel 2R09(2007) 82%
NRI noindicationsfound N3DIR NozzleInnerRadius 2R09(2007) 100%
NRI noindicationsfound N5A NozzletoVessel
no3rdintervalinspection N5AIR NozzleInnerRadius
no3rdintervalinspection N5B NozzletoVessel 2R09(2007) 85%
NRI noindicationsfound N5BIR NozzleInnerRadius 2R09(2007) 100%
NRI noindicationsfound N6A NozzletoVessel
no3rdintervalinspection N6AIR NozzleInnerRadius
no3rdintervalinspection N6B NozzletoVessel
no3rdintervalinspection N6BIR NozzleInnerRadius
no3rdintervalinspection N7 NozzletoVessel 2R13(2015) essentially100%
NRI noindicationsfound N7IR NozzleInnerRadius 2R13(2015) 100%
NRI noindicationsfound N8A NozzletoVessel 2R10(2009) 83.7%
NRI noindicationsfound N8AIR NozzleInnerRadius 2R10(2009) 100%
NRI noindicationsfound N8B NozzletoVessel 2R10(2009) 83.7%
NRI noindicationsfound N8BIR NozzleInnerRadius 2R10(2009) 100%
NRI noindicationsfound N17A NozzletoVessel
no3rdintervalinspection N17AIR NozzleInnerRadius
no3rdintervalinspection N17B NozzletoVessel 2R10(2009) 81.8%
NRI noindicationsfound N17BIR NozzleInnerRadius 2R10(2009) 100%
NRI noindicationsfound N17C NozzletoVessel
no3rdintervalinspection N17CIR NozzleInnerRadius
no3rdintervalinspection N17D NozzletoVessel 2R09(2007) 84%
NRI noindicationsfound N17DIR NozzleInnerRadius 2R09(2007) 100%
NRI noindicationsfound LimerickGeneratingStationUnit2
- NRInorecordableindications