ML16187A235

From kanterella
Jump to navigation Jump to search
Notification of Inspection and Request for Information
ML16187A235
Person / Time
Site: Watts Bar  Tennessee Valley Authority icon.png
Issue date: 07/01/2016
From: Sandra Walker
NRC/RGN-II/DRS/EB3
To: James Shea
Tennessee Valley Authority
References
Download: ML16187A235 (7)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 July 1, 2016 Mr. Joseph W. Shea Vice President, Nuclear Licensing Tennessee Valley Authority 1101 Market Street, LP 3R Chattanooga, TN 37402-2801

SUBJECT:

WATTS BAR NUCLEAR PLANT - NOTIFICATION OF INSPECTION AND REQUEST FOR INFORMATION

Dear Mr. Shea:

From July 26 through September 24, 2016, the U.S. Nuclear Regulatory Commission (NRC) will perform an inspection of the independent spent fuel storage installation (ISFSI) Dry Run and Initial Loading activities at the Watts Bar Nuclear Plant using NRC Inspection Procedures 60854, 60855, 60856, and 60857. Experience has shown that this inspection is resource-intensive both for the NRC inspectors and your staff. In order to minimize the impact to your onsite resources and to ensure a productive inspection, we have enclosed a request for documents needed for this inspection. These documents identify the information which the inspectors will need upon arrival at the site. It is important that all of these documents are up-to-date, and complete, in order to minimize the number of additional documents requested during the preparation, and/or the onsite portions of the inspection.

We have discussed the schedule for these inspection activities with your staff, and understand that our regulatory contact for this inspection will be Mr. Russell Stroud of your licensing organization. Our inspection dates are subject to change based on changes to your schedule for ISFSI activities. If there are any questions about this inspection or the material requested, please contact the lead inspector, Robert Carrion, at 404-997-4522 (Robert.Carrion@nrc.gov).

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public inspections, exemptions, requests for withholding, of the NRCs Agency Rules of Practice and Procedure, a copy of this letter, and its Enclosure, will be available electronically for public inspection in the NRC Public Document Room, or from the Publicly Available Records (PARS)

J. Shea 2 component of NRC's Agencywide Documents Access and Management System (ADAMS);

accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Shakur A. Walker, Chief Engineering Branch 3 Division of Reactor Safety Docket Nos. 050-390, 050-391, and 072-1048 License Nos. NPF-90 and NPF-96

Enclosure:

Pre-Inspection Document Request cc: Distribution via Listserv

SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII:DRS/EB3 RII:DRS/EB3 SIGNATURE RPC1 SAW4 NAME R. Carrion S. Walker DATE 6/ 30 /2016 7/1/2016 E-MAIL COPY YES NO YES NO PRE-INSPECTION DOCUMENT REQUEST Inspection Dates:

July 26-28, 2016 (Tuesday - Thursday)

MPC Fluid Ops and Cask Drying Operations - Dry Run August 8-12, 2016 (Monday-Friday)

Inspection of Upgraded Auxiliary Building Crane August 30-31, 2016 (Tuesday - Wednesday) - TEAM INSPECTION Outside Pad Operations - Dry Run September 14-15, 2016 (Wednesday - Thursday)

Wet Operations - Dry Run September 19-September 24, 2016 (Monday - Saturday)

Initial Loading Campaign Dry Run Demonstration Inspection Procedures:

IP 60854, Preoperational Testing of an Independent Spent Fuel Storage Installation IP 60856, Review of 10 CFR 72.212(b) Evaluations IP 60857, Review of 10 CFR 72.48 Evaluations Initial Loading Campaign:

IP 60855, Operation of an Independent Spent Fuel Storage Installation A. Information Requested for the In-Office Preparation Week The following information should be made available to the Region II office by July 15, 2016, to facilitate the selection of specific items that will be reviewed during the onsite inspection weeks. The inspectors will select specific items from the information requested and then request from your staff additional documents needed during the onsite inspection weeks (Section B of this Enclosure). We ask that the specific items selected from the lists be available and ready for review on the first day of inspection.

Please provide requested documentation via your SharePoint web site, if possible. If the requested documents are large and/or only hard copy formats are available, please inform the lead inspector, Robert Carrion, and provide the subject documentation during the first day of the onsite inspection. We understand that any proprietary information reviewed by the inspectors will be appropriately protected against being released to the public. If you have any questions regarding this information request, please call Robert Carrion, as soon as possible.

Enclosure

2 Updated Schedules for Independent Spent Fuel Storage Installation Activities Procedures and Programs

  • Leak Testing Procedure for Canister
  • Transient Combustible and Flammable Substances Program ISFSI-Related Evaluations
  • Fire Hazards Evaluation for ISFSI Cask Hauling and Storage
  • Explosion Hazards Evaluations for the ISFSI Cask Hauling and Storage
  • Cask Transport Path Evaluation of Buried Components
  • 50.59 Evaluations for cask system use
  • 72.212 Evaluation
  • 72.48 evaluations applicable to Holtec at Watts Bar
  • Safe Load Path Evaluation
  • Site-Specific Tornado Missile Evaluation for the Holtec HI-STORM FW System Radiation Protection
  • Procedures for Fuel Assembly Selection
  • Radiation Protection (ALARA) Work Plan for ISFSI-Related Work Activities
  • Fuel Characterization and Verification Documents Training and Qualifications
  • Training Department Lesson Packages for ISFSI
  • Personnel Training, Certifications, and Qualification Records Corrective Action Program
  • Watts Bar ISFSI Program Audit
  • List of corrective action documents (Condition Reports, etc.) related to ISFSI issues Audits and Self-Assessments
  • QA audits for yoke, transfer cask, and any other components related to the ISFSI
  • Inspections of ISFSI Lifting Devices, including the spent fuel pool crane, sling, hooks, etc.

Information Specific for the Auxiliary Building Crane Upgrade to Single-Failure Proof:

  • Copies of all NUREG 0612 Phase I and II correspondence between the licensee and the NRC.
  • A list of any major modifications that were made to the crane after installation.
  • 10 CFR 50.59 Screenings/Evaluations which established that the Auxiliary Building Crane has been designed/modified to safely handle the heavy loads associated with the Holtec International HI-STORM FW System.

3

  • Drawings related to modifications made to the Auxiliary Building Crane.
  • Specifications related to the Auxiliary Building Crane and associated hardware (slings, hooks, etc.).
  • Procedures related to the operability of the crane, including designated safe load paths and interlocks which prevent travel over stored spent fuel assemblies.
  • Maintenance procedures of the Auxiliary Building Crane used to perform the frequent and periodic inspections as required by ASME B30.2, Sections 2-2.1.2 and 2-2.1.3, and the results from the most recent periodic inspections.
  • Compliance matrix of crane license basis requirements (if one already exists).
  • Names and contact information for the Auxiliary Building Crane Modification program leads.

B. Information requested to be provided on site for the inspectors at the Entrance Meeting (July 25, 2016)

Please provide the information requested below in hard copy or electronic (preferred) format to the lead inspector at the entrance meeting in order to finalize the planning of inspection activities onsite. Prior to the onsite inspection, the inspector will select part of the inspection samples from the information provided in response to section A of this Enclosure, and then request additional information needed to complete the review. There is a possibility that some of the inspection samples for which direct observation is desired will not be selected until the inspector arrives onsite and confirms the current schedule of activities for that week.

  • Updated schedules for ISFSI activities, including welding and NDE, if available.
  • Copies of NDE personnel qualifications
  • Welder Performance Qualifications
  • Welding Operator Performance Qualifications
  • Ready access (i.e., copies provided to the inspector to use for the duration of the inspection at the onsite inspection location, or room number and location where available) to applicable editions of the ASME Code and EPRI and industry standards referenced in the procedures used to perform the ISFSI activities.

Information Requested Specific to the Auxiliary Building Crane Upgrade Onsite Inspection Week - August 8-12

  • Original crane installation package (or crane upgrade) including the welding requirements, rated load test of the bridge (125 percent of the rated load),

inspection results after the load test, temperature at time of the load test, and vendor acceptance records for the crane. Provide additional information of most recent load test information with temperature at time of load test.

  • Copy of crane manufacturers operating manual/maintenance requirements.
  • The licensee requirements for the crane operators (physicals, training, etc.).
  • List of the condition reports written on the crane during the past two years.
  • Last inspection results of structural steel, rails, rail hold-down attachments, etc.,

which support the crane.

4

  • Manufacturers specifications for the wire rope in use on the main hoist.
  • Analysis of the building structure and the crane structure to support the crane during a design basis seismic event while a rated capacity load is suspended.

Inspector Contact Information: Mailing Address:

Robert Carrion US NRC Region II Senior Reactor Inspector Attn: Robert Carrion 404-997-4522 245 Peachtree Center Avenue NE robert.carrion@nrc.gov Suite 1200 Atlanta, GA 30303