MONTHYEARML15188A3462015-06-30030 June 2015 2014 Annual Report of Emergency Core Cooling Syetem (ECCS) Model Changes Pursuant to the Requirements of 10 CFR 50.46 Project stage: Request ML15253A2052015-09-0101 September 2015 Proposed License Amendment Request Small Break Loss of Coolant Accident Reanalysis Project stage: Request ML15253A2062015-09-0101 September 2015 ANP-3315NP, Revision 0, Millstone Unit 2 M5 Upgrade, Small Break LOCA Analysis Licensing Report. Project stage: Request ML16047A1712016-02-16016 February 2016 2016/02/16 E-mail from R.Guzman to M. Whitlock Request for Additional Information - Small Break Loss of Coolant Accident Re-Analysis (MF6700) Project stage: RAI ML16040A2152016-02-24024 February 2016 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML16096A3882016-03-24024 March 2016 Response to Request for Additional Information for Proposed License Amendment Request Regarding Small Break Loss of Coolant Accident Reanalysis Project stage: Response to RAI ML16122A0012016-04-27027 April 2016 2016/04/27 E-mail from W.Craft to R.Guzman Supplemental RAI Clarification Information - SBLOCA LAR Project stage: Supplement ML16152A1862016-05-26026 May 2016 E-mail from W. Craft to R. Guzman SBLOCA LAR - Clarification in Steam Generator Secondary Side Mass (MF6700) Project stage: Other ML16249A0012016-09-30030 September 2016 Issuance of Amendments Small Break Loss of Coolant Accident Reanalysis Project stage: Approval 2016-02-24
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML24213A2602024-07-31031 July 2024 Request for Additional Information LAR to Support Implementation of Framatome Gaia Fuel ML24116A0112024-04-25025 April 2024 Acceptance Review Determination for Proposed Alternative Request IR-4-13 Regarding Steam Generator Channel Head Drain Modification ML24115A2622024-04-24024 April 2024 Acceptance Review Determination for Proposed Alternative Request IR-4-14 Regarding Pressurizer and Steam Generator Pressure-Retaining Welds and Full-Penetration Welded Nozzles ML24114A3192024-04-23023 April 2024 Acceptance Review Determination LAR to Extend Inspection Interval for Reactor Coolant Pump Flywheels (TSTF-421) Using the CLIIP ML24113A2502024-04-22022 April 2024 Request for Additional Information (e-mail 4/22/2024) License Renewal Commitment for Aging Management Program of Alloy 600 Components ML24092A1082024-04-0101 April 2024 3R22 RFO ISI Owners Activity Report Extension - NRC Staff Acknowledgement Email (4/1/2024) ML24065A3112024-03-0505 March 2024 Request for Additional Information (Redacted) (03/05/2025 E-mail from R. Guzman to S. Sinha) Framatome Gaia Fuel LOCA LAR ML24058A2322024-02-27027 February 2024 2/27/2024 E-mail from S. Sinha to R. Guzman P-8 Instrument Uncertainty in Support of LAR Framatome Gaia Fuel ML24032A4702024-02-0101 February 2024 Change in Estimated Review Schedule Revision to TS Design Features Section to Remove the Nine Mile Point Unit 3 Nuclear Project, LLC ML24024A2452024-01-24024 January 2024 1/24/2024 E-mail from R.Guzman to S.Sinha - Acknowledgement of Error in SE for Amendment No. 288 - Revision to Applicability Term for RCS Heatup and Cooldown Pressure-Temperature Limitations Figures ML24024A0202024-01-24024 January 2024 Correction to Safety Evaluation Associated Wit Amendment No. 288 - Revision to Applicability Term for RCS Heat-Up and Cooldown Pressure-Temperature Limitations Figures ML23326A0132023-11-22022 November 2023 Acceptance Review Determination LAR to Support Implementation of Framatome Gaia Fuel ML23318A0952023-11-14014 November 2023 Request for Additional Information (E-mail Dated 11/14/2023) LAR to Revise TSs Related to Framatome Gaia Fuel ML23317A0732023-11-13013 November 2023 Acceptance Review Determination - License Amendment Request Modification of TS SR 4.3.6.a ML23297A2312023-10-24024 October 2023 E-mail to File - Summary of September 13, 2023, Meeting with Dominion to Discuss Proposed LAR to Support Cycle Reloads Using Framatome Gaia Fuel ML23265A2302023-09-22022 September 2023 Acceptance Review Determination - License Amendment Request Revision to TS Design Features Section to Remove the Nine Mile Point Unit 3 Nuclear Project, LLC ML23258A0552023-08-31031 August 2023 Setup of Online Reference Portal and Audit Plan for the NRC Staff'S Review of LAR to Use Framatome Small Break and Realistic Large Break LOCA Methodologies (08/31/2023 e-mail) ML23199A2832023-07-18018 July 2023 Request for Additional Information (E-mail Dated 7/18/2023) LAR to Revise the Pressure-Temperature Limits ML23172A0752023-06-21021 June 2023 Acceptance Review Determination LAR to Revise TSs for Reactor Core Safety Limits, Fuel Assemblies, and COLR Related to Framatome Gaia Fuel ML23171B0522023-06-20020 June 2023 NRR E-mail Capture - RAI for Review of Appendix F to DOM-NAF-2-P (Redacted) ML23145A0052023-05-25025 May 2023 Acceptance Review Determination Exemption to Use Framatome Gaia Fuel Assemblies Containing Fuel Rods Fabricated with M5 Fuel Rod Cladding ML23145A0042023-05-25025 May 2023 Acceptance Review Determination LAR to Use Framatome Small Break and Realistic Large Break LOCA Methodologies ML23115A3022023-04-24024 April 2023 4/24/2023 E-mail from R.Guzman to S.Sinha - Acknowledgement of Error in Issuance of Amendments Adoption of TSTF-359, Increase Flexibility in Mode Restraints ML23089A1882023-03-29029 March 2023 Request for Additional Information (E-mail Dated 3/29/2023) Spring 2022 Steam Generator Tube Inspection Report ML23067A2162023-03-0707 March 2023 NRR E-mail Capture - RAI for North Anna, 1 & 2, Surry 1 & 2, Millstone, 2 & 3, Request for Approval of App. F Fleet Report DOM-NAF-2-P, Qual of the Framatome ORFEO-GAIA and ORFEO-NMGRID CHF Correlations in the Dominion VIPRE-D Computer Code ML23038A0152023-02-0707 February 2023 Acceptance Review Determination LAR to Revise the Applicability Term for RCS Heatup and Cooldown Pressure-Temperature Limitations Figures ML23024A1522023-01-24024 January 2023 Acceptance Review Determination LAR to Supplement Burnup Credit of Criticality Safety Analysis ML23018A0352023-01-17017 January 2023 NRR E-mail Capture - Acceptance Review for Fleet Report Re Appendix F of DOM-NAF-2-P (L-2022-LLT-0003) ML22320A5752022-11-16016 November 2022 E-mail to File - Summary of October 18, 2022, Meeting with Dominion to Discuss Requested Actions for Implementing Framatome Gaia Fuel ML22298A2052022-10-25025 October 2022 Acceptance Review Determination for Alternative Request for Extension of Examination Interval for Reactor Pressure Vessel Head Penetration Nozzles ML22292A3212022-10-19019 October 2022 Acceptance Review Determination for Alternative Request for Containment RSS Pump Periodic Verification Testing Program ML22297A1802022-10-0707 October 2022 Email Acknowledgement to Dominion Energy Nuclear Decommissioning Trust Fund Disbursement 30 Day Notification for Millstone Power Station Unit 1: Docket No 50-245 ML22278A0932022-10-0505 October 2022 E-mail to File - Summary of September 7, 2022, Meeting with Dominion to Discuss Proposed Supplement to the Spent Fuel Pool Criticality Safety Analysis (EPID L-2022-LRM-0059 ML22272A0332022-09-29029 September 2022 Memo E-mail to File - Summary of August 29, 2022, Meeting with Dominion to Discuss Proposed Alternative Request Post-peening follow-up Volumetric Exam of RPV Head Penetration Nozzle ML22252A1772022-09-0909 September 2022 Memo E-mail to File - Summary of August 9, 2022, Meeting with Dominion to Discuss Proposed Alternative Reqeust Recirculation Spray Pump Flow Testing (EPID L:2022-LRM-0057) ML22242A0452022-08-23023 August 2022 NRR E-mail Capture - Dominion GL 04-02 Response Draft RAIs (L-2017-LRC-0000) ML22174A3552022-06-23023 June 2022 NRR E-mail Capture - Acceptance Review for Dominion Fleet LAR to Implement TSTF-554 (L-2022-LLA-0078) ML22123A0812022-05-0303 May 2022 Acceptance Review Determination for Proposed LAR for TS Change Applicable to TSTF-359, Increase Flexibility in Mode Restraints ML22069A7192022-03-10010 March 2022 E-mail from R. Guzman to S. Sinha - Millstone Unit 3 Steam Generator Outage Conference Call ML22020A4122022-01-11011 January 2022 1/11/2022 State Consultation E-mail, R. Guzman to J. Semancik Millstone Power Station, Unit 3 Planned Issuance of Amendment to Clarify Shutdown Bank TS and Add Alternate Control Rod Position Monitoring Requirements ML21348A7392021-12-14014 December 2021 E-mail - Acceptance Review Determination Alternative Request IR-4-09 for Use Alternative Brazed Joint Assessment Methodology for Class 3 Moderate Energy Piping ML21347A9412021-12-13013 December 2021 E-mail from R.Guzman to S.Sinha - Acknowledgement of Error in Safety Evaluation for Amendment No. 280 Measurement Uncertainy Recapture Power Uprate ML21334A1922021-11-30030 November 2021 NRR E-mail Capture - Audit Plan for Reactor Core Thermal-Hydraulics Using the VIPRE-D Appendix E Review ML21326A1502021-11-22022 November 2021 NRR E-mail Capture - Acceptance Review for Relocation of Unit Staff Requirements to the QAPD LAR (L-2021-LLA-0195) ML21306A3302021-11-0202 November 2021 NRR E-mail Capture - Acceptance Review for TSTF-569 LAR ML21297A0072021-10-19019 October 2021 E-mail from R. Guzman to S. Sinha - Acknowledgemnt of Error in SE for Millstone Power Station, Unit 3, Amendment No. 279 Addition of Analytical Methodology to the COLR for LBLOCA ML21286A7372021-10-13013 October 2021 Additional Element Included in the Implementation Plan for the Surry Fuel Melt Safety Limit (SL) LAR ML21223A3042021-08-11011 August 2021 Request for Withholding Information from Public Disclosure Proposed LAR to Add an Analytical Methodology to the COLR for a Large Break LOCA ML21200A2562021-07-19019 July 2021 7/19/2021 E-mail Pressurizer Steam Space Line Classification ML21195A2442021-07-13013 July 2021 NRR E-mail Capture - Draft RAI Appendix E to Topical Report DOM-NAF-2 Qualification of the Framatome BWU-I CHF Correlation in the Dominion Energy VIPRE-D Computer Code 2024-07-31
[Table view] |
Text
Guzman, Richard From: Wanda D Craft (Generation - 6) <wanda.d.craft@dom.com>
Sent: Thursday, May 26, 2016 4:50 PM To: Guzman, Richard
Subject:
[External_Sender] RE: SBLOCA LAR - SG Secondary Side Mass Issue
- Rich, The following information is provided to address your question related to Figure 414 of the LAR. If you need additional information, we can support a call next week. Thanks.
The response in Figure 4-14 is consistent with model expectations. AFW flow is stopped to both SGs at 1200 seconds. During the period from ~1200-1600 seconds, there is mass exchange from Loop 2 SG (broken) to Loop 1 SG (intact) through the main steam header. The non-return valves are not modeled, so the steam generators are not isolated. As shown in Figure 4-3, pressure is increasing in both SGs after 1200 seconds due to primary-to-secondary heat transfer. The mass exchange occurs due to small pressure differences between the SGs that is a result of the broken loop (Loop 2) having a larger energy removal rate than the intact loop (Loop 1). The pressure difference between the loops is not evident in Figure 4-3 due to the scale, but a small mass exchange is occurring. The total mass in the two SGs is constant from 1200-1600 seconds. After ~1600 seconds, the SG pressure on the broken loop is high enough to open the MSSV #1. There are three rapid openings that causes the large SG total mass reduction between 1600 and 2000 seconds.
Wanda D. Craft Nuclear Licensing and Operations Support Dominion Resources Services, Inc (804) 273-4687 tie-line 730-4687 From: Guzman, Richard [1]
Sent: Thursday, May 26, 2016 10:26 AM To: Wanda D Craft (Generation - 6)
Subject:
SBLOCA LAR - SG Secondary Side Mass Issue
- Wanda, As we discussed, please let me know when your folks can support a call to discuss:
- In Figure 4-14 of the LAR, the Loop 2 steam generator shows a mass decrease between ~1200-2000s
- During this period, AFW is off for both SGs and heat transfer should be from secondary side to primary side.
1
- Secondary side pressure during the majority of this time period is less than the MSSV min setpoint. If an MSSV were open, it would be understood where the mass is going, but since it's shut, and with both SGs essentially at the same pressure, the technical staff does not understand why the mass in one (Loop 1 SG) is increasing and the other decreasing (Loop 2 SG).
Rich Guzman Sr. Project Manager NRR/DORL US NRC 3014151030 CONFIDENTIALITY NOTICE: This electronic message contains information which may be legally confidential and or privileged and does not in any case represent a firm ENERGY COMMODITY bid or offer relating thereto which binds the sender without an additional express written confirmation to that effect. The information is intended solely for the individual or entity named above and access by anyone else is unauthorized. If you are not the intended recipient, any disclosure, copying, distribution, or use of the contents of this information is prohibited and may be unlawful. If you have received this electronic transmission in error, please reply immediately to the sender that you have received the message in error, and delete it. Thank you.