ML16148A840

From kanterella
Jump to navigation Jump to search
Insp Repts 50-269/93-29,50-270/93-29 & 50-287/93-29 on 931019-27.Violations Noted.Major Areas Inspected:Events Associated W/Component Failure Caused by Inoperability of One Emergency Power Source
ML16148A840
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 10/29/1993
From: Harmon P, Lesser M, Poertner W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML16148A839 List:
References
50-269-93-29, 50-270-93-29, 50-287-93-29, NUDOCS 9311160103
Download: ML16148A840 (5)


See also: IR 05000269/1993029

Text

R REGL1

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTA STREET, N.W., SUITE 2900

ATLANTA, GEORGIA 30323-0199

Report Nos.:

50-269/93-29, 50-270/93-29 and 50-287/93-29

Licensee:

Duke Power Company

422 South Church Street

Charlotte, NC 28242-0001

Docket Nos.: 50-269, 50-270, 50-287, 72-4

License Nos.:

DPR-38, DPR-47, DPR-55, SNM-2503

Facility Name:

Oconee Nuclear Station

Inspection Conducted: October 19 - 27, 1993

Inspector:

____t___

P. Harmon, Senior Resident Inspector

Date Signed

W. Poertner, Resident Inspector

Date Signed

Approved by:_

/

1)

/f3

M. Lesser, Section Chief

Date Signed

Projects Section 3A

Division of Reactor Projects

SUMMARY

Scope:

This special inspection was conducted to review the events

associated with a component failure which caused inoperability of

one of the emergency power sources which was initially discovered

in September, 1992.

Results:

One apparent violation was identified involving a lack of prompt

corrective action to resolve a previously identified deficiency.

A component essential to the operation of the emergency power

distribution system was found to have never been adequately

tested. Corrective action was not timely and when testing

ultimately was performed, it was discovered to have been

inoperable for an indeterminate period.

9311160103 931029

PDR ADOCK 05000269

G

PDR

REPORT DETAILS

1.

Persons Contacted

Licensee Employees

  • H. Barron, Station Manager

S. Benesole, Safety Review Manager

D. Coyle, Systems Engineering Manager

J. Davis, Safety Assurance Manager

T. Coutu, Operations Support Manager

B. Dolan, Manager, Mechanical/Nuclear Engineering

W. Foster, Superintendent, Mechanical Maintenance

  • J. Hampton, Vice President, Oconee Site

D. Hubbard, Component Engineering Manager

C. Little, Superintendent, Instrument and Electrical (I&E)

  • M. Patrick, Regulatory Compliance Manager

B. Peele, Engineering Manager

  • S. Perry, Regulatory Compliance
  • G. Rothenberger, Operations Superintendent

R. Sweigart, Work Control Superintendent

Other licensee employees contacted included technicians, operators,

mechanics, and staff engineers.

NRC Resident Inspectors

  • P. Harmon

t

Poertner

  • Attended Exit Interview

2.

Background

During accident conditions concurrent with the loss of offsite power,

the emergency power supply for Oconee Nuclear Station is the two Keowee

Hydrostation units.

The two hydroelectric generators provide the

emergency power through two separate and independent paths.

One path,

the overhead path, is a 230 kv transmission line to the Oconee station

230 kv switchyard yellow bus, which will supply each unit's startup

transformer. The other path is an underground feeder to the Oconee CT-4

transformer. The Keowee units are normally lined up with one unit

aligned to the overhead path, and the other aligned to theunderground

path.

No particular precedence is established for which Keowee unit is

aligned to which path.

Automatic start of both Keowee units occurs on a loss of the grid, an

engineered safety features actuation, or loss of vol'

tage on an Oconee

unit's main feeder bus.

On loss of offsite power, the Keowee unit

assigned to the overhead path will connect to the yellow bus after the

yellow bus has been disconnected from the grid.

When Keowee unit 2 is

aligned to the overhead path, this connection is viansa

ACB-2.

Confirmation that the yellow bus has been disconnected from the grid,

2

and is ready for connection to Keowee unit 2 is accomplished by relay

27T2X, a Westinghouse MG-6 relay. If this relay does not operate, the

ACB will not close in and the Keowee unit will not provide power to the

yellow bus.

3.

Event Description

On September 29, 1992, at approximately 10:00 p.m., technicians were in

the process of performing post-modification tests on ACB-2. When ACB-2

did not close as required, the licensee investigated and discovered that

an MG-6 relay, 27T2X, was set with an improper gap of one half inch

instead of seven sixteenths as required by the manufacturer.

Technicians found a plastic armature stop nut was broken. The relay was

repaired and the post-modification test was performed successfully.

The licensee performed a root cause investigation and determined that

the ACB-2 failure was caused by the failed MG-6 relay. The exact time

of the failure is indeterminate, and could have existed since original

installation. The MG-6 relay had not been modified, inspected or tested

since original installation.

The licensee submitted Licensee Event Report LER 269/92-14 on October

29, 1992 to document the event. The LER concluded that Keowee Unit 2

had been inoperable for an indeterminate period of time prior to

discovery during the periods when Keowee unit 2 was aligned to the

overhead path. When called upon in that configuration, Keowee Unit 2

would not have been available to supply emergency power to the Oconee

units.

As previously stated, the MG-6 relay and consequently the Keowee

overhead path were inoperable for an indeterminate period of time. The

time is indeterminate for the following two reasons:

A.

The overhead path through ACB-2 was inoperable only when Keowee

Unit 2 was aligned to the overhead path. Swapping of Keowee Units

between overhead and underground paths is done routinely.

B.

Neither the specific MG-6 relay nor the Keowee overhead path had

ever been tested according to the licensee. The relay and

consequently the overhead path could have been inoperable since

initial installation. Periodic testing of either the relay or the

overhead path would have identified the problem.

The inspectors had discussed the issue regarding the lack of direct

testing of the overhead path with the licensee prior to this event. The

licensee had acknowledged the inspectors' concern, and stated that they

were in the process of devising a test to prove that the overhead path

would work if called upon. The licensee's test, as required by T.S.

4.6.5, was limited to testing the External Grid Protection System Logic.

This test is a logic continuity test and does not directly test the

Keowee overhead function.

3

Oconee T.S. 4.6.2.a requires that the Keowee Hydro units will be started

annually using the emergency start circuits in each control room. This

is to verify that each hydro unit and associated equipment is available

to carry load within 25 seconds of a simulated requirement for

engineered safety features. The licensee conforms to this requirement

by performing PT/O/A/0620/16, Keowee Hydro Emergency Start Test. This

performance test verifies operability of the Keowee emergency start

circuitry, and demonstrates that both Keowee units can supply 25 MW of

power within 25 seconds of emergency start initiation. The test does

not verify operability of the MG-6 feature of ACB-2. The inspectors

questioned whether MG-6 is included as "associated equipment" referred.

to in T.S. 4.6.2.a. The licensee stated that they do not consider this

to be the intent of the T.S. In effect, the licensee had never tested

the actual path emergency power would have to take from Keowee to the

Oconee emergency buses via the overhead line.

The inspectors

documented their concerns in NRC Inspection Report 50-269, 270, 287/92

24 as Unresolved Item 92-24-01.

The inspectors determined that in January, 1991, the licensee completed

a Design Baseline Determination (DBD) on the Keowee Emergency Power

System. The published results included a Test Acceptance Criteria (TAC)

which listed the specific test requirements necessary to provide

assurance of operability of the system. The TAC includes specific

requirements to test the overhead path, and to test the ACB-1 and ACB-2

breaker functions. The licensee performed some preliminary work on

devising tests to satisfy the TAC requirements, but had not fully

developed the tests when the failure was discovered on September 29,

1992.

The Code of Federal Regulations, 10 CFR 50, Appendix B, Criterion XI

requires that a program be established to assure that all testing

required to demonstrate that structures, systems and components will

perform satisfactorily in service is identified and performed.

The Code of Federal Regulations, 10 CFR 50, Appendix B, Criterion XVI,

Corrective Action, requires that measures shall be established to assure

that conditions adverse to quality are promptly identified and

corrected. In the instance described above, the licensee had identified

deficiencies in the test program relative to full functional testing of

the emergency power path. However, corrective actions were not pursued

in a timely manner to devise and perform the required tests.

Specifically the test inadequacy was discovered in January 1991 and

corrective action was not implemented until September 1992, some 20

months later. Prompt corrective action to devise and perform the

required tests would have identified that the overhead emergency power

path was inoperable prior to the discovery date. This apparent

violation is being considered for escalated enforcement action, 50-269,

270, 287/93-27-01: Untimely Corrective Action for Test Program

Inadequacy Causes Keowee Unit 2 Inoperability for Indeterminate Time.

4

4.

Exit Interview

The inspection scope and findings were summarized on October 27, 1993,

with those persons indicated in Paragraph 1. The inspectors described

the areas inspected and discussed in detail the inspection finding. The

licensee did not identify as proprietary any of the material provided to

or reviewed by the inspectors during this inspection nor did they

provide any dissenting comments.

Item Number

Description/Reference Paragraph

50-269,270,287/93-29-01

(Apparent Violation) Untimely Corrective

Action for Test Program Inadequacy Causes

Keowee Unit 2 Inoperability for

Indeterminate Time (paragraph 3).