Notification of Initial Shipping Window for Shipment of Areva MkB-HTP-1 15x15 Fuel Assemblies from the Crystal River 3 to the Oconee Power Plant
ML16099A141
Person / Time
Site: Oconee, Crystal River  Duke Energy icon.png
Issue date: 04/06/2016
From: Travis Tate
AREVA
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards, Office of Nuclear Reactor Regulation
References
TAC L25086, TJT:16:014
Download: ML16099A141 (1)


Text

April 6, 2016 T JT:16:014 US Nuclear Regulatory Commission Director, Division of Spent Fuel Mgmt.

Office of Nuclear Material Safety and Safeguards Attn: Document Control Desk 11555 Rockville Pike One White Flint North Rockville, MD 20852 Gentlemen:

A AREVA

Subject:

Notification of Initial Shipping Window for Shipment of AREVA MkB-HTP-1 15x15 Fuel Assemblies from the Crystal River 3 to the Oconee Power Plant Ref.1.

Letter, S. Ruffin (USN RC) to T J Tate (AREVA Inc.); Authorization for Shipment of the Model No. 51032-2 Package from Crystal River 3 to Oconee Nuclear Power Plant; TAC No. L25086; March 2, 2016.

The referenced NRC correspondence conveys the NRC's authorization to ship AREVA MkB-HTP-1 15x15 PWR fuel assemblies of 4.55 and 4.95 wt.% U-235 enrichments from the Crystal River 3 to the Oconee Nuclear Power Plant under special conditions prescribed therein. One of those conditions requires that AREVA provide the NRC with at least ninety (90) days pre-notification prior to the initiation of either of the two four-month windows over which the fuel shipments will be made. The purpose of this correspondence is to inform the NRC that the first of the two four-month shipping windows will commence ninety (90) days from the date of this letter, i.e. July 5, 2016. All shipments will be made in accordance with the conditions set forth in the NRC's referenced letter of authorization. If you have questions, please feel free to contact me at 509-375-8550.

Very truly yours, T. J. Tate, Manager Environmental, Health, Safety, & Licensing

/mah AREVA INC.

2101 Horn Rapids Road, Richland WA 99354 Tei.: 509 375 81 00 - www.areva.com

April 6, 2016 T JT:16:014 US Nuclear Regulatory Commission Director, Division of Spent Fuel Mgmt.

Office of Nuclear Material Safety and Safeguards Attn: Document Control Desk 11555 Rockville Pike One White Flint North Rockville, MD 20852 Gentlemen:

A AREVA

Subject:

Notification of Initial Shipping Window for Shipment of AREVA MkB-HTP-1 15x15 Fuel Assemblies from the Crystal River 3 to the Oconee Power Plant Ref.1.

Letter, S. Ruffin (USN RC) to T J Tate (AREVA Inc.); Authorization for Shipment of the Model No. 51032-2 Package from Crystal River 3 to Oconee Nuclear Power Plant; TAC No. L25086; March 2, 2016.

The referenced NRC correspondence conveys the NRC's authorization to ship AREVA MkB-HTP-1 15x15 PWR fuel assemblies of 4.55 and 4.95 wt.% U-235 enrichments from the Crystal River 3 to the Oconee Nuclear Power Plant under special conditions prescribed therein. One of those conditions requires that AREVA provide the NRC with at least ninety (90) days pre-notification prior to the initiation of either of the two four-month windows over which the fuel shipments will be made. The purpose of this correspondence is to inform the NRC that the first of the two four-month shipping windows will commence ninety (90) days from the date of this letter, i.e. July 5, 2016. All shipments will be made in accordance with the conditions set forth in the NRC's referenced letter of authorization. If you have questions, please feel free to contact me at 509-375-8550.

Very truly yours, T. J. Tate, Manager Environmental, Health, Safety, & Licensing

/mah AREVA INC.

2101 Horn Rapids Road, Richland WA 99354 Tei.: 509 375 81 00 - www.areva.com