10 CFR 50.90 A member of the STARS (Strategic Teaming and Resource Sharing) Alliance Callaway
- Diablo Canyon
- Palo Verde
- Wolf Creek 102-07202-TNW/DCE February 26, 2016 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Sirs:
Subject:
Palo Verde Nuclear Generating Station (PVNGS)
Units 1, 2, and 3 Docket Nos. STN 50-528, 50-529, and 50-530 License Nos. NPF-41, NPF-51 and NPF-74 Response to Regulatory Issue Summary (RIS) 2015-16, Planned Licensing Action Submittals for All Power Reactor Licensees, Revision 1 Regulatory Issue Summary (RIS) 2015-16, Revision 1, Planned Licensing Action Submittals for All Power Reactor Licensees, dated January 15, 2016, requested licensees to provide information regarding the licensing actions that are planned to be submitted to the NRC staff for review over the next 2 calendar years and power uprate applications planned over the next 5 years. The requested information is strictly voluntary. The NRC staff plans to use the information in allocating its resources for licensing reviews.
Arizona Public Service Company (APS) supports the objective of the RIS in promoting early communication with the NRC staff regarding planned licensing activities. Enclosure 1 of this letter provides estimated licensing actions over the next 2 calendar years for the Palo Verde Nuclear Generating Station (PVNGS) Units 1, 2 and 3 and Enclosure 2 of this letter provides estimated power uprate licensing actions over the next 5 calendar years.
APS requests that the contents of Enclosure 2 be withheld from public disclosure, pursuant to 10 CFR 2.390. The NRC has waived the affidavit requirements on its own initiative as documented in the RIS, since the response to the survey contains business-sensitive information, the disclosure of which is likely to cause competitive harm and should, therefore, be classified as proprietary information.
The enclosures reflect the current target dates for the APS submittals. These target dates are subject to change. Also, operational considerations may result in the addition of licensing actions that are not currently itemized in the enclosures.
A copy of this letter and enclosures is being provided to Tracy Orf, Division of Operating Reactor Licensing, Technical Assistant.
Palo Verde Nuclear Generating Station 5801 S. Wintersburg Road Tonopah, AZ 85354 contains PROPRIETARY information to be withheld under 10 CFR 2.390 of this document contains SUNSI information. The transmittal document is decontrolled when Enclosure 2 is detatched.
102-07202-TNW/DCE ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Response to RIS 2015-16, Revision 1 Page 2 No commitments are being made to the NRC by this letter. Should you need further information regarding this submittal, please contact Michael Dilorenzo, Licensing Section Leader, at (623) 393-3495.
Sincerely, Thomas N. Weber Nuclear Regulatory Affairs Department Leader TNW/DCE
- Table of Estimated Licensing Actions for PVNGS Units 1, 2 and 3 - Table of Estimated Power Uprate Licensing Actions for PVNGS Units 1, 2 and 3 cc:
M. L. Dapas NRC Region IV Regional Administrator M. M. Watford NRC NRR Project Manager for PVNGS L. J. Klos NRC NRR Project Manager C. A. Peabody NRC Senior Resident Inspector for PVNGS T. Orf NRC Technical Assistant, Division of Operating Reactor Licensing Weber, Thomas N(Z00499)
Digitally signed by Weber, Thomas N(Z00499)
DN: cn=Weber, Thomas N(Z00499)
Reason: I am approving this document Date: 2016.02.26 18:31:31 -07'00' Elkinton, Delbert C(Z34657)
Digitally signed by Elkinton, Delbert C(Z34657)
DN: cn=Elkinton, Delbert C(Z34657)
Reason: By Direction Date: 2016.03.02 09:59:53 -07'00'
Table of Estimated Licensing Actions for PVNGS Units 1, 2 and 3
Palo Verde Nuclear Generating Station (PVNGS) Units 1, 2, and 3; Dockets 50-528, 50-529. and 50-530 Enclosure 1 Table of Estimated Licensing Actions for PVNGS Units 1, 2 and 3 Plant Name and Unit Number(s)
Licensing Action Type
[Please select from drop list]
- Number, if any Licensing Action Description/Title Proposed Submittal Date MM/YYYY (for items expected to be submitted within 1 year) and YYYY ( for items expected to be submitted beyond the second year)
Proposed Submittal Date (Quarter/Calendar Year) (if precise date is not available)
[Please select from drop list]
Outage Related?
(Yes or No)
[Please select from drop list]
Outage Related Date (MM/DD/Y YYY)
Can the NRC staff make the information public? (Yes or No)
[Please select from drop list]
Comments (include any associated contingencies)
Proprietary Information (Yes or No)
[Please select from drop list]
PVNGS 1, 2, 3 License Amendment Revise TS 3.3.7 Degraded Voltage Relay Time Delay Setting Apr-16 (02) April - June 2016 No Yes Regulatory Commitment No PVNGS 1, 2, 3 License Amendment 523 Adopt TSTF-523, Generic Letter 2008-01, Managing Gas Accumulation Jun-16 (02) April - June 2016 No Yes Regulatory Commitment No PVNGS 1, 2, 3 License Amendment Revise TSs to permit use of Next Generation Fuel Jun-16 (02) April - June 2016 Yes Yes Exact Outage Date TBD in October 2018 No PVNGS 1, 2, 3 Exemptions Exemption to 10 CFR 50.46 per 10 CFR 50.12 to permit use of Next Generation Fuel Jun-16 (02) April - June 2016 Yes Yes Exact Outage Date TBD in October 2018 No PVNGS 1, 2, 3 License Amendment 426 Adopt TSTF-426: Revise or Add Actions to Preclude Entry into LCO 3.0.3 Nov-16 (04) Oct - Dec 2016 No Yes No PVNGS 1, 2, 3 License Amendment 493 Adopt TSTF-493: Implement in TS for as-found and as-left set-points per TSTF-493, Clarify Application of Setpoint Methodology for Limiting Safety System Settings 2017 (05) Jan - March 2017 No Yes Regulatory Commitment No PVNGS 1, 2, 3 Relief Request Submit 4th Interval ASME Section XI Inservice Inspection (ISI) Relief Requests 2017 (05) Jan - March 2017 No Yes 3rd ISI intervals expire in 2018 No PVNGS 1, 2, 3 License Amendment Adopt 10 CFR 50.69, Risk-informed categorization and treatment of structures, systems and components for nuclear power reactors 2017 (07) July - Sept 2017 No Yes No PVNGS 1, 2, 3 License Amendment 545 Adopt TSTF-545: TS Inservice Testing (IST) Program Removal 2017 (07) July - Sept 2017 No Yes No PVNGS 1, 2, 3 License Amendment Revise TS 5.5.16 to adopt integrated leak rate testing (Type A Test) 15 year interval permanently 2017 (08) Oct - Dec 2017 No Yes Next ILRT in 2025 No
10 CFR 50.90 A member of the STARS (Strategic Teaming and Resource Sharing) Alliance Callaway
- Diablo Canyon
- Palo Verde
- Wolf Creek 102-07202-TNW/DCE February 26, 2016 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Sirs:
Subject:
Palo Verde Nuclear Generating Station (PVNGS)
Units 1, 2, and 3 Docket Nos. STN 50-528, 50-529, and 50-530 License Nos. NPF-41, NPF-51 and NPF-74 Response to Regulatory Issue Summary (RIS) 2015-16, Planned Licensing Action Submittals for All Power Reactor Licensees, Revision 1 Regulatory Issue Summary (RIS) 2015-16, Revision 1, Planned Licensing Action Submittals for All Power Reactor Licensees, dated January 15, 2016, requested licensees to provide information regarding the licensing actions that are planned to be submitted to the NRC staff for review over the next 2 calendar years and power uprate applications planned over the next 5 years. The requested information is strictly voluntary. The NRC staff plans to use the information in allocating its resources for licensing reviews.
Arizona Public Service Company (APS) supports the objective of the RIS in promoting early communication with the NRC staff regarding planned licensing activities. Enclosure 1 of this letter provides estimated licensing actions over the next 2 calendar years for the Palo Verde Nuclear Generating Station (PVNGS) Units 1, 2 and 3 and Enclosure 2 of this letter provides estimated power uprate licensing actions over the next 5 calendar years.
APS requests that the contents of Enclosure 2 be withheld from public disclosure, pursuant to 10 CFR 2.390. The NRC has waived the affidavit requirements on its own initiative as documented in the RIS, since the response to the survey contains business-sensitive information, the disclosure of which is likely to cause competitive harm and should, therefore, be classified as proprietary information.
The enclosures reflect the current target dates for the APS submittals. These target dates are subject to change. Also, operational considerations may result in the addition of licensing actions that are not currently itemized in the enclosures.
A copy of this letter and enclosures is being provided to Tracy Orf, Division of Operating Reactor Licensing, Technical Assistant.
Palo Verde Nuclear Generating Station 5801 S. Wintersburg Road Tonopah, AZ 85354 contains PROPRIETARY information to be withheld under 10 CFR 2.390 of this document contains SUNSI information. The transmittal document is decontrolled when Enclosure 2 is detatched.
102-07202-TNW/DCE ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Response to RIS 2015-16, Revision 1 Page 2 No commitments are being made to the NRC by this letter. Should you need further information regarding this submittal, please contact Michael Dilorenzo, Licensing Section Leader, at (623) 393-3495.
Sincerely, Thomas N. Weber Nuclear Regulatory Affairs Department Leader TNW/DCE
- Table of Estimated Licensing Actions for PVNGS Units 1, 2 and 3 - Table of Estimated Power Uprate Licensing Actions for PVNGS Units 1, 2 and 3 cc:
M. L. Dapas NRC Region IV Regional Administrator M. M. Watford NRC NRR Project Manager for PVNGS L. J. Klos NRC NRR Project Manager C. A. Peabody NRC Senior Resident Inspector for PVNGS T. Orf NRC Technical Assistant, Division of Operating Reactor Licensing Weber, Thomas N(Z00499)
Digitally signed by Weber, Thomas N(Z00499)
DN: cn=Weber, Thomas N(Z00499)
Reason: I am approving this document Date: 2016.02.26 18:31:31 -07'00' Elkinton, Delbert C(Z34657)
Digitally signed by Elkinton, Delbert C(Z34657)
DN: cn=Elkinton, Delbert C(Z34657)
Reason: By Direction Date: 2016.03.02 09:59:53 -07'00'
Table of Estimated Licensing Actions for PVNGS Units 1, 2 and 3
Palo Verde Nuclear Generating Station (PVNGS) Units 1, 2, and 3; Dockets 50-528, 50-529. and 50-530 Enclosure 1 Table of Estimated Licensing Actions for PVNGS Units 1, 2 and 3 Plant Name and Unit Number(s)
Licensing Action Type
[Please select from drop list]
- Number, if any Licensing Action Description/Title Proposed Submittal Date MM/YYYY (for items expected to be submitted within 1 year) and YYYY ( for items expected to be submitted beyond the second year)
Proposed Submittal Date (Quarter/Calendar Year) (if precise date is not available)
[Please select from drop list]
Outage Related?
(Yes or No)
[Please select from drop list]
Outage Related Date (MM/DD/Y YYY)
Can the NRC staff make the information public? (Yes or No)
[Please select from drop list]
Comments (include any associated contingencies)
Proprietary Information (Yes or No)
[Please select from drop list]
PVNGS 1, 2, 3 License Amendment Revise TS 3.3.7 Degraded Voltage Relay Time Delay Setting Apr-16 (02) April - June 2016 No Yes Regulatory Commitment No PVNGS 1, 2, 3 License Amendment 523 Adopt TSTF-523, Generic Letter 2008-01, Managing Gas Accumulation Jun-16 (02) April - June 2016 No Yes Regulatory Commitment No PVNGS 1, 2, 3 License Amendment Revise TSs to permit use of Next Generation Fuel Jun-16 (02) April - June 2016 Yes Yes Exact Outage Date TBD in October 2018 No PVNGS 1, 2, 3 Exemptions Exemption to 10 CFR 50.46 per 10 CFR 50.12 to permit use of Next Generation Fuel Jun-16 (02) April - June 2016 Yes Yes Exact Outage Date TBD in October 2018 No PVNGS 1, 2, 3 License Amendment 426 Adopt TSTF-426: Revise or Add Actions to Preclude Entry into LCO 3.0.3 Nov-16 (04) Oct - Dec 2016 No Yes No PVNGS 1, 2, 3 License Amendment 493 Adopt TSTF-493: Implement in TS for as-found and as-left set-points per TSTF-493, Clarify Application of Setpoint Methodology for Limiting Safety System Settings 2017 (05) Jan - March 2017 No Yes Regulatory Commitment No PVNGS 1, 2, 3 Relief Request Submit 4th Interval ASME Section XI Inservice Inspection (ISI) Relief Requests 2017 (05) Jan - March 2017 No Yes 3rd ISI intervals expire in 2018 No PVNGS 1, 2, 3 License Amendment Adopt 10 CFR 50.69, Risk-informed categorization and treatment of structures, systems and components for nuclear power reactors 2017 (07) July - Sept 2017 No Yes No PVNGS 1, 2, 3 License Amendment 545 Adopt TSTF-545: TS Inservice Testing (IST) Program Removal 2017 (07) July - Sept 2017 No Yes No PVNGS 1, 2, 3 License Amendment Revise TS 5.5.16 to adopt integrated leak rate testing (Type A Test) 15 year interval permanently 2017 (08) Oct - Dec 2017 No Yes Next ILRT in 2025 No