Other: 0CAN011602, Entergy Update to the Communication Submittals Associated with Near-Term Task Force Recommendation 9.3, 0CAN081601, Revision to Update to the Communication Submittals Associated with Near-Term Task Force Recommendation 9.3, 1CAN041601, Response to PRA RAI 19, Adoption of National Fire Protection Association Standard NFPA-805, 1CAN051602, Update to Tables S-1 and S-2 - Adoption of National Fire Protection Association Standard NFPA-805, 1CAN081605, General Updates, Adoption of National Fire Protection Association Standard NFPA-805
|
MONTHYEAR1CAN051501, Response to Request for Additional Information Adoption of National Fire Protection Association Standard NFPA-8052015-05-19019 May 2015 Response to Request for Additional Information Adoption of National Fire Protection Association Standard NFPA-805 Project stage: Response to RAI 1CAN071501, Arkansas, Unit 1 - 90-Day Response to Request for Additional Information Adoption of National Fire Protection Association Standard NFPA-8052015-07-21021 July 2015 Arkansas, Unit 1 - 90-Day Response to Request for Additional Information Adoption of National Fire Protection Association Standard NFPA-805 Project stage: Response to RAI 1CAN081501, 120-Day Response to Request for Additional Information Adoption of National Fire Protection Association Standard NFPA-8052015-08-12012 August 2015 120-Day Response to Request for Additional Information Adoption of National Fire Protection Association Standard NFPA-805 Project stage: Response to RAI 1CAN091501, Round 2 Response to Request for Additional Information, Adoption of National Fire Protection Association Standard NFPA-8052015-09-22022 September 2015 Round 2 Response to Request for Additional Information, Adoption of National Fire Protection Association Standard NFPA-805 Project stage: Response to RAI 0CAN011602, Entergy Update to the Communication Submittals Associated with Near-Term Task Force Recommendation 9.32016-01-12012 January 2016 Entergy Update to the Communication Submittals Associated with Near-Term Task Force Recommendation 9.3 Project stage: Other 0CAN011604, Notification of Readiness of 95003 Supplemental Inspection Arkansas Nuclear One - Units 1 and 22016-01-15015 January 2016 Notification of Readiness of 95003 Supplemental Inspection Arkansas Nuclear One - Units 1 and 2 Project stage: Request 1CAN011601, Response to Round 3 Request for Additional Information, Adoption of National Fire Protection Association Standard NFPA-8052016-01-15015 January 2016 Response to Round 3 Request for Additional Information, Adoption of National Fire Protection Association Standard NFPA-805 Project stage: Request 1CAN041601, Response to PRA RAI 19, Adoption of National Fire Protection Association Standard NFPA-8052016-04-0707 April 2016 Response to PRA RAI 19, Adoption of National Fire Protection Association Standard NFPA-805 Project stage: Other 0CAN051605, Registration of Cask Use2016-05-19019 May 2016 Registration of Cask Use Project stage: Request 1CAN051602, Update to Tables S-1 and S-2 - Adoption of National Fire Protection Association Standard NFPA-8052016-05-19019 May 2016 Update to Tables S-1 and S-2 - Adoption of National Fire Protection Association Standard NFPA-805 Project stage: Other 0CAN081601, Revision to Update to the Communication Submittals Associated with Near-Term Task Force Recommendation 9.32016-08-0404 August 2016 Revision to Update to the Communication Submittals Associated with Near-Term Task Force Recommendation 9.3 Project stage: Other 1CAN081605, General Updates, Adoption of National Fire Protection Association Standard NFPA-8052016-08-29029 August 2016 General Updates, Adoption of National Fire Protection Association Standard NFPA-805 Project stage: Other 2CAN101601, License Amendment Request to Revise the National Fire Protection Association (NFPA) Standard 805 Modifications2016-10-27027 October 2016 License Amendment Request to Revise the National Fire Protection Association (NFPA) Standard 805 Modifications Project stage: Request ML16334A3822016-11-22022 November 2016 NRR E-mail Capture - ANO-2 Acceptance Review of License Amendment Request to Revise the National Fire Protection Association (NFPA) Standard 805 Modifications Project stage: Acceptance Review ML16333A3072016-11-29029 November 2016 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment Request to Revise National Fire Protection Association Standard 805 Modifications Project stage: Acceptance Review ML16348A4212016-12-21021 December 2016 Acceptance of Requested Licensing Action License Amendment Request to Revise the National Fore Protection Association Standard 805 Modifications Project stage: Acceptance Review ML17033A2892017-02-0202 February 2017 NRR E-mail Capture - Arkansas Nuclear One Unit 2 - Final Request for Additional Information Concerning License Amendment Request to Revise Certain NFPA 805 Modifications Project stage: RAI ML17096A2352017-05-12012 May 2017 Issuance of Amendment No. 306 Request to Revise the National Fire Protection Association (NFPA) Standard 805 Modifications Project stage: Approval 2016-11-22
[Table View] |
Text
Enteigy Entergy Operations, inc.
Russeilville, AR 72802 Tel 479-858-3110 Jeremy G. Browning Site Vice President Arkansas Nuclear One OCANO1 1604 January 15, 2016 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk 11555 Rockville Pike Rockville, MD 20852
SUBJECT:
Notification of Readiness of 95003 Supplemental Inspection Arkansas Nuclear One Units 1 and 2 Docket Nos. 50-313 and 50-368 License Nos. DPR-51 and NPF-6
REFERENCE:
Mid-Cycle Assessment Letter for Arkansas Nuclear One, Units 1 and 2 (Report 050000313/2015005 and 050000368/2015005, dated September 1,2015 (0CNA091505) (ML15243A553)
Dear Sir or Madam:
This letter serves as notification of Arkansas Nuclear Ones (ANO) readiness for your office to perform a 95003 supplemental inspection. The site is also prepared to support the 95001 supplemental inspection for the ANO-2 white performance indicator and the 95002 supplemental inspections for the stator and flooding yellow findings.
ANOs readiness for the inspection was discussed with Mr. Neil OKeefe, Region IV Branch Chief. ANO is ready to support the 95003 inspection scheduled to begin on January 25, 2016.
This letter contains no new commitments.
If you have any questions or require additional information, please contact Stephenie Pyle at 479.858.4704.
Sincerely, J?jv JGB/nbm ADAMS ACCESSION NO. ML16019A047
OCANO1 1604 Page 2of2 cc:
Mr. Marc L. Dapas Regional Administrator U. S. Nuclear Reguator Commission, Region IV 1600 East Lamar Boulevard Arlington, TX 76011-4511 NRC Senior Resident Inspector Arkansas Nuclear One P.O. Box 310 London, AR 72847 U. S. Nuclear Regulatory Commission Attn: Ms. Andrea E. George MS O-8B1 One White Flint North 11555 Rockville Pike Rockville, MD 20852 ADAMS ACCESSION NO. ML16019A047
Enteigy Entergy Operations, inc.
Russeilville, AR 72802 Tel 479-858-3110 Jeremy G. Browning Site Vice President Arkansas Nuclear One OCANO1 1604 January 15, 2016 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk 11555 Rockville Pike Rockville, MD 20852
SUBJECT:
Notification of Readiness of 95003 Supplemental Inspection Arkansas Nuclear One Units 1 and 2 Docket Nos. 50-313 and 50-368 License Nos. DPR-51 and NPF-6
REFERENCE:
Mid-Cycle Assessment Letter for Arkansas Nuclear One, Units 1 and 2 (Report 050000313/2015005 and 050000368/2015005, dated September 1,2015 (0CNA091505) (ML15243A553)
Dear Sir or Madam:
This letter serves as notification of Arkansas Nuclear Ones (ANO) readiness for your office to perform a 95003 supplemental inspection. The site is also prepared to support the 95001 supplemental inspection for the ANO-2 white performance indicator and the 95002 supplemental inspections for the stator and flooding yellow findings.
ANOs readiness for the inspection was discussed with Mr. Neil OKeefe, Region IV Branch Chief. ANO is ready to support the 95003 inspection scheduled to begin on January 25, 2016.
This letter contains no new commitments.
If you have any questions or require additional information, please contact Stephenie Pyle at 479.858.4704.
Sincerely, J?jv JGB/nbm ADAMS ACCESSION NO. ML16019A047
OCANO1 1604 Page 2of2 cc:
Mr. Marc L. Dapas Regional Administrator U. S. Nuclear Reguator Commission, Region IV 1600 East Lamar Boulevard Arlington, TX 76011-4511 NRC Senior Resident Inspector Arkansas Nuclear One P.O. Box 310 London, AR 72847 U. S. Nuclear Regulatory Commission Attn: Ms. Andrea E. George MS O-8B1 One White Flint North 11555 Rockville Pike Rockville, MD 20852 ADAMS ACCESSION NO. ML16019A047