UNITED STATES NUCLEAR REGULATORY* COMMISSION WASHINGTON, D.C. 20555-0001 February 5, 2016 MEMORANDUM TO: Michael T. Markley, Chief Plant Licensing Branch 11-1 FROM:
SUBJECT:
Division of Operating Reactor Licensing
, Office of Nuclear Reactor Regulation &
G. Edward Miller, Project Manager Plant Licensing Branch 11-1 l;
Division of Operating Reactor Licensing
~
Office of Nuclear Reactor Regulation
SUMMARY
OF DECEMBER 8, 2015, PUBLIC MEETING REGARDING LICENSE AMENDMENT REQUEST TO IMPLEMENT RISK-INFORMED TECHNICAL SPECIFICATION COMPLETION TIMES On December 8, 2015, the U.S. Nuclear Regulatory Commission (NRC) staff held a public meeting 1 with staff from Southern Nuclear Company (SNC or the licensee). The purpose of the meeting was to discuss SNC's license amendment request to implement risk-informed Technical Specification Completion Times for the Vogtle Electric Generating Plant. Specifically, the discussion was focused on a draft request for additional information (RAI) that was provided to SNC on November 3, 2015. 2 During the meeting, SNC presented slides3 that provided an overview of how they planned to respond to the NRC staff's information request. During the discussion, a few wording clarifications were identified:
RAI 1.b.i, it was identified that the word modeled should be evaluated.
o Note, subsequent to the meeting and upon further consideration, the NRC staff determined that the word "modeled" was properly used, however, an additional sentence was added to indicated that the NRC staff information need was a list of those items not modeled and the evaluation of why this was acceptable; RAl 1.c, it was identified that the term "design basis accident initiator" was more appropriate than "design basis accident"; and RAl 1.c, the NRC staff indicated that it would further consider whether Loss of Offsite Power coincident with a Loss of Coolant Acciqent would be considered a design basis accident initiator.
1 The original meeting notice is available via the Agencywide Documents Access and Management System (ADAMS) under Accession No. Ml 15331A084.
2 The draft RAI is available under ADAMS Accession No. ML15313A547.
3 The licensee's slides are available under ADAMS Accession No. ML15230A594.
No regulatory decisions were made and both the NRC staff and the licensee indicated that they would consider the items discussed in the meeting.
Following the discussion, an opportunity was afforded to any other participants who wished to ask questions or make comments. One question was received regarding parallels between the RICT process and a notice of enforcement discretion.
CONTACT: G. Edward Miller, NRR/DORULPL2-1
. 301-415-2481
Enclosure:
List of Attendees
Sign In Sheet DATE: Dec 8, 2015 Name Ed Miller Robert Elliott David Gennardo Stephen Dinsmore Stacey Rosenberq Norbert Carte George Wilson Michael Markley Margaret Chernoff Steven Arndt Joseph Giitter Margaret Watford Audrey Klett Perry Buckberg Ken McElroy Chuck Pierce Erin Anners Anees Farruk Justin Wheat Faramarz Pournia Dan Churchman George Gunn Public Meeting with Southern Nuclear Company Re: Vogtle RICT LAR Organization NRC NRC NRC NRC NRC NRC NRC NRC NRC NRC NRC NRC NRC NRC SNC SNC SNC SNC SNC SNC SNC SNC
ML15364A448 ICE DORL/LPL2-1/PM DORL/LPL2-1/LA DRA/APLA NAME GEMiller DATE 02/03/16 SFigueora SRosenberg*
SDinsmore for 02/03/16
UNITED STATES NUCLEAR REGULATORY* COMMISSION WASHINGTON, D.C. 20555-0001 February 5, 2016 MEMORANDUM TO: Michael T. Markley, Chief Plant Licensing Branch 11-1 FROM:
SUBJECT:
Division of Operating Reactor Licensing
, Office of Nuclear Reactor Regulation &
G. Edward Miller, Project Manager Plant Licensing Branch 11-1 l;
Division of Operating Reactor Licensing
~
Office of Nuclear Reactor Regulation
SUMMARY
OF DECEMBER 8, 2015, PUBLIC MEETING REGARDING LICENSE AMENDMENT REQUEST TO IMPLEMENT RISK-INFORMED TECHNICAL SPECIFICATION COMPLETION TIMES On December 8, 2015, the U.S. Nuclear Regulatory Commission (NRC) staff held a public meeting 1 with staff from Southern Nuclear Company (SNC or the licensee). The purpose of the meeting was to discuss SNC's license amendment request to implement risk-informed Technical Specification Completion Times for the Vogtle Electric Generating Plant. Specifically, the discussion was focused on a draft request for additional information (RAI) that was provided to SNC on November 3, 2015. 2 During the meeting, SNC presented slides3 that provided an overview of how they planned to respond to the NRC staff's information request. During the discussion, a few wording clarifications were identified:
RAI 1.b.i, it was identified that the word modeled should be evaluated.
o Note, subsequent to the meeting and upon further consideration, the NRC staff determined that the word "modeled" was properly used, however, an additional sentence was added to indicated that the NRC staff information need was a list of those items not modeled and the evaluation of why this was acceptable; RAl 1.c, it was identified that the term "design basis accident initiator" was more appropriate than "design basis accident"; and RAl 1.c, the NRC staff indicated that it would further consider whether Loss of Offsite Power coincident with a Loss of Coolant Acciqent would be considered a design basis accident initiator.
1 The original meeting notice is available via the Agencywide Documents Access and Management System (ADAMS) under Accession No. Ml 15331A084.
2 The draft RAI is available under ADAMS Accession No. ML15313A547.
3 The licensee's slides are available under ADAMS Accession No. ML15230A594.
No regulatory decisions were made and both the NRC staff and the licensee indicated that they would consider the items discussed in the meeting.
Following the discussion, an opportunity was afforded to any other participants who wished to ask questions or make comments. One question was received regarding parallels between the RICT process and a notice of enforcement discretion.
CONTACT: G. Edward Miller, NRR/DORULPL2-1
. 301-415-2481
Enclosure:
List of Attendees
Sign In Sheet DATE: Dec 8, 2015 Name Ed Miller Robert Elliott David Gennardo Stephen Dinsmore Stacey Rosenberq Norbert Carte George Wilson Michael Markley Margaret Chernoff Steven Arndt Joseph Giitter Margaret Watford Audrey Klett Perry Buckberg Ken McElroy Chuck Pierce Erin Anners Anees Farruk Justin Wheat Faramarz Pournia Dan Churchman George Gunn Public Meeting with Southern Nuclear Company Re: Vogtle RICT LAR Organization NRC NRC NRC NRC NRC NRC NRC NRC NRC NRC NRC NRC NRC NRC SNC SNC SNC SNC SNC SNC SNC SNC
ML15364A448 ICE DORL/LPL2-1/PM DORL/LPL2-1/LA DRA/APLA NAME GEMiller DATE 02/03/16 SFigueora SRosenberg*
SDinsmore for 02/03/16